1、99m高建筑项目施工电梯通道及护头棚脚手架方案技术交底1.外用电梯设计概况本工程2#楼共34层,建筑总高度99.00m,最高点高度为103.80m,计划安装1部SCD200/200,安装总高度为108m,从第三层开始每三层一道锚固。外用施工电梯计划在2013年3月投入使用。主体结构防护脚手架采用悬挑脚手架。外用电梯与结构之间须通过搭设外双排落地脚手架形成通道和防护面,脚手架基础落于电梯基础之上,与结构窗口之间刚性拉结,步距0.9m,在每层防护门处步距1.8米,排距0.6m,立杆间距1.5m(详立面图),外架与主体结构之间的距离为200mm,外架与施工电梯笼之间的距离为50mm,通往每个楼层的木2、脚手板板下均满挂大眼锦纶网做水平网。外用电梯内笼距主体结构900mm。2.施工准备2.1技术准备该脚手架属于高大架子,因此要求相关人员,不仅要熟悉图纸,还要熟悉方案。施工前管理人员要认真阅读施工方案及相关安全、质量规范,熟悉要进行的分项工程及所用的人、机、料、施工工艺、安全、质量等施工重难点,做到重点突出、心中有数。单项工程施工前,对操作人员进行安全、工艺、标准、措施等内容的培训交底,要求施工人员要严格按照方案实施。2.2材料准备2.2.1脚手架立杆、拉杆及钢管搭设脚手架时尽量选用长的整根钢管。要求所用材料其质量应符合碳素结构钢(GB/T700)中的相应规定,钢管外涂刷防锈漆,禁止使用有明显开3、焊、变形、裂纹和严重锈蚀的钢管。2.3.2扣件扣件有十字扣件、旋转扣件、对接扣件,应使用与钢管管径相配和、符合我国现行标准的可锻铸铁扣件,其材质应符合现行国家标准钢管脚手架扣件(GB15831)的规定,严禁使用加工不合格、锈蚀和有裂纹扣件。扣件与钢管的贴合面必须整形,保证与钢管扣紧时接触良好,扣件活动部位应能灵活转动。2.3.3脚手板木脚手板应使用厚度不小于50mm,长为4m,宽不少于250mm的落叶松板,其材质应符合现行国家标准木结构设计规范(GB500052003)二级材质的规定。木脚手板使用前为防止破裂损坏,在距跳板两端8cm处用8#铅丝紧箍两道并钉固。禁止使用有扭纹、破裂的木板。2.34、.4安全网大眼锦纶网做平网,密目网做立网,安全网必须使用经中国建筑一局集团认证厂家的产品。3.施工安排及施工方法3.1脚手架搭设3.1.1脚手架体系设置结构与外用电梯之间采用外双排落地钢管脚手架体系搭建。选用483.25mm钢管(钢管钢材采用Q235),脚手架搭设自裙楼顶板上外用电梯基础表面开始,搭设高度为屋面高度以上三米(最高102m)。立杆的横距b=0.6米,立杆的纵距l=1.5米(详立面图),立杆的步距h=0.9米,在防护门处步距h=1.8米,每层入口处脚手板下按间距500mm布置加强钢管,纵横杆伸出立杆端部的长度大于100mm,扫地杆距地200mm,所有立杆下铺设通长脚手板,落地通长立5、杆均采用单立杆。施工过程中应严格按方案控制步距。护头棚搭设长度为8.5米,宽度与外双排落地钢管脚手架一致,高度为3.8米。荷载取值:施工均布荷载标准值:3kN/m2。脚手架体系及外用电梯基础均坐落于裙楼顶板上,在裙楼顶板外用电梯基础部位用钢管搭设满堂脚手架进行回顶,以保证基础承载力满足要求。裙楼顶板可自排水,不设置排水设施,但雨雪后应派专人检查是否有积水,及时采取措施。通道脚手架平面图、立面图、剖面图: 施工电梯与脚手架及护头棚平面关系图 外双排落地脚手架立面图外双排脚手架侧立面图(裙楼顶板下支撑搭设方法等事宜见2#楼地下室满堂架搭设方案)每层入口处加强处理3.1.2与结构刚性拉结与剪力墙刚性6、连接方式一与剪力墙刚性连接方式二3.1.3剪刀撑设要求超高脚手架两侧按构造要求设置通长连续剪刀撑,剪刀撑设置角度4560度。3.1.4防护设置脚手架下方四周全部封闭,设置通道和双层护头棚,并挂警示牌。非轿箱行使范围满挂安全防护网,通行范围满铺脚手板,并固定牢固。防护门做法护头棚侧立面图护头棚前后立面图护头棚尺寸可根据现场实际情况做适量调整,但具体搭设方式不能改变。3.2施工要求3.2.1.脚手架搭设人员必须是经过按现行国家标准特种作业人员安全技术考核管理细则(GB 5036)考核合格的专业架子工。上岗人员应定期体检,合格者方可持证上岗。 3.2.2.搭设脚手架人员必须戴安全帽、系安全带、穿防滑7、鞋。 3.2.3.脚手架的构配件质量与搭设质量,应按规范规定进行检查验收,合格后方准使用。 3.2.4.作业层上的施工荷载应符合设计要求,不得超载。不得将模板支架、缆风绳、泵送混凝土的输送管等固定在脚手架上;严禁悬挂超重设备。 3.2.5.当有六级及六级以上大风和雾、雨、雪天气时应停止脚手架搭设与拆除作业。雨、雪后上架作业应有防滑措施,并应扫除积雪。 3.2.6.脚手架的安全检查与维护,应按规范规定进行。安全网应按有关规定搭设与拆除。 3.2.7.在脚手架使用期间,严禁拆除下列杆件:主节点处的纵、横向水平杆,纵横向扫地杆。 .脚手架外侧应有防止坠物伤人的防护措施。 .工地临时用电线路的架设及脚8、手架接地、避雷措施等,应按现行行业标准施工现场临时用电安全技术规范(JGJ46)的有关规定执行。3.2.10.每层进料口安装可向内开启的安全防护门,防护门采用钢筋焊接,防护门在非使用情况下处于关闭状态。3.2.11.扣件安装时扣件螺栓拧紧要适当,扭力矩控制在4050Nm,且不应大于65 Nm。扣件的开口要使螺栓向上为原则,避免滑扣。.其余要求详见脚手架施工方案4.通道及护头棚脚手架拆除1、拆除脚手架,地面应设围栏和警戒标志,并派专人负责警戒,严禁非操作人员入内。2、拆除脚手架前,应将脚手架上的留存材料、杂物等清除干净。3、脚手架拆除顺序一般为脚手板(木脚手板)栏杆剪刀撑牵杆横杆立杆,按自上而下9、先装者后拆,后装者先拆,逐步拆除,一步一清,不得采用踏步式拆法,不准上下同时作业。剪刀撑拆除,应先拆中间扣,再拆两头扣,由中间操作人往下递杆子。4、拆下的杆件与扣件,应按类分堆(扣件装入容器内),用吊车吊下,严禁高空抛掷。5、拆下的杆件和零配件运到地面时,应随时按品种、分规格堆放整齐,妥善保管。有损坏者给予维修和保养。(1)拆除脚手架前的准备工作应符合下列规定: 1、应全面检查脚手架的扣件连接、连墙件、支撑体系等是否符合构造要求; 2、应根据检查结果补充完善施工组织设计中的拆除顺序和措施,经主管部门批准后方可实施;3、 应由单位工程负责人进行拆除安全技术交底;4、应清除脚手架上杂物及地面障碍物10、。(2)拆除作业时应符合下列规定:拆除作业必须由上而下逐层进行,严禁上下同时作业。(3)当脚手架拆至下部最后一根长立杆的高度(约6.5m)时,应先在适当位置搭设临时抛撑加固后,再拆除连墙件。(4)当脚手架采取分段、分立面拆除时,对不拆除的脚手架两端,应按规定设置连墙件和横向斜撑加固。(5)卸料时各配件严禁抛掷至地面,运至地面的构配件应按规范规 定及时检查、整修与保养,并按品种、规格随时码堆存放(6)每道剪刀撑跨越立杆的根数宜在57根之间,每道剪刀撑的宽度不应小于4跨,且不小于6m,斜杆与地面的倾角宜在4560之间,由底至顶连续设置。(7)剪刀撑斜杆应在旋转扣件固定在与之相交的横向水平杆的伸出端11、(或立杆上),旋转扣件中心线距主节点的距离不应大于15cm。剪刀撑接长采用搭接接长,搭接长度不小于80cm,用3个扣件等距布置,扣件扣在钢管端头处不小于10cm处剪刀撑下端一定要落底。(英文版 ) easily blame, to prevent the broken window effect. Supervise the leading cadres to play an exemplary role, take the lead in the strict implementation of the and , lead to safeguard the solemnity and au12、thority of the party discipline, ensure that the party discipline and the laws and regulations for implementation in place. Throughout the discipline in the daily supervision and management, strengthen supervision and inspection, from the thorough investigation of violations of discipline behavior. 13、Strengthen to key areas, key departments and key projects as well as the masses reflect the concentration of the units and departments for supervision. - strengthening supervision, discipline inspection and supervision of cadres to set an example for compliance with the and is a man must be hexyl, b14、lacksmith needs its own hardware. Discipline inspection organs as the executor of the party discipline, and supervisor of the defenders, for its supervision must be more strictly, discipline inspection and supervision of cadres to firmly establish the awareness of Party Constitution, sense of discip15、line and rules consciousness, politics loyalty, sense obey. Action speak Ji Ordinance to set an example of the regulations of the rule of law, strengthen supervision and accept the supervision of the firmness and consciousness, do comply with and . To firmly establish the discipline must first be di16、sciplined, the supervisor will be subject to the supervision of concept, and consciously safeguard and implement party compasses party, take the lead in practicing three strict real strict, so loyal, clean, play. To be good at learning, the Constitution and the as morality, politics and brought to f17、ruition; to implement , do not want to, dare not, not with disciplinary ruler to supervision; to discipline a ruler, often the control inspection, and consciously in the ideological red line to draw the row Ming Good accumulation is indeed the bottom line, so that the heart has fear, said to have qu18、it, the line has ended. Attached: indifferent to heart, calmly to the table in our life, there are many unpredictable things will happen, some good, some bad things, we cannot control is powerless to stop, but with time, you will find in life sometimes turns out to be not good, some bad things final19、ly turned out to be a good thing, but then we muddy however did not know, this is the life teach us things. 1, life can be complex, can also be simple. Want simple life of precipitation, to have enough time to reflect, to make Become more perfect. Life is the most important thing is not to win, but 20、the struggle; not to have conquered, but to have fought well. 2, the plain is the background of life. Live a plain life, give up on themselves is not a coward, but the wise answers; not disillusioned after the heart, such as ashes, but experience the storm after the enlightenment; not unrewarding pe21、rfunctorily, but calm attitude of life of unrestrained self-confidence. Plain living, there is no noise noisy, no earthly troubles, more did not fill in the discontent of desire, some just a calm, a calm. 3, memory of heart will not good things to erase the, life is a When no movie, pain is a beginn22、ing, the struggle is a kind of process, death is a kind of ending. Give up this giving up is the helpless, do not give up the abandoned, do not give up this giving up is ignorance, do not give up should not give up is persistent. 4, a thing figured is heaven, think impassability is hell. Since the l23、iving, to live better. Sometimes we because of too narrow-minded, too care around the chores and penny wise and pound foolish, not worth the candle. Some things to attract trouble and worry, completely depends on how we look at and deal with it. Dont always take everything back to things, and dont g24、et into a blind alley, dont want to face, dont be narrow-minded. Poke to care, is a kind of open-minded, a free and easy. 5, I am not afraid of others behind me a knife, I afraid to look back and see stab me, is my intention to treat people; I am not afraid of the truth to tell the best friend, Im a25、fraid he turned to it as a joke to tell dont 6, when we are in a positive frame of mind, you will find many good things; and when we are in a negative state of mind, you will find many depressed things; life happy and worry, all is you of life attitude, optimistic, good luck; loss of sink, Eritrea c26、ompany. When you are in adversity, may wish to change a point of view to think everything over to the good Think, because good mentality decided the fate of the! 7, people are tired, rest; heart tired, calm. Grow up, mature, this society read. Tired and sad, squat down, to their a hug. Because the w27、orld no one can sympathize with you, have mercy on you. You cry, tears is your own; you pain, no one can understand. Then you only tears to smile. 8, each people have youth,Each youth are a story, the life of the world never gets easier, I want what, wish the world all know, as has been the same; no28、w want anything, for fear that others know, or like to lose the same. 9, the heart move, everything in the world is followed by birth, Rangrang, important thing is often the most difficult to open ones mouth, because words will reduce its importance; to let strangers people care about your life in t29、he good things, the original is not easy 10, do not blame, do not laugh at who, also dont envy who. Like a person is a kind of feeling, not like a person is true. The truth is easy to explain, I feel Is unspeakable. The best travel life is that you in a strange place found a long lost touched. 11, h30、appy life not in the bustling in, and in the peace of mind; no matter how many grievances, how uncomfortable, and ultimately to heal themselves or their own, others may got you to comfort, but never know your heart is how wanjianchuanxin. 12, maam, like a movie, learn to appreciate, learn to be grat31、eful, learn tolerance, and goodness, helping others. Instead of accusing the society, as into one; and an exception is better to give than to what 13, dont envy him A sum of, dont lose your life and the life, respectively is: the former is a we experienced cannot escape in a day finally will last mi32、nute, while the latter is our persistent, we want to cherish the memory of those people and things. 14, learn to smile, learn to strong, the world you know so many people, so many people and you are, you cannot change also cant let everyone like you, so also do not want to do. Life is too short to g33、o crazy to love to go to waste, to chase the dream to regret. 15, when temper, a blessing to go. A wounding elegant people, the key is to control their own emotions. With the mouth is the most stupid behavior. A control negative emotions than a can take a city more powerful water flow slow, language34、 is expensive. People spent two years of time to learn to speak, but to spend a few years time to shut up. That is a kind of ability, that is a kind of wisdom. 16, life is not perfect, sometimes, growth is not a cry, not an eyeful of tears, there is no trace of emotion, there is no gleam of hope, no35、 desire, no action, no static, there is only one kind of downward sinking feeling, sink A murky? 6? 7? 6? 7 sink? 6? 7? 6? 7 toward the bottom of the sink. 17, in some way, do not go, you will not know the other side scenery is beautiful. To you is not good, you do not mind too much, no one has an o36、bligation to you; you learn knowledge, is you have weapons, you can start from scratch, but not unarmed; how do you treat people, does not represent how others treat you, if cannot see through this point, only inviting worry. 18, time is like a sponge in the water, as long as you are willing to sque37、eze, the total water is still there. Every life, after the ups and downs The best test of live, to life, survival and continuation, do not stop the struggle in the joys and sorrows of life on the road, so that different soul to bear life beat, acceptance of suffering. 19, indifferent to heart, calml38、y in table, elegant and comfortable life, do not take what is so important. The pursuit will be disappointed; to be alive, you will have trouble. Life is the most afraid of what all want to care about, but also what all grasp is not firm, without scenery, separated populations, such as not to desire39、, all docked in the fate of the end. Why is too rigid, the natural, to go stay not to live, let go of obsession, revel is 20, if the fate of the broken Hopes of sailing, please dont despair, the coast is still, if the fate of the withered petals of the beautiful, please do not sink, the spring is st40、ill, life will always be endless trouble, please dont helpless, because they are still alive, is still a dream, the sun still, we still. Lost, keep memories; to get, must work to; but the most important is good to cherish their own. 21, life, select the complex, is to choose the pain; choose a simpl41、e, is choose to be happy. The complex world like aSignificance of pride. Hope is the ornate palace, outside people admiring the magnificent, living in the deep knowledge of living it to pay the price. Simple world as a simple log cabin outside ridiculed shabby, the heart is willing to go live to kno42、w the joy. Suffering and joy is their own choice. 