回填土施工专项方案(定稿)(10页).doc
下载文档
上传人:正***
编号:504967
2022-08-01
10页
111.50KB
1、中国银行信息中心(上海)项目一期工程回填土施工专项方案中国银行信息中心(上海)项目一期工程回填土施工专项方案目 录一、工程概况- 2 -1、工程概况- 2 -2、回填土概述- 2 -3、编制依据- 3 -4、施工说明- 3 -二、回填土施工进度计划- 4 -1、1号楼动力区回填土施工进度计划- 4 -2、1号楼灾备中心回填土施工进度计划- 4 -3、2号楼办公楼回填土施工进度计划- 4 -4、2号楼研发楼回填土施工进度计划- 4 -三、工程回填土实物量和劳动力配备- 5 -1、回填土实物量- 5 -2、回填土劳动力配备- 6 -四、回填土施工方案- 6 -1、施工流程- 6 -2、主要施工机械2、选用和配备- 7 -3、回填土施工部位与要求- 7 -4、施工方法- 7 -五、质量保证措施- 9 -六、安全技术措施和文明施工措施- 9 -中国银行信息中心(上海)项目一期工程回填土施工专项方案一、工程概况1、工程概况中国银行信息中心(上海)项目位于上海浦东新区张江高科技园区银行卡产业园2-2、2-4地块,总用地面积约101149.4平方米,呈折尺型,其中一期工程建设用地约56016平方米,二期约45133平方米。一期建筑群体由1#楼、2#楼和3#楼组成。其中1#楼分为动力区和灾备中心,建筑面积35815m2,4层结构;2#楼分为办公楼和研发楼,建筑面积21725m2,7层结构;3#楼分为综3、合楼和宿舍楼,建筑面积13886m2,7层结构。各楼号均为两栋独立单体。本工程基地东面为城市主干道华东路,南侧为上丰路,西面靠中横港,北侧为张家浜,并与规一路、规二路相邻。基地地势平坦。本工程基础设计形式为独立承台加桩基,2#楼部分为筏板基础加桩基。桩型为400400预制混凝土方桩和PHC管桩。基础埋置深度1#楼约为2.30米;2#楼办公楼约为5.60米,研发楼约为2.1米;3#楼综合楼约为5.50米,宿舍楼约为2.555.90米。本工程基础轴线1#楼1-11-12轴、1-A1-L轴,东西向长107米,南北向长90米;2#楼2-12-16轴、2-A2-L轴,东西向长120米,南北向长90米;34、#楼3-13-11轴、3-A3-H轴,东西向长90米,南北向长62.05米。2、回填土概述按照设计图纸,本工程1号楼动力区、灾备中心和2号楼办公楼、研发楼有回填土施工内容,回填土内容为:1号楼: 动力区: 范围为基础结构井字地梁、承台内外回填土。 灾备中心:范围为基础结构井字地梁、承台内外回填土。2号楼: 办公楼: 在地下室墙外范围回填土。 研发楼: 范围为基础结构井字地梁、承台内外回填土。3、编制依据1、 合同及招投标文件2、 业主提供的工程建筑和结构施工图3、 国家及上海市现行建筑设计、施工、安装、验收规范及有关文件。4、 本公司企业标准等有关文件5、 建筑工程质量验收统一标准(GB5035、00-2001)6、 建筑工程项目管理规范(GB/T50326-2001)7、 地基与基础工程施工质量验收规范(GB50202-2002)8、 混凝土结构工程施工及验收规范(GB50204-2002)4、施工说明本工程回填土施工,按照施工进度计划安排,主要分春节前和春节中两个施工阶段。春节后,正常进行主体结构施工等内容。春节前,回填土主要局限于1号楼动力区、灾备中心部分南侧区域和2号楼研发楼,其中研发楼已于先期完成回填土施工。春节中,主要为2号楼办公楼和1号楼的基础内回填土。春节后,1号楼部分有基础内的回填土施工内容。但不影响关键施工流程和节点。二、回填土施工进度计划1、1号楼动力区回填土施工6、进度计划2、1号楼灾备中心回填土施工进度计划3、2号楼办公楼回填土施工进度计划4、2号楼研发楼回填土施工进度计划三、工程回填土实物量和劳动力配备1、回填土实物量序部位数量备注1动力区基础内、外4300m32灾备中心基础内、外8325m33办公楼墙外11500m34研发楼基础内、外3200m3先期完成2、回填土劳动力配备序部位劳动力数量机械或人力备注1动力区墙外5人/天反铲挖土机墙内30人/天人力2灾备中心墙外10人/天反铲挖土机墙内30人/天人力3办公楼5人/天反铲挖土机4研发楼10人/天反铲挖土机先期完成四、回填土施工方案1、施工流程1号楼动力区:定位、标高引测基础挖土、护坡基础结构施工一框7、主体结构施工一框拆模结构脚手架拆除回填土(内外同时进行)第二次脚手架基础及搭设下道各工序施工1号楼灾备中心:定位、标高引测基础挖土、护坡基础结构施工一框主体结构施工一框拆模结构脚手架拆除回填土(内外同时进行)第二次脚手架基础及搭设(至二框)二框结构施工以上各层结构施工2号楼办公楼:定位、标高引测井点降水基坑挖土、护坡基础底板施工B1层基础结构施工外墙拆模外墙防水层、保护层等B1层外墙脚手架拆除回填土(仅限于墙外)上部结构脚手搭设一框主体结构施工以上各框结构施工2号楼研发楼:定位、标高引测基础挖土、护坡基础结构施工回填土砌地垄、挡墙等一层结构施工(-0.10米)二层结构第一次临时脚手架搭设二层结8、构施工(4.40米)二层结构第一次临时脚手架拆除主体结构脚手架基础二三层脚手架搭设三层主体结构施工(8.90米)以上各层结构施工2、主要施工机械选用和配备1号楼和2号楼回填土由二期堆放土区域驳运至各楼基坑部位,采用机械和人力回填。在二期堆放土区域布置一二台反铲挖土机,用于配备的土方车装土,回填土各楼部位,另行布置反铲挖土机用于回填。动力区、灾备中心等基础内的回填土,由人力回填,配备人力车驳运。3、回填土施工部位与要求(1) 1号楼动力区1.65米(局部-0.30米)标高下至结构基底,在基础内外作回填土,回填土标高按照设计要求为-0.10米。(2) 1号楼灾备中心1.60米(局部-1.30米等)9、标高下至结构基底,在基础内外作回填土,回填土标高按照设计要求为-0.10米。(3) 2号楼办公楼基础结构(B1层)完成后,外墙拆模,防水层及保护层施工后,作回填土,回填标高为-0.10米。(4) 2号楼研发楼按照总施工流程安排,基础结构施工后,在基础内外作回填土,回填土按-0.10米结构楼板各部位标高控制。4、施工方法(1) 本工程各楼号按照回填土施工流程和施工进度计划安排机械和配备劳动力进行回填土施工。(2) 为使墙内回填土施工正常展开,动力区、灾备中心在墙外回填时,在施工口部分别留设人力运送土通道,做成斜坡,使手推车能从墙外送入墙内。(3) 土方车倾倒回填土时,应随卸随由人力车运走,送入墙10、内回填,使现场保持整洁、通畅的状态。(4) 动力区回填土由基础内外同时进行施工。周边直接用反铲挖土机回填,楼内基底由人力驳运土回填,由西侧进入,由东向西退出。(5) 灾备中心回填土体积大,面积区域大,采用南、北二组同时进行回填施工,楼内基底人力驳运由中间向南、北向退。(6) 办公楼墙外回填土,按照取土方向,由西向东展开,全部采用反铲挖土机回填。(7) 研发楼回填土在基础施工完成后,采用反铲挖土机回填,人工扦平。(8) 二期用地临时堆场无道路处和场地内回填土非道路区域采用铺设走道板的方法,以使土方车顺利驳运。(9) 上述土方回填前,应清除基底的垃圾、建筑材料等,并按照设计和规范要求,做好回填前的11、各项前道工序施工和验收工序,达到施工验收合格后,再安排回填土施工。(10) 各种管道必须在回填前埋设,做好检查、验收和必要的工种和工序交接。(11) 回填土料应选用开挖原状土,不得回填建筑垃圾和有机杂物。(12) 回填土过程中,应检查每层填筑厚度、含水量控制、压实程度。填筑厚度、压实遍数根据土质、压实系数及所用机具确定。(13) 填土施工后,检查标高、压实程度或边坡坡度。(14) 回填按要求分层夯实,做好环刀试验和取样、送样。(15) 部分后续进行的动力区、灾备中心墙内回填土,当外墙脚手架已搭设时,在外脚手上,按标准方式留设过人孔。五、质量保证措施1、 回填土施工,按工程质量保证措施,落实现场12、质量管理制度和严格质量责任制。2、 回填土施工前,由项目部按照技术质量要求,认真做好技术交底和质量交底,并做好书面记录。3、 用于回填土的机械操作人员应有专业工种上岗证书,遵照专业工程操作上岗要求,达到施工质量标准。4、 严格执行施工操作规程,工艺流程和施工工艺,以工序控制,做好每一环节的施工质量。5、 加强工种配合、协调工作,特别是回填土施工过程中,注意做好已完成产品的成品保护,不得随意损坏完工产品。6、 操作人员接受和贯彻技术质量交底,检查施工机具和施工前的各项准备工作。7、 认真学习本工种的施工技术,作业须提高质量意识、技术水平,精心施工。8、 依据见证取样和送样规定,做好环刀试验,及时13、取样、送样。六、安全技术措施和文明施工措施1、 积极参加文明施工活动,保持环境整洁和落手清工作。施工便道、回填土出入口随时安排专人,做好保洁工作。2、 机械作业的操作人员必须经过专业培训考试合格,并取得操作证或特殊工种操作证后,方可上岗。3、 机械作业时,操作人员不得擅自离开工作岗位或将机械交给非本机操作人员操作,严禁无关人员进入作业区和操作室内。作业时,思想要集中,严禁酒后操作。4、 组织班组安全活动,开好班前安全生产会,合理安排和分配回填施工。5、 作业前,对所使用的机具、设备、防护用品及作业环境进行安全检查,发现问题,及时采用整改措施,清除安全隐患。6、 认真进行安全技术交底,执行本工程14、安全操作规程。7、 自觉遵守工地的劳动纪律,听从指挥、服从分配,提高安全意识和安全操作要求。8、 维护安全设施,爱护安全标志,不违章作业。9、 回填土人工平整夯实作业,应在机械旋转臂范围之外进行。10、 基坑回填时,施工现场应栏出警戒线,以防机械伤人。11、 土方车不得靠近基坑平行行驶,防止坍方翻车。12、 下雨期间进行回填时,车辆行走的施工道路,设草包或麻袋,防止污染物品和污染场外环境。Opinions and suggestions on the partys mass line educational practiceAccording to the central and provin15、cial, municipal unified deployment, according to municipal Party committee about carrying out the partys mass line educational practice activity in the citys implementation opinions, the spirit of the partys mass line educational practice activities from 20* in January to 99 months, carried out at a16、ll levels of departments and directly affiliated institutions and grass-roots party organizations. According to my actual County, the county to carry out the education practice put forward the following implementation opinions.First, the overall requirementsCounty county education practice to the ei17、ghteen Party of eight, the spirit of the the third Plenary Session of the 18th CPC Central Committee as the guidance, conscientiously implement the spirit of general secretary Xi Jinping book series of important speech, earnestly implement the Central Committee really, opinions and advice , party im18、plementing the guiding ideology of opinions to determine the objectives and requirements, step method, in accordance with the look in the mirror, dress up, wash bath, cure treatment, the general requirements of for the people pragmatic honest people as the theme, in carrying forward the spirit of Zh19、uanglang Zhuang, improve their work style, service to the masses of the people, the foundation of consolidating grassroots, promote transformation across efforts, to further implement the central eight regulations and The opposition party and government austerity waste regulations , double section p20、rovincial regulations, municipal provisions of the twelve plan and the implementation measures for on improving the work style of close ties with the masses law, highlight style building, carry out the whole wind spirit, resolutely oppose formalism, bureaucracy, hedonism and wasteful extravagance to21、 solve the problems, Party members and cadres