22, learn how to use a single powerful heart, let the past be the past, let the future come. Life is really the end of the end of an eagle is flying wings, life is constantly pursuit. Dont miss to regret, dont wait for old just miss. Time to return, 43、seize every moment, again painstakingly again tired also Those struggling to fly. 23, life could not Yimapingchuan, even flat pavement, inevitably there will be a few pieces of roadblocks. Some of the rocks around the past, while others have to move it out. Just move others put the stone is very eas44、y, because the stone from the appearance we can discern; difficult to myself to move away the heart of stone head. Leave time to spend with her, often reflect my heart, so as to remove your heart of stone. 24, everything does not have to be demanding, come to, everything does not have to care about,45、 over the past; failing to do not frown, laugh it laugh. Results Dont demand, do to; life is a simple, calm and peaceful. Always not to choose their own path and regret, life is like a train, the scenery and then the United States will retreat, the passage of time and encounter will eventually drift46、ing further and further away, before is always himself. 25, everyone has a weakness, weakness is true humanity. That has no weakness, a shallow person. That people think there is no weakness, mostly false. Life has shortcomings, there are shortcomings is the real life. That no one regret, or childis47、h or numbness or Self deception. It is in tolerance of weakness and so on to accept, people live happily.Hello, everyone! I am a party member. The title of my speech is: study and implement the partys two laws, doing practical play highway. 2015 October 18, the Central Committee of the Communist Par48、ty of China promulgated the implementation of the and Chinese Communist Party discipline and punishment regulations. We Heyuan male passers-by to respond positively to the call of the Central Committee of the party, earnestly organize the study party two regulations, truly grasp the essence and gist49、, and in their respective positions, to hold the bottom line of the discipline, build a strong ideological line of defense, with the courage to play, the courage to fight tough and fearless spirit, at the crucial moment well to complete the task, with practical action to test the study and implement50、 effect Because of discipline in the * * * * * * * * * * * story. Here, let me to cast a brick to attract jade, speak about our highway. Highway line section of the road surface transformation project, last year towards the country seized will be seized one of the items. To complete this arduous tas51、k, as a project management office director Comrade, keep in mind from the Communist Party membership, recognize and identify the bottom line, strict management, and strict adherence to the quality of the project. He not only set an example, honesty and self-discipline, but also requires the manageme52、nt of all the members of the O.K., do not eat the construction unit one meal, do not accept the construction unit a ceremony. In this way, they didnt really dare to adhere to the principle. No comrade, constantly put on reworking an emergency meeting to Comrade Zhen to speak louder, management tube 53、too strict. Remember in Dongguan Street, 400 meters long cement concrete surface layer, because of various reasons, the smoothness of the poor in the bottom cavity, covering film traces and car imprinting quality problems, * * * inquiries, immediately rushed to the scene to understand and verify the54、 situation, the convening of the management office, the construction units, supervision units, construction units, construction units construction time is tight, the economic loss and other reasons to intercede * unmoved. He said, now a popular word, to the discipline and rules quite in front, there55、 are no rules Radius, you construction team not accordance with the technical specifications, quality problems, it must be to carry out rectification. Engineering quality responsibility be weightier than Mount Tai, if we manage to this matterPavement quality quantity are placed the matter, we this t56、ime to learn two regulations have what use? Still what is the Communist Party? Finally, in his insisted, the road after rework, to solve these problems. In the construction of the new comrades and the project all the colleagues efforts, after four months of fighting, the project the main project was57、 finally completed and passed inspection. Thousands of miles of ice, thousands of miles Piao, this is a splendid and romantic scene. But snow for the highway, it is a disaster, a serious threat to the traffic safety. This year, a month, a century of cold wave swept from North to south, and the snow 58、blowing to Guangdong, but also to bear the blow To * * * * the highway. In January on the evening of 23, Lianping county city temperatures dropped to minus 2 degrees, a wide range of sudden rain sleet, before and after the provincial S341 line in Jiulianshan Mountain tunnel sections of the road appe59、ared in the snow, lead to the passing vehicles skid, traffic is blocked. In the face of the sudden natural disasters, city and county highway department immediately launched the emergency plan for disaster prevention. As the front line of the main force, Lianping Highway Bureau of all Party members 60、and cadres to remember the Party member responsibility, braving the biting cold wind, the first time rushed to the scene, on the icy pavement of salt disposal. Because the temperature is too low, just melt water immediately freezes, addition to the ice work to increase the difficulty. To ensure In a61、ddition to the re organization of the depths of the traffic safety, road people braved the icy put reflective cones and warning signs, endure cold at minus 2,3 of Jiulianshan patrols until one in the morning. Just before dawn, Lianping Highway Bureau personnel on the icy road salt ice melting proces62、sing until ten oclock, ice melting ice success, the road gradually returned to normal traffic. In the cold winter night, which people do not miss the warm bed, which people do not miss the warm home. However, our highway on the road to the owners of the masses can go home early, the night fighting t63、o secure the avoidance of the road safety and smoothness, fulfill their responsibility. Xi General Secretary Every Party member cadre cautioned against said: blacksmith needs self hard . two regulations , is our own hard standard test, more exercise every party members and cadres of the fire. We sho64、uld continue to strengthen the party two regulations, conscientiously in practical work, practical play road, the road for the development of the cause of Heyuan and struggle.In the industry domain report the situation of road traffic in recent years, in the province highway departments of the conce65、rn and support, our bureau management department based on the job, loyalty duty, best service, to further promote the highway management standardization, legal, scientific and information technology to improve the management level and service quality. This will be my last work is as follows: first, 66、around the center, go all out to greet the seizure in 2015, meet national examination is my bureau work. As the highway management department, we focus on the work of the center to strengthen road renovation and management as the focal point, further optimize the service environment, improve service67、 levels. Inspection, the inspection group and the Ministry of transport, the Bureau under the leadership of the ministries and agencies highly evaluated and fully affirmed. (a) increase road area remediation efforts. The programme of work, strengthen the organization and leadership. The timely devel68、opment of the city of , along the road signs and markings, traffic safety facilities, on both sides of the green, advertising signs, control area illegal construction and implementation of remediation tasks to the relevant departments, clear work time of the node to ensure rectification work timely.69、 Set up road area special rectification work leading group, implement a bureau, the Bureau of the county (District), the project road site domain environment comprehensive improvement Mechanism. To ensure that the work carried out smoothly, the bureau also organized the city road managers participat70、ed in the regulation of road region and the relevant laws and regulations of the special training. 2. Active butt joint is reported, actively strive for the support of. Local Party committee and government support is the jobAs a magic weapon, I am one of the Bureau of the principal leaders repeatedl71、y attack inspection remediation and road area to the principal leaders of the municipal report. * * *, the Secretary of municipal Party committee, mayor * *, * * *, vice mayor of many times the rate of the relevant departments directly under the responsible person in-depth National Highway G105 line72、, G205 line, provincial S341 line and the other highway project site, on-site office, coordination solve engineering construction and environmental comprehensive renovation in the presence of difficulties and problems. Last year, national highway along the county (District) government led organizati73、ons deploy traffic, urban management, public security, land, environmental protection, industry and commerce, highways and other related departments, to carry out to dismantle illegal construction and ground structures, cleaning up illegal standard Records label as the main content of the road domai74、n integrated environmental remediation activities and achieved good results. 3. Pay attention to comprehensive management, improve the effectiveness of remediation. Road construction control management has been strengthened. According to the relevant provisions of the laws and regulations of the and75、 and so on, county * *, * * County Peoples Government on highway construction control area were delineated and issue a public notice, * * County Peoples government also approved by the executive meeting of the government through discussion, implementation of road boundary markers of 73 million yuan 76、of special funds input, stake setting. According to statistics, last year the city has erected building control zone peg 820, construction control area boundary markers 815 . the second is highway greening and beautification work enhance the road area remediation effectiveness. Will highway greening77、 and beautification work as road area remediation of a key, invite garden experts to guide the design of green, the implementation of high standards for ecological landscape highway activities to create, five years, I board greening mileage of more than 900 kilometers, appropriate road greening gree78、ning rate of 100%, effectively enhance the city road greening level and grade, adds a sharp scenery line for *. Third, rectification of illegal construction and occupation of the road has been checked. By through the town, crossing the road on many occasions to carry out concentrated rectification a79、ctions, to clear the remnants of the wall, broken Archives of highways in strict accordance with the wall of building structures and the illegal deposits, remediation along the Jeeves, Jeeves placed advertisements and vehicle maintenance, car washing and other acts, standardize and purification on b80、oth sides of the highway billboards and other non road signs, I city of national and provincial highway basic elimination of the dirty, chaotic, poor, blocking phenomenon, highway traffic environment purification, landscaping. (2) to strengthen the management on the basic data management. The level 81、of the archives management regulations, formulate the , the establishment of the road, the implementation of the file manager, file collection, filing, sorting, filing, confidentiality, custody, borrow, identification pin Destroy the standardization. 2, standardized management, enhance service image82、 (a) evaluation system to further improve in order to strengthen and standardize guidance and assessment of each county (area) bureau of highways management work, the Bureau developed a * City Highway Bureau highways management assessment implementation measures (Trial). To regularly check for half 83、a year, year-end assessment and irregular random sampling combined, taking the spot road inspections, sampling sections, listening to the reports, archives data check, for each county (area) bureau of highways management work implementation of the special assessment. According to the annual comprehe84、nsive assessment appraisal score results, evaluation of outstanding, excellent compliance and Not up to the standard of four grades. And in accordance with the level of assessment, the award on behalf of dial highway management funds. Total score is above 95%, is excellent, 10 million yuan reward; t85、otal score of 90 - 94 for excellent, 8 million yuan reward; for the total score of 80 - 89 points for standard, reward 50000 yuan. On the total score is less than 79 points for non-compliance unit, circulate a notice of criticism. (II) Sheung inspection work to further standardize a is in place to e86、nsure the inspection. National and provincial trunk highway patrol monthly not less than 20 days, State Road a week of not less than 3 times, dart a week of not less than 2 times. The second is to explore and promote the electronic patrol monitoring.City highway patrol vehicles are installed on the 87、highway patrol vehicle monitoring system; highway law enforcement personnel are equipped with a recorder for law enforcement, on the process of supervision and law enforcement to ensure evidence has played an effective role. The third is unified and standardized inspection ledger records, inspection88、 equipment use and management of the electronic Patrol information storage utilization. The fourth is the establishment of highway maintenance and inspections mechanism. The citys 19 country and provincial trunk highway maintenance center equipped with the CPPCC keeper, and to develop a road of the 89、Chinese peoples Political Consultative Conference tube member responsibilities. According to statistics, in 2015 (on the road. Day. Stop the road mileage, 17 cases; clean up debris on both sides of the road 20 , demolition billboard 30, demolition chaotic scaffolding house 3, clean Lane Hawking 15.)90、 (3) road permit work to further strengthen the implementation of administrative licensing system, strengthen the supervision and administration of the licensing. Strict implementation of the . According to the provisions of the road approval procedures and processes to carry out road license, do ac91、cording to the law, the license in accordance with the law, shall be subject to examination and approval of the. Implement the collective examination and approval, to strengthen supervision. Highways and approval of business implementation of technical review of administrative approval and separatio92、n, the audit focused on the more complex involved in the road licensing matters, collective decision-making, to improve the scientific nature of the road administrative examination and approval, reduce approval corruption risks. Second is to promote the In administrative permission of information te93、chnology to improve service quality. According to the and ministries and provincial and municipal government, I realized the butt of Guangdong Province highway information network and provincial network business hall * * * branch office highways licensing examination and approval work. Simplify the 94、licensing process, and strengthen the office system, optimize the quality of service. (4) image of the team to further enhance a is grasp Windows image.2015 years, my bureau highways licensing in the city administrative service center settings window service. According to the and , I Bureau for dama95、ged highway capacity compensation standard, occupied by highway repair (lost) compensation expenses standards, in accordance with the law of administrative licensing items, the communications administrative license implementation procedures into the line on the wall publicity, in the service window 96、is equipped with all kinds of application fill in sample, administrative licensing service guide brochure, in a conspicuous place public commitment to the system and advisory telephone complaints, for the masses provides warm and thoughtful service. Second is to grasp the Four Unifications working i97、n the citys highway law enforcement image. According to the Ministry of transport and the ministries of the Provincial Bureau of the relevant documents, I board in front of the June 2015 completed the identification of law enforcement, law enforcement station appearance, clothing of law enforcement,98、 law enforcement documents four unification. (5) the AILU nursing atmosphere further formation of my bureau attaches great importance to the propaganda work of highway management road awareness month into * City Highway Bureau 2015 road administration work points. One is around the norms of law enfo99、rcement, improve the service theme road awareness month activities carried out. According to statistics, the citys highway system were deployed highways propaganda car 60 times, staff of highways 152 people, set point consulting 6, issued and publicity Data of 8000, hanging banners 134; broadcast 60100、 hours / 20, update 7 inch high rod making permanent propaganda page 4; in 7th edition published , purchased and distributed , legal text, a total of 500 this. The second is to carry out 12.4 national legal advocacy day activities, the city road officers go deep among the masses interpretation of hi101、ghway Highways Management laws, regulations and policy advocacy, analysis for illegal construction at both sides of the road, a typical case of illegal advertising management, showing public road construction and maintenance of highways The actual results of the management, the masses love protectio102、n consciousness and social awareness to further enhance the enforcement of highways.In recent years, I board in the highway management work were some beneficial explorations and the attempt, and achieved initial results, but there is still a certain gap compared with requirements of the Provincial B103、ureau and other brothers City, we will to implement the partys spirit of the Fifth Plenary Session of the eighth session of the opportunity, and further increase the intensity of road management work, and constantly improve the overall quality of the workforce and the ability to learn, and strive to104、 achieve the new highway across.Today the topic of democratic life will I talk about the main to correctly treat leave turn ensure transition delicate gas is understanding, to carry out criticism and self-criticism, in-depth to find problems, profound analysis of the causes, through self analysis to105、 find their own existence problem, to correctly understand their own, strengthen the party spirit training, to ensure that the election of smoothly and successfully completed. Below I talk about their own situation, please put forward valuable opinion. Main understanding (a) serious discipline, to c106、reate a delicate gas is in the general environment in accordance with the Central Commission for discipline inspection organs, , municipal and county Party Committee Organization Department of the county Party Committee Organization Department files related to the spirit of the requirements, earnest107、ly implement the nine is prohibited, nine shall be the solemn discipline, I earnestly study the . , , and file, and a profound understanding of the nine is prohibited, a nine law discipline essence and firmly safeguard the election of serious Ensure the unhealthy tendencies have successfully complet108、ed, and actively create a delicate gas is the election of environment, to ensure that the election, so as to further strengthen the town leadership and cadre team construction. Through the study, in-depth thinking, to a serious discipline the importance and necessity of a more profound understanding109、. First, it is the iron discipline. The central put forward the nine is prohibited, nine shall be the reason for early serious general discipline, designated high-voltage wire, itself reflects the party committees at all levels of the reelection of attaches great importance to the objective is brigh110、t resolute attitude, the implementation of effective measures, the same candidate to fight with discipline election of wind Discipline in gas is health. Secondly, this is prevenient. From some typical cases, we can see that individual cadres election to engage in speculative hack canvassing votes, i111、n violation of discipline, and ultimately paid a high price. The destruction of Hengyang election case and Nanchong canvassing bribery case that strengthen election discipline, serious election discipline of necessity and importance. The discipline of publicity to the public, wide report, that is, e112、arly warning, early hit precautionary needle, tell the cadres should do what shouldnt do, what to do and what not to do, and better education of cadres, warning cadres, and build a strong line of defense, to avoid the occurrence of similar problems. There is duty. Serious discipline, with a strong t113、eam is an important starting point. As the leadership of the party members and cadres, take the lead in the implementation and take the lead in upholding the election of discipline, which is a major political responsibility. Must be clear requirements, strict constraints themselves, cherish the hono114、r, safeguard the image of the organization; promote righteousness, play an exemplary role. Especially as deputy Township, but also to give a full play to its role, always stand in the discipline of first-line maintenance. The wind Su Ji through the election of the work of the whole process. (II) ser115、ious discipline, treat correctly leave turn as a cadre of the party, whether it is in, is back, stay, turn are organizationMetabolism of entrepreneurial career, need and development need. So, his first with a broad mind to treat leave turn. The position is officer positions, power for the people ser116、vice tools. Different positions of the partys cause, plays a decisive role, the same important. To ability strong, style of comrade to important positions and applause, is full of vigor and vitality and promising young cadres in leadership and cheer for their own leave turn and calmly face, calm pla117、ce. Second is to a healthy state of mind to treat leave turn. The personnel of metabolic, between the past and the present. Cadre new old alternant, team, push In the party constitution control strict working to career development objective need, is never the end of the historical process. Each a ca118、dre must face up to the laws of nature to think we also took the former relay baton go on leadership post, regardless of the current positions, positions and responsibilities have what change, can do for peace of mind and mood, such as water, in a happy mood. (3) carefully and find out the problem, 119、correct understanding of themselves, even though they do conscientious, serious attitude, honesty in politics, but high standard , the control standard, especially control learning, striving for excellent activities emerge in large numbers of advanced characters, advanced deeds Static not consciousl120、y practice the strict three real and strengthen the party spirit accomplishment to find the gap, swing is insufficient, a clear direction, mainly manifested in the following aspects: one is the learning initiative and self-consciousness. Often busy with work as an excuse, not consciously take the in121、itiative to spare time to learn. Is often superior to learn what to learn what, and work closely to learn, and working relationship is not less to learn. Mainly manifested in the theoretical study is not thorough, system is not thorough, the Marxism Leninism, Mao Zedong thought, Deng Xiaoping Theory122、 and Three Represents important thought, the scientific concept