of the style and the masses of people strong, the Ministry of Party members and cadres to further improve their thinking and understanding, to further change the style of the wind, the masses to close, honest and pragmatic people honest image to further 22、establish the foundation to further reinforce the basic level. Style of the building of the new results to promote the construction of a powerful force of the county and the ecological culture of the county and county construction.In educational practice activities of the unit is mainly: the county 23、and below county departments under the organs, enterprises and institutions directly under the township, street, and community, village, non-public economic organizations, social organizations and other grass-roots organizations. Agencies and branches, each single unit, follow the rules on internal 24、institutions. Educational practice with step by step.To adhere to the county leadership, leadership and leading cadres to focus on outstanding catch to directly contact the service of the masses of law supervision departments and window units, service industry, educational practice, pay attention to25、 grasp the heavy towns, streets and villages, community education activities and the masses of grassroots groups in close contact to strengthen, and the majority of Party members, cadres and the mass line line Marx doctrine view of the masses and the partys education.Always speak seriously as a basi26、c attitude, adhere to positive education, to carry out criticism and self criticism group, adhere to the pragmatic, more emphasis on leadership, pay more attention to the layers of the demonstration, more focus on the four winds, solve the problem, pay more attention to open the door, the participat27、ion of the masses, pay more attention to the classification guidance. Orderly, pay more attention to the cooperation and cohesion driven, more strict requirements on injection, really supervision practice, ensure education practice is not empty is not empty is not partial, not as a mere formality.Tw28、o, the key point of the taskThe main task of the countys education practice is to seize against four wind this focus on centralized solve outstanding problems asked County, township leadership and leading cadres of the four winds, the disadvantages of the style, scale behavior to a large scale inves29、tigation, overhaul, cleaning greatly. At the same time, respond to the concerns of the masses, safeguard the interests of the masses, pay attention to solve practical problems, solve the people around the unwholesome tendencies especially on eat, take the card, Yong lazy luxury, extravagance and was30、te fees, privileges and other issues, timely and effective, without any discount to solve, to improve the style of real implementation of the requirements of real to the grassroots, real let group Benefit the public.