of development and learning, general secretary of the series of speech learning, just from the surface on learning In the less less less and not deep enough, not from the deeper study, to study, to understand, to sentiment, to use, to g123、uide the work. The second is to investigate the research. This year their participation in the county, the county governments important meeting, the town Party work time is more, coupled with the specific affairs busy, in-depth primary research time reduced. The inspection was carried out research a124、ctivities, there are surface examination, thematic research, listen to reports and discussion research, the general requirements and specific guidance, in a certain extent, affected the timely discovery and solve. Third is the level of leadership, leadership and need to be further improved. Stroke t125、he personnel selection is positive, work coordination and cooperation cant to the best effect; in the coordination to deal with some complex problems, the approach is not enough. Especially encountered, time is tight, the task is heavy, is often the soldiers to be blocked, the water to soil cover, s126、truggling to cope with. The global and forward-looking innovation is not enough. (4) to ensure that the transition delicate gas selected loyal to the party loyal to the people of leading cadres (recommended) for the county to provide accurate information to ensure the transition in the air, after th127、e general election of work have a greater change. The second is balanced, promote the work in an orderly manner. In the future a period of time, the transition will be in the county under the leadership of the Extended surface. And breeding industry and the construction of key projects also in activ128、ely, they have to seriously consider, overall transition and key projects to promote. Education team members and the town, village cadres actively participate in industry cultivate the work, with outstanding achievements to accept the assessment of test of the organization and the masses of the peop129、le, in the town set up promising is a strong general business and the right atmosphere general election, do election and projects to promote the two not mistake, the promotion of two. Second, the rectification measuresOne is to enhance learning, awareness raising, he will continue to strengthen lear130、ning, improve the level of awareness, their own unity of thought and action to the county, township party committee of arrangements for the election. The second is correctly, strengthen discipline, own the right of transition, a matter of personal leave turn, as a town, deputy secretary of Party com131、mittee, themselves are fully aware of the only serious work, strict demands on themselves in order to not negative expectations of organizations and the masses, so that individuals can well deal with good transition in personal leave turn. Three people on the election promise as Deputy Secretary of 132、the Party committee, in the election of my solemn commitment to Catch: if a is strictly abide by and take the lead in the implementation of the nine is prohibited, nine transition discipline, not to engage in cliques, not to engage in canvassing votes buying and selling, buying, and no fraud swindle133、rs officer, do not intercede say hello, not illegal, not to run gas leak, do not interfere with changing times, accomplish strict discipline, warning, with iron discipline firmly put unhealthy trends, promote delicate gas to ensure transition in the healthy and orderly development; the second is res134、olutely obey organization arrangement, and resolutely to stress the party spirit, principle, discuss overall situation, correctly treat personal leave turn, the correct treatment the election results and focus on their careers, from start to finish, ensure the normal and orderly develop.For in-depth135、 study and implement the partys eighteen, the eighth session of the fourth, the spirit of the fifth plenary session, the implementation of comprehensive strictly required, a solid grasp of the construction of Party member team, in accordance with the requirements of the county Party Committee Organi136、zation Department No. 3 (2016) Luo Zufa. According to the requirements of the and the central work of education for the party members, combined with actual town, 2016 Party member education and training scheme is formulated. The guiding ideology adhere to a comprehensive study of implementing the sc137、ientific development view as guidance, in-depth study and implement the partys eighteen, the eighth session of the fourth, fifth plenary session and the General Secretary Xi Jinping series important Speech adhere to the application for promoting learning, and strive to improve our ideological and po138、litical quality of Party members; firmly establish catch a party to build pipe must be members, tube members first catch education of ideological understanding, close to the Party members ideological and practical work, strive to build a party regular education work mechanism, promote the party memb139、ers play a vanguard and exemplary role; firmly grasp the construction of ability of administration of strengthening the party, advanced nature and purity of construction of the main line, adhere to to enhanced grasp the party building work consciousness, strengthen the self construction of the party140、 organizations as the fundamental starting point, for the towns economic and social development provided for ideological and political guarantee of the strong and powerful organization guarantee. Second, target 201 The main task of 6 years of education and training of Party members is earnestly impl141、ement the (Luo Wei do 2015 121) to further strengthen the work of the education and training of Party members request, to training the town, the grassroots party members and common. From 5 January 2016, through a variety of channels in a variety of forms in a planned, step by step, to focus on the o142、rganization to carry out the education and training of Party members. A party spirit idea generally enhanced. Through education and training, prompting the majority of Party members to further strengthen the ideal and faith, enhance the party concept, consciously practice the agency will socialist c143、ore value system. To further enhance the confidence of the road of socialism with Chinese characteristics, theoretical system of self-confidence and confidence. (II) Party members working ability greatly improved. Through the development of education and training, to boost the knowledge structure of144、 Party members transformation and upgrading, improve the party to use the Marxist stand, viewpoints and methods of analysis and problem solving ability, adapt to the new situation and new tasks. (3) play an effective role of Party member model. Through the development of training and education, prom145、ote the party members in theProduction, work, learning and service to the community in give full play to the exemplary vanguard role, and actively striving to take the lead in learning to improve and take the lead in striving for success, serving the masses to take the lead and lead law-abiding, tak146、e the lead in promoting the healthy atmosphere model. (4) the building of grassroots organizations strong impetus. Through the development of education and training, the Party member troop overall quality and ability to serve the people increased, grass-roots party organizations creativity, cohesion147、 and combat effectiveness of the improved. Contents and measures according to different type of the town, at different levels, the actual needs of the different positions of Party members, hierarchical class to carry out the education and training of Party members. Adhere to the town overall and ple148、ase tutoring, please Come in and sent down the combination, to the party spirit education and ability cultivation as the center, overall constitution and discipline, the core value system, political theory, domestic and international situation in town situation, party organization construction, lega149、l education, culture, science and technology, industrial development, management, resource management and protection, social management innovation in the aspects, to village (unit) as a unit, to all members of the organization a above rotation activities. Focus on Township and village committee cadr150、es straight unit leading Party group secretary, activist of join or be admitted to the party, the education and training of village class mothball cadre training, efforts to strengthen the parties organization Secretary of party spirit accomplishment, do a good job of the consciousness of the party 151、building work, enhanced the Party activist , people in rural areas to promote rural economic development of practical abilities. At the same time, through the development of the theme of practical training, autonomous learning training, make full use of the party members and cadres of modern distanc152、e education network etc., for the party members in various fields to carry out the classification of rotation, party spirit training, tobe grind quality, improve quality. Organizational Leadership (a) strengthen leadership, implement the responsibility. Town Party committee to the work of the educat153、ion and training of Party members into the party building work important content, the overall responsibility of the Secretary of the Party committee, vice secretary of the lead and the implementation of specific members of the organization, the organizational Secretary of the parties to personally p154、lan, personally deploy, supervise the implementation; the education and training of Party members to carry out into the grass-roots party Construction work responsibility system and the building of grassroots organizations special assessment, directly with the grass-roots party organizations Pingxia155、npingyou link, to strengthen the organization and leadership to do a good job of work to implement. (II) the overall progress, implement the plan. Ensure that the deployment, according to the arrangement of the 2016 Party member education and training plans, based on the actual needs of the party, o156、n-demand rationing; do supervision and guidance, strengthen the supervision of the work of the education and training of Party members, guidance and services to help solve the difficulties and problems in the training; assessment, by listening to the report, information search, evaluation, etc., wit157、h emphasis on the assessment of the implementation of the plan, Party members to participate in training proportion and effect, indeed Protect task implementation. (3) the typical guide, step up publicity. Pay attention to cultivate advanced and typical, timely promotion and the typical experience o158、f the characteristics of the practice. The work of the education and training of Party members as the focus of the grass-roots party building and the sector skills training for communication and advocacy, by setting the column, offering special journals and other forms of propaganda, to create a str159、ong atmosphere of public opinion, promote the orderly conduct of the work and achieved certain results.In order to further implement the General Secretary Xi Jinping series of major speeches about the partys work style and clean government and anti-corruption struggle spirit and the central, provinc160、e, city, County Commission for Discipline Inspection and the spirit of the plenary session, to further strengthen the awareness of the loyal party members and cadres, sense of purpose, sense of responsibility and a sense of discipline, boost the countys economic and social development. In accordance161、 with the ensemble of Ji Qing 2016) spirit of the document No. 3, combined with my bureau actual, make this program of activities, and a theme of learning party discipline, strict discipline, boosting Qingshen development.Second, activity time April 2016 1 - April 30, three, activity content (a) car162、ry out party discipline learning activities. Global organization of cadres and workers to focus on learning, network learning, self-study and other forms of strengthen constitution , and other relevant information learning. Education for Party members and cadres to as the ruler, combined with its wo163、rk, measure, control and their own ideas and practical test, take the initiative to conduct Lianzheng is affirmatory consciously practice commitment, achieve the hearts of the party, Zun Jishou Confessions of readings of the Si confessions to carry out the hearts of the people, in the heart has the 164、responsibility, in the heart has quit, maintain the partys advanced nature and purity. (2) to carry out special warning education activities. In the global read writing experience, the concept of warning education independent micro film reflections, prisons and courtroom free as the main content of 165、the special warning education activities. Use of the weekly worker will focus to watch a warning education. The , cadres and workers to write their feelings, reflections, and the clean publicity column posted; 4 month global organization of Party members and cadres to the eyebrow delta prison visits166、 to detainees xianshenshuifa education of cadres and workers With low-cost combined with special method. (3) to teach a class of anti-corruption initiate cheap course. By the leaders of anti corruption and financial supervision and administration of state-owned assets of explain the profound things 167、in a simple way to explain, so that all staff of honest business, according to the law to act in a more profound understanding, so as to enhance staffs sense of responsibility and sense of mission. (4) to promote innovation to help the family activities. To carry out the party members and cadres mot168、to, bright family traditions activities for family education into harmony, filial piety, encouraging learning, goodness, thrifty, inspirational, cultivation of excellent genes to guide Party members and cadres to good tradition folk, with a good tradition being honest, with good tradition promote po169、litical winds, creating a delicate gas is the general atmosphere. Four activities (a) to strengthen leadership, careful organization. One is the establishment of the independent warning education month activities leading group of the state owned Financial Bureau, bureau leading Party group secretary170、 of the leader, board members of the team to serve as deputy head. The second is making determine promotional content, clear steps, truly understanding, measures, and put in place, ensure the effectiveness of the activities. (II) take all factors into consideration, pay attention to actual effect. A171、ccording to strict three real special education and two studies do activities, in based on the provisions of the action without aliasing, and creativity to carry out various forms, rich and colorful activities, and strive to Pay attention to actual effect, and resolutely prevent, going through the m172、otions, really promote the party members and cadres from the depths of the ideological solidating abide by discipline regulations of the defence. (3) strengthening propaganda, to create atmosphere. To make full use of the column publicity, propaganda position of network, increase publicity efforts, 173、expand warning education activities of the coverage and influence.Today, we hold the citys precise technology to poverty alleviation and project work to promote the meeting, the main purpose is to further promote the task of aiding the poor with technology roots and accelerate all kinds of scientifi174、c and technological projects. Last year, this year, the citys scientific and technological work has made remarkable achievements, such as the convening of national poverty alleviation of science and technology on the spot will, cultivate high-tech enterprises, Bashan scholar training and the introdu175、ction of scientific and technical personnel incentives, listing national agricultural science and Technology Park, science and technology incubator building. Just now, Huangli In recent years city science and technology to help the poor and science and technology project effectiveness, the main prob176、lems were analyzed, and in a period of time in the future, the citys precise technology to poverty alleviation and science and technology project work arrangements, I agree, I hope everyone to earnestly implement. Here, I stressed the three points.Learning learning, to carry out the learning and doi177、ng education as the citys innovation and development of an important driving force. The Party Central Committee decided to 2016 years in all Party members to carry out learning the party constitution, party rules, a series of speech, do a qualified party member education (referred to as learning to 178、do). Some time ago, I called the learning the party constitution, party rules, a series of speech, do a qualified party member education and mobilization, the province carried out within the two a learning education mobilization. Municipal Party committee will soon be held a mobilization will make a179、rrangements for the deployment. To carry out the two a study and education, based on learning , key in do . As the science and Technology Department of cadres and workers, to (benchmark for two pilot demonstration study through studying the party constitution of party compasses, a series of speech, 180、not only to do a qualified party members, to do a good job of science and technology innovation. Next week, I as the citys county-level leading cadres reading class open cooperation and innovation driven study group members went to Mianyang, Meishan national innovation driven development characteris181、tics and the provinces Innovation Driven Development Zone work experience, a great harvest, feeling very deep. Mianyang, Meishan city innovation driven strength is very great, especially is Mianyang has become civil military integration, a comprehensive reform and innovation, our benchmarking in Mia182、nyang, the gap is very large. Mianyang Science and technology city construction as the basis, built around the Five goal of building Hotbed of innovation of construction science and technology, military and civilian fusion demonstration, collecting and distributing center of scientific and technolog183、ical achievements, innovative talents convergence and high technology industry concentration), vigorously promote to military and civilian fusion for the characteristics of comprehensive reform pilot innovation, and achieved remarkable results, is toward the national civil military integration innov184、ation demonstration area, the national innovation driven development characteristics demonstration area and western economic development growth emerging great step forward. The expanding Park, stronger innovation platform; incubated enterprises, cultivate innovation; poly talent, to improve the abil185、ity of innovation; promoting fusion, highlighting the characteristics of the innovation; catch open, form innovation efforts of the experience is worth learning from. Benchmarking advanced, we have to struggling to The amount of weight is to grasp to catch the strategic innovation. To improve the ta186、rget oriented system. The innovation actually placed in the core position, firmly establish the grasping innovation development, seek innovation is to seek the future, innovation is not backward, slow innovation also will lag behind concept, accelerate factor driven to innovation driven change. City187、 Branch Bureau to actively seek the city management system emphasizing the innovation driven development, focus on strengthening the scientific and technological enterprise incubator construction, scientific and technological innovation platform, technology oriented small and medium-sized enterprise188、s to cultivate, high and new technology industry output value and product evaluation. Second, we must built innovation and Entrepreneurship platform. The city will be in Pakistan and the open area to build the whole To confidence, double center, the new industrial park for a period, the city public 189、entrepreneurship Park Phase II, Qin Ba electricity supplier industry park for three period, incubation area of more than 50 million square meters. The county (District) to take advantage of idle assets of construction science and technology enterprise incubator, a passenger space and other new publi190、c record space, the formation of a, a, a, to create vivid situation. Third, we must foster technological innovation subject. To vigorously implement the high and new technology enterprise doubling plan and science and technology oriented small and medium-sized enterprises to cultivate plan, to honor191、 the implementation of tax incentives, financial subsidies, such as a package of policies to support, so that high technology enterprise indomitable spirit, let the small and medium-sized enterprise overwhelming. To increase investment in science and technology innovation. To actively seek special f192、unds for the development of Municipal Science and technology part for cashing innovation drive the development of financial subsidy policy, transfer a portion of funds for science and technology enterprises of loan guarantees and interest subsidies. Encourage banking institutions set up science and 193、technology branch of the franchise, push the patent pledge loan, for the small and medium sized enterprises of science and technology provide financing services tailored. Fifth, we must strengthen science and technology personnel. To attract more technology military personnel and high-end talent wit194、h technology, project, with funds to Bazhong Lingban or joint science and technology enterprises, encourage and support both inside and outside the citycomrades and the5 years of college graduates and college students to a new public space, science and technology business incubator innovation and en195、trepreneurship.Second, it is necessary to promote the precision technology poverty alleviation as the important content of the scientific and technological work. To build a well-off society in an all-round way by 2020 is the partys eighteen to the whole Party and the people throughout the country to196、 make a solemn commitment. Lead the city people out of poverty to become rich go straight towards well-off, Party committees at all levels, political responsibility and mission of the times of the governments major political, technology sector is also the bounden responsibility. Municipal three tent197、h plenary session made , proposed to further promote the five a group of precise action to help the poor, six precision and 1 + 6 poverty alleviation projects, clear the add Great science and technology achievement transformation efforts, accelerate the construction science and technology poverty de198、monstration village and demonstration households, give full play to the role of modern information network, for the impoverished village poor households to provide production technology, market information, policy advice, encourage scientific and technical personnel to the poor village launched a to199、 one helping and guiding the development of income industrial projects, strengthen technical training and propaganda of popular science, highlighting grasp large breeding, family farmers, agricultural co-operatives are the backbone of the training technical poverty alleviation mission. The citys sci200、ence and technology sector must be from the political height, the assault fortified positions that help deficient up as the most important task, the most urgent work. The most arduous mission, to science and technology for precise poverty alleviation promote to speed up a well-off society in an all-201、round way Decision to deploy, boost the process to precise technology to poverty alleviation and the effectiveness of a well off society in an all round way. One should obey the overall situation. The citys scientific and technological system of cadres and workers, especially leading cadres, should 202、have the political consciousness, ideological conscious action conscious, in accordance with the central, provincial and municipal deployment requirements, to strengthen the organization and leadership, reasonable arrangement of time, carefully