(a) focus on solving the four winds outstanding issuesThe central and provincial req31、uirements, the county leadership and leading cadres of key performance concept is not correct, do not dare to play, to engage in image project, political project, a leadership guide, a set of ideas, orders and prohibitions, and a policy, there are countermeasures county. The units directly under the32、 heavy focus on solving Yung lazy drag, buck passing skin, work is not implemented, the service is not active. The dynamic problem of law enforcement and supervision departments and window units, service industry mainly solve the door hard, ugly face, something difficult, and arbitrary charges, fine33、s, levies, and breach of privilege, chinakayao, not the problem of law. The township, street The collar of leading bodies and leading cadres to solve key does nottheir own conditions to develop the correct road, the maximum to avoid investment risk, gain profit.(three) vigorously promote the brand. 34、To establish brand awareness, awareness of the use of brand, brand value, brand acquisition performance, enhance the competitive strength. Concentrated manpower, careful planning, packaging and publicity of a number of unique, market influence and coverage of the brand, the implementation of key bre35、akthroughs, to enhance the competitive strength, walking business road the competition of alienation and characteristics, the pursuit of stability and development of the market.(four) to promote the integration of resources. To further broaden their horizons, effective integration of resources withi36、n the group, the city resources, other industries and regional resources, mutual trust, mutual benefit, seeking win-win principle, in the framework of national policies and regulations, strict inspection and argumentation, legal consultation, examination and approval procedures, strict regulation of37、 economic activities, attract injection the social investment to the industry group, to achieve leveraging the development, ensure that the value of state-owned assets.(five) to strengthen the construction management personnel. Strengthen the management of education and training of cadres and worker38、s of the existing business, firmly establish the concept of the market, enhance the sense of crisis to adapt to market competition, the sense of urgency, improve the ability to respond to market competition, improve management and operation of the market. At the same time, according to the need of i39、ndustrial development, vigorously the introduction of high-quality management management personnel, and strive to build a high-quality professional management team, hard work, and promote the entire workforce knowledge structure, age structure, structure optimization and upgrading ability, enhance c40、ore competitiveness, adapt to the need of market competition.(six) seriously study the policy for policy. Serious research about social support the development of cultural undertakings in the country and the XX policy, especially the policy of industrial development, financial investment policy, financial policy and tax policy, and actively seek policy, projects and funds, enterprise and industry group mission to promote leapfrog development.第 - 9 - 页 共 10 页