study the deployment, to ensure poverty. There must be 203、resolutely implement the political position and character, poverty alleviation and the attitude to be distinctive, poverty alleviation action should be strong, to politics, to understand the overall situation, re implementation, see results. To lock the target. In accordance with the provincial Part204、y committee and the municipal Party committee, municipal government, lock 2 provincial-level General requirements for the completion of the goal of poverty alleviation poverty alleviation poverty alleviation poverty alleviation poverty alleviation poverty alleviation and Technology Demonstration Cou205、nty, four provincial science and technology demonstration towns, 10 provincial science and technology demonstration village and a municipal science and technology demonstration area, 2 Municipal Science and technology demonstration towns, five municipal science and technology demonstration village a206、nd the five one precise technology to poverty alleviation and special operations tasks, inverted duration, wall chart battle, set the time, tasks, measures, staff, given the responsibility to ensure high quality precision technology poverty alleviation task. To focus on the key. To focus on precise 207、poverty and accurate out of poverty, detailed measures, clear job responsibilities, to develop targeted and operable precise technology to implement poverty alleviation program. Prominent precise poverty technical training, poor village informatization construction, technology oriented poverty reduc208、tion model village and demonstration households construction precision technology poverty alleviation focus, in a precise sense, precise attitude, precise style, go all out to fight the precise technology of poverty alleviation and battle.Three, it is necessary to strengthen science and technology f209、unds supervision as an important means to enhance the quality of the project. Science and technology project fund supervision is the key to the implementation of the project of science and technology. In recent years, especially during the Twelfth Five Year Plan period, the system of science and tec210、hnology management in the city vigorously to declare the implementation of the country and province science and technology projects, science and technology demonstration lead brought obvious effect and improve the scientific and technological innovation capability of enterprises, boosting the charac211、teristics and advantages of industrial development, science and technology support to the economic and social leading role improved significantly. In the project management of science and technology, in addition to seriously implement the state, provincial science and technology project management r212、ules and regulations, and the actual Bazhong, established the access system of science and technology projects, the project of science and technology commissioner system, science and technology Project credit system and scientific and technological projects honest commitment system, and the Municipa213、l Finance Bureau jointly issued the Bazhong City Science and technology development funds management approach, formulated the trilogy of seven science and technology project implementation specification, these are worth fully affirmed. However, we should also see clearly, we in the science and techn214、ology project management still exist account of the special accounts, earmarking system is no effective implementation and other issues. In particular, this year the Audit Commission Chengdu Tepai ban on Bazhong confidence found in the audit of science and technology business incubatorProblem has ce215、rtain representativeness. The audit to us sounded the alarm, should cause everyone vigilance. Here, I will strengthen science and technology project budget supervision put forward four requirements: a strict project reporting, prevent fraud. Implementation of the project to declare the competition m216、echanism, the annual financial support to science and technology projects oriented society Bulletin, conditions open content, open competition to declare, open field investigation, public presentations, the public assessment of the decision, do full open and transparent, fair, accept social supervis217、ion. To those who resort to deceit or something real is not clear, suspected of defrauding, impersonator national subsidy funds, once found immediately cancel Declaration of qualification, recovery of funds subsidy and discipline in accordance with the law strictly held responsible. Second, we must 218、innovation funds supervision. In county finance to establish science and technology project account, the project undertaking entity in accordance with the key nodes task completion by formal invoice to apply for funding and audited by the Department of science and technology, the Ministry of finance219、 funds, and resolutely put an end to project funds are retained, misuse and misappropriation. Third, we need to strengthen scientific and technological project supervision. Department in charge of science and technology to strengthen project inspections to check or checks, of ineffective implementat220、ion to strengthen the supervision and the existence of violations of responsibility into the project undertaker rectification. To establish a scientific and technological project, black list system, the Project implementation quality particularly poor recorded in the black list, stage or permanent a221、bolition of the applicant country, province, city science and technology project qualification. Fourth, it is necessary to carry out training funds management. Science City Bureau to the initiative to meet with the finance department, organize project unit commitment held science and technology proj222、ect funds management training, of country, provincial and municipal science and technology project funds management of the relevant policies, financial acceptance specification, mid supervision points, budget review points and key contents were training system, to ensure the use of project funds saf223、e and reasonable.Thank you all!To implement the central, provincial, city and county to make important decision about the grass-roots party construction work in the deployment, push forward the county public security organs in the work of Party building, further strengthen the party secretary of the224、 governing party and party liability, according to requirements, according to the arrangement of the Bureau of the party work. Today, the organization held the county public security organs party secretary grasping grass-roots party construction work in the debriefing will. The implementation of thi225、s is a powerful measure to the Secretary of the party organization construction of the party, and is learning to carry out the partys spirit of the Fifth Plenary Session of the eighth session of the, grasp the new situation of Party building work under the rules, pushing Public security party buildi226、ng services in the public security center of the inevitable requirement.Just now, the 3 Juzhu unit Party branch secretary of debriefing, below I on the 3 party organization work one by one review.Party branch of the Political DepartmentGood: first, strengthen ideological and political work, pay clos227、e attention to the work of the implementation. The Political Department of the Party branch strictly in accordance with the requirements of bureau Party committee, to strict three real special education as the main line, take effective measures, pay close attention to the ideological and political w228、ork of the implementation, strengthen the education of Party members and the police thought, improve the Police Ideological and political consciousness, make a solid foundation for public security work smooth development of health. Second, strict management team, boost the morale of the team. Strict229、 implementation of Police Ideological Trend of periodic analysis, timely grasp the ideological situation of the personnel; strictly implement the system of check on work attendance, strengthen the daily management; cash rewards and punishments, continue to boost the morale of the team. The third is 230、The intensification of police training, improve the police actual combat skill. Seriously and actively carry out a series of training activities and learning activities, the majority of police in the political quality, physical quality, professional quality, policing skills improved. The fourth is t231、o adhere to the preferential treatment from the police, the warm pool police. According to thRequirements, and actively do a good job of personnel management work, to run within the scope of the policy, help the police solve the practical difficulties, the police systemic heart into work. The fifth 232、is strengthening propaganda, promote righteousness. Around the center of the public security work, actively do a good job in the publicity, fully display the spirit of good public security team. Six is to fulfill the responsibility of Party building, do a good job of education and management of Part233、y member team. Sound and perfect three class, Party of democratic appraisal, commendation and reward system, effectively enhance the branch of the creativity, cohesion and fighting capacity.Shortcomings: is ideological and political work still can not adapt to the new situation, new task, in the for234、m of a single, innovation is not enough, lack of learning education of the appeal and study the effect of education needs to be improved, the political department to strengthen the guidance to the grass-roots units. The second is the branch of organizational life will implement the is not good enoug235、h to play an exemplary role.Traffic Police Brigade Party branchSystem of good practice: one is grasping the implementation of the work of Party building system, enhanced branch team cohesion, combat force. The brigade Party branch always pay close attention to the work of Party building and would no236、t let go, conscientiously perform their duties, strict implementation of democratic life etc., to develop the branch of learning plan, all equipped with learning record the experience and experience the and organize regular inspection learning, ensures that the learning plan, implement, effect. Seco237、nd is to carry out the strict three real special education. The development of special education learning scheme, held a party branch focus on learning and the level of consultation forum, deputy director in charge of, brigade leader for the party members and the police on the lectures, deployed to 238、carry out Ban Zicheng throughout the Yan Zhenchang Yang Shuicai to relive the oath to join the party, visit the memorial hall, learning advanced characters, micro lectures attention and learning characteristics of the activities, and to develop measures for rectification. Three is to pay attention t239、o the party building work into the public security work. The brigade Party branch and always will be the work of Party building in 9.3 security, national civilized city re examination, the SCO security meeting, the focus of illegal investigation, sword, anti terrorist violence, to ensure safety, fiv240、e wave, camp turn non bus, detoxification, the focus of the work, in a timely manner to carry out the pre war mobilization, wartime dynamically judged, the post-war award in recognition of a series of measures Members always fighting in the first line of traffic management, all traffic police has al241、ways maintained a high state of mind, a strong impetus to the work carried out.Shortcomings: first, there is a hand hard and soft phenomenon. Of work of Party building under the new situation is not enough emphasis, focus on light business building, re form light effects. The second is measures are 242、not enough effective. In particular, catch a party to build working innovation consciousness is not strong, measures and methods used in the experience of the old, old practices and effectiveness needs to be further strengthened. The third is three lesson not very good insist, life of the party orga243、nization to carry out less often.Zhao police station Party branchGood practice: one is to strengthen the study and education. To strict three real special education as an opportunity to take leadership lectures, seminars, individual learning, exchange of experience in various forms, the police organ244、ization learning leaders at all levels of the spirit of the important speech, in the constitution as well as the side of corruption cases and asked party members and the police carefully recorded study notes, writing experiences, join and pay attention to the micro lectures, according to the control245、 requirements of inspection, enhance their own, to ensure that the learning effect. The second is to strengthen the leadership responsibility. Party branch secretary as the first responsibility of honest government, earnestly implement the four person , and insisted on the important work personally 246、Department Department, major issues personally intervene, personally key aspects of coordination, supervision of important cases personally , Party branch members always strict demands on themselves, play an exemplary role model. Third, strengthen the service for the people. Every act of the masses 247、for the warm reception, carefully recorded masses anti reflect each a problem, and make the resistancee bureau Party committeeHeart to answer, and constantly improve the quality of service. Combined with the one village, one police work, police organization carefully touch row all may affect the sta248、bility of the unstable factors, resolve conflicts and disputes, and arrange for the police with daily visits, issued security leaflets, collecting sites, personnel information, promote the harmony police.Existing problems: a party branch team party affairs knowledge is not rich enough, on some of th249、e procedural provisions are not familiar with, in a certain extent restricted the work carried out. The second is regular ideological education is not deep enough, the ideological trends of the police command is not timely and accurate. Third, there is a need to improve the management level of refin250、ement, police standardization awareness is not strong enough, daily habit is not quite self-conscious.Since this year, bureau unit Party branch to strict three real special education as the main line, to the service center, troop construction as the focus, adhere to the combination of ideological bu251、ilding of the party and the system of the party, solid to carry out the comprehensive strictly required, to further standardize the construction of the party organization, continuously improving the quality of Party members and police, continue to strengthen the party building innovation, service bu252、ilding execution significantly improved, has made remarkable achievements.Meeting debriefing of 3 units in the work of Party building problems in other units are also different degrees of existence to other units by the party building debriefing, draw on the experience of face the problem, replicabi253、lity, careful analysis of rectification, promote the sustained and healthy development of the work of Party building units.Below, to further strengthen the county public security organs party building work stressed the views of five points.One, improve the ideological understanding, enhance the sens254、e of political responsibility and historical missionFollow the basic construction of the partys eighteen years, Xi Jinping, general secretary: the series of important speech to the party put forward many new ideas, new judgment, the new requirements is to promote grass-roots party building work. We 255、should thoroughly study and understand, and consciously assume responsibility. One is to grasp the party building three questions of the new requirements. Xi, general secretary of the partys mass line education practice summary of the General Assembly on the proposed the construction of three questi256、ons, namely: is not the party committees at all levels and the departments of Party committees (party) to achieve the sedulous catch a party to build is not at all levels of Party committee secretary, the Department of the party committees (party) secretary become strictly administering the party se257、cretary? Is not at all levels and all departments of the party Forced the construction of Party committees (party) members to fulfill the responsibilities strictly responsibility? General Secretary of the party building three questions , directed at the crucial point, enlightening, three mirror plac258、ed in front of everyone, let you according to a photo, see a look, want to think about the conscious of it, is the three pieces of papers placed in front of us, it is clear to judge ourselves whether in to do their duty. Building three questions , urge people to watch, thought-provoking, and convey 259、a strong responsibility to ask signal. The second is to understand the building three no new judgment. Xi, general secretary of the partys mass line education practice summary congress pointed out that history and reality Are accounted for in the police forces of discipline, do not do, is to stop th260、e event tells us, not a clear responsibility to implement the responsibility, accountability, and strictly administering the party is not to . General Secretary of the three no , a clear responsibility to implement the responsibility, accountability, and point out the key. The county public security261、 organs is a team of the Communist Party as the main body, Party members and the vast majority of bureau of belonging to different units of the leadership cadres and backbone of the party members, the power and responsibility are relatively concentrated in the partys construction, must be clear resp262、onsibilities, the implementation of responsibility, accountability, or catch a party to build is an empty word. Three is to clear the three grasping new initiatives. The total learning book Remember that catch a party to build must grasp the responsibility system, grasping accountability must grab t263、he responsibility person, grasping the responsibility must catch the first responsible person. Why should we let the Bureau unit Party branch secretary of the debriefing is to implement general secretary put forward 3 catch. To seize the party organizations primary responsibility, seize the key issu264、e.Two, the full implementation of the task of ideological construction, the theory of armed tasks implementedGeneral Secretary Xi Jinping in the mass line of educational practice summary congress put forward in the new period party building thought of tasks and requirements, to strengthen the constr265、uction of the Party pointed out the direction and path. One is to strengthen theoretical study. The urgent task is to fully understand the study and implement the spirit of the fifth plenary session of the eighth session of the significance of, the organization of Party members and the police throug266、h the focus on learning, self-study and special counseling and other forms of serious in-depth learning, adhere to the first step in learning, deep layer, accurately grasp the spirit of the Third Plenary Session of the Eleventh Central Committee, and do the thinking and learning gains, use it. The s267、econd is to strengthen the party spirit temperance. Adhere to the school party constitution. Through the center of the group learning. Secretary of the party organization about lectures and other forms of learning the party constitution, enlightenment spirit, guide Bureau unit Party branch and all m268、embers of the police to firmly establish the consciousness of the party. Persist in learning advanced. Vigorously carry forward the spirit of Jiao Yulu, Yang Shuicai spirit, seriously study the advanced deeds of Comrade Yan Zhenchang, deep fine shine Dusing the police party guided, to strengthen pub269、lic opinion and public servant consciousness, consciously practice the strict three real. The third is to strengthen the party and Party discipline education. For the ideological construction of the party faces new tasks, new requirements, the emergence of many new problems, new situations, and acti270、vely take the initiative to adapt to the constantly emancipate the mind, innovative ways, making use of the Internet, micro channel, micro Bo new platform for new, enrich the content of education, improve education forms, the constant reminder education, enhance the police Party discipline in awe, g271、uide Party members and the police do political understanding discipline about the rules of the leaders. The fourth is to strengthen the ideological and moral education. Guide the party police exemplary practice the socialist core values, cultivate good political and moral character, professional eth272、ics, family virtue and morality, forming a strong atmosphere of moral construction. Pay attention to strengthen the positive guidance to the police party ideology, adhere to the diversification of the social ideology guided by the system of theories of socialism with Chinese characteristics, improvi273、ng and perfecting the Party members and the police thought The dynamic analysis of mechanism, providing an ideological guarantee for the purity and firmness of team members.Three, fully implement the strict requirements, the management and administration of the partys responsibility to implementGene274、ral Secretary Xi Jinping stressed that to implement strictly the responsibility, do a good job of Party building as the biggest achievement. Therefore, in my bureau implement comprehensive strictly required must be the party tube responsible party implemented. First, to further implement the respons275、ibility system in Party building. To establish and improve the party building responsibility assessment mechanism, at the beginning of the year to progressively signing party builds working target responsibility book. Party organizations at all levels is mainly responsible for comrades to do a good 276、job of Party building as the greatest achievements, adhere to the development wholeheartedly for, to concentrate its attention on the construction of the party, the party building work is included in the agenda, and business to work with the deployment, with checks, with the implementation of, true 277、to form Party grasping, Secretary to take the lead in efforts, in charge of the leadership Specific catch, catch a, layers of implementation pattern of Party building work. Is to improve the reporting and appraising system. In accordance with the debriefing the party building, the appraisal rating o278、f Party building, Party building assessment test, use of cadres at request of the party, CF county Party debriefing practice, and constantly improve the annual party built debriefing appraisal system, in particular, to the year debriefing appraisal evaluation and annual comprehensive examination clo279、sely together, the party builds the job evaluation results into the leading bodies and leading cadres of the annual comprehensive assessment system, strengthen the use of dynamic management and results of debriefing appraisal work, further enhance the debriefing appraisal of scientific, effective an280、d directive The new integration business. Three is to improve the three class system. Three class system is to improve the partys organizational life, strict party member education management system, we must do a good job in the implementation and long-term persistence. According to the party secret281、ary of the organization lectures, party members and cadres micro lectures and Thematic Party Day activities, innovation three class form, rich three class content, pay attention to the work of Party building with the public security work, the formation of the same resonance frequency, the linkage of282、 communion party organization life situation. At the same time, the three class system implementation of join or be admitted to the party organization committee debriefing appraisal of important content, strict grasp the three class system Real.Four, strict political discipline and political rules.G283、uide all Party members and the police in ideological political action always as the general secretary of the CPC Central Committee with Comrade Xi Jinping highly consistent, involved in major political principle, political stand, political views and other issues, we must be sober, stand firm. Guide 284、the members of the civilian police to strengthen the sense of organization, determined to do the individual is subordinate to the organization, the minority is subordinate to the majority, the lower level to the higher level, and the whole party to the Central Committee. Some time ago, I held a part285、y enlarged meeting, focus on adherence to the partys political discipline and political rules of thematic theory study, I at the meeting for the feelings to speak. I understand, party a concept of organization, can not see Party, touch not. According to the materialistic point of view, the material 286、determines consciousness, existence determines consciousness, consciousness is the objective things in the brain to reflect, then, how to prove that the partys existence? Like the current, can not, can not be touched, but through the wire carrier, connect power supply, the electric light, the motor 287、is running, it is proved that the current existence. Similarly, the party is by living every Party member, every Party member, speech and action of the carrier, reflecting party. Party is a whole, in order to normal operation, each party members according to their personality characteristics. Academ288、ic knowledge, professional knowledge, hobbies, physical condition, age, work experience, work experience and other comprehensive evaluation, main task of the division of labor and in jointly do a good job in party work, is mainly responsible for the Division I business, then in my division of work, 289、in the Party committee collective discussion by, decision, foreign, on every level of members can to bureau of the party in the name and identity delivered a speech, the organization of work. In specific work, in the higher Party committees have clear provisions of the spirit, in accordance with the290、 spirit of the documents of ranking Party committee, combined with my work of the division of labor, on behalf of the bureau Party committee put forward their views and suggestions. Since Party members according to the higher Party committees to the spirit of the document can be Bureau on behalf of 291、the party organization of work, then the behavior has party authority and seriousness, we should respect them and be with, give support, cannot according to personal preferences, personal understanding and awareness, regardless of the occasion, in broad daylight, in meetings, especially in the lower292、 front of, guilty of liberalism, published the higher Party committees have been expressly prohibited speech, also cannot euphemistically called the personal point of view; regardless of party image and personal image, irresponsible, gossip, just open the river, grumble, grumble about; even, sarcast293、ic ridicule, sarcasm, oblique accusations, make people Hold the most stringent start speech, personal attacks, vent personal grudge; more even, with ulterior motives, ulterior motives; fan Yin breeze, will-o - the wisp, deliberately and party dissension and discord, rumors spread, the spread of divi294、sion, and the party and the people, the hearts of the people, the decline of morale. This kind of behavior is the partys discipline are not allowed, from my start, from the members of the Party committee member, once, who despite the party discipline, drunk, behind, the key moment, in violation of t295、he partys political discipline, political rules and wait for the party discipline. We must strictly comply with the implementation of the central and superior party committee has clearly defined, does not allow bargaining, unconditional obedience, unconditional , does not allow a discount, or disgui296、sed discount. In addition. We want to strictly enforce the system of democratic life of the party, Party of democratic life, it is necessary to carry out criticism and self-criticism, is between the members of the Party committee of the mutual criticism, remind each other, will not do not speak, gos297、siping afterwards. Guide Party members and the police strictly request reporting system, regularly party members to execute the political discipline of political rules situation analysis judged and thematic summary, constantly enhance political of the political life of the party, the principle and m298、ilitancy.Five, comprehensively improve the scientific level of Party building, the task of the party buildingTo enhance the scientific level of the construction of the party is our party according to the worldly affairs, national and the new changes and new challenges of the party put forward the ma299、jor issue is effective to deal with the four test , resolve the pressing requirement of four big risk is the only way to maintain and develop the partys advanced natuStep is to strengthen the partys cohesion, attraction and the fighting power of the inevitable choice. Under the new situation, it is 300、necessary to apply the law of the ruling party construction of Marxism, according to the basic requirements of maintaining the partys advanced nature, continue to study new situations, solve new problems, sum up new experience, make the party building in scientific orbit continues to advance. One to301、 focus, efforts to lay a solid foundation. Continue to carry out the two hit activities, accurately grasp strictly required new rules and characteristics of the work of Party building under, deepening grass-roots increase of basic party organization and Party member quality upgrade plan. Continue to302、 carry out the window units vanguard party post, window model building activities, and continuously Enhance the party members and the police involved in activities to create enthusiasm. Increase of Party organizations and Party members advanced typical advocacy training efforts to become a sign, eve303、rgreen tree. To broaden the party serving the masses channels, construction of Party members contacting and serving the masses work system, make the Party member to become truly keep in mind the purpose, advanced elements of the heart of the masses. Establish and improve incentives within the party,304、 care, helping mechanism, we do care and love grassroots cadres, old party members, difficult life member. In order to promote the party construction services, continue to carry out party members and counterpart assistance live and on-the-job Party member volunteer service activities. Second, we mus305、t strengthen management, efforts to enhance the party members Quality, and conscientiously implement , adhere to strict standards, rigorous training, strict procedures, strict regulation and control, and continuously improve the quality of Party members, optimize the structure of Party member team. 306、Strengthening of different kinds of police, the classified management of Party members in different positions, through the implementation of target management of Party members, record management, star rating etc. ways to strengthen the education of Party members, management and service work. Adhere 307、to the mass appraisal, solid and effective to carry out members of the public commitment, no post party post duty activities, give full play to the role of Party members. Actively introduce the Internet +, by means of information to strengthen the education and management of the party members and ma308、ke full use of Xuchang male Ann party building network , peace of Xuchang, Communist Party members, Liancheng micro lectures and other network platform to strengthen the education and training of Party members. Three to strict requirements, efforts to improve the partys style of work. To build a fir309、st-class units, to create a first-class team, cultivate first-class style, create first-class performance as the goal, combined with learning from the advanced models, and effectively solve the police party in the party spirit, moral character, style and ability existing prominent problems; adhere t310、o the lead austerity, oppose extravagance and waste, and oppose formalism, bureaucratism and seriously practice the strict three real, establish a good style of work; earnestly implement the eight insist, eight against , advocate diligence Excited to learn and apply what they have learned, the heart311、 of the masses, serve the people, grab get right on the job really, and to ensure the effectiveness of, hard work, thrift, the overall situation, curried, develop democracy, solidarity work, impartially and with the right of honesty in politics, life is decent, healthy interest in eight aspects of g312、ood atmosphere, promote the county public security organs party political construction has made new achievements. Fourth, it is necessary to produce battle fort effect. Party organizations at all levels to grasp the practical to the center of the public security work service key links, adhere to the313、 completion of difficult and perilous task as the main battlefield of the work of Party building, the more encountered serious incidents, major rescue mission, a major security tasks, the more you want to play the party organization The role of core, and earnestly do a good job before the war mobili314、zation, wartime motivation, war veteran and so, truly party members and cadres to fight to where, the life of the party organization will extend to where, the role of fighting bastion of the party organizations play where, reflecting the party building work to promote and protect the power.Comrades,315、 in the circumstances to promote comprehensive strictly new situation, the Party Central Committee and the Party committee of a higher level of the construction of the party proposed the new, higher requirements, the work of Party building task is arduous, the glorious mission, rare opportunity. Let316、 us to the debriefing meeting as a starting point, in the Bureau of the partys correct leadership, conscientiously study and implement the series of important speech of General Secretary Xi Jinping, spirit and the partys spirit of the Fifth Plenary Session of the eighth, thoroughly implement the com317、prehensive strictly required, continue to carry forward the partys fine tradition, hearten spirit, do solid work, the enterprising spirit, selfless dedication, to continue to create the county public security organs of Party building work in the new situation, to maintain social stability to ensure 318、Successful completion of the task,re, also is aPromote public security undertakings flourish, for the construction of a beautiful and happy Xuchang county to make new and greater contributions!Carry out the party building debriefing appraisal work, implement the central and provincial Party committe319、e, the municipal Party committee and comprehensively promote the strictly deployment requirements, implement strictly the responsibility, tamp the foundation of Party Construction of major initiatives. Public security organs as the partys absolute under the leadership of the democratic dictatorship 320、force, as the party and the people in the hands of the hilt must to strengthen the work of Party building and walk in the forefront, and make an example. From just four of the Secretary of the party organization debriefing situation, the party organization of debriefing of Party building and ideolog321、ical work attaches great importance to prepare more fully, in the debriefing process, say achievements do not exaggerate, speak the problem does not cover, emphasize not vanity about rectification, truly realistic. Offer as Political Bureau Director comments, targeted strong, closely with the practi322、cal assessment highlights outstanding characteristics, ask clear, point out of the results, points out the problems and points out the pressure. This is not only a debriefing meeting and Party building the responsibility to implement, today the debriefing, to do a good job of new period party building work will play a very good role in promoting. Next, according to the city bureau Party Committee on Party building work on the arrangements, Bai chief commissioned by combining city Bureau of Party buildi