某涉外项目电缆桥架安装施工方案培训资料.docx
下载文档
上传人:地**
编号:1245203
2024-10-19
36页
502.66KB
1、METHORD STATEMENT FOR CABLE TRAY INSTALLATION电缆桥架施工方案版本Rev.编制Prepared by审核Reviewed by批准Approved by认可Accepted byContents目 录、 工程概述1General1、适用范围1Scope of work1、 编制依据1References1、 施工准备2Preparation for construction25、 桥架安装技术要求4Technical Requirements for Cable Tray Installation4、 桥架施工工序8Cable tray instal2、lation procedure8、 施工详细描述8Installation description8、 施工注意事项及措施11Construction precaution and measurement to be taken119、施工特别措施13Special measurement to be taken in construction1310、 脚手架搭设描述及注意事项15The procedure of setting up scaffold and precaution1511、(JHA)25工作安全分析25Page 33 of 34、 工程概述General为了保证电缆桥架安3、装工作正常有序地进行,力求施工周期最短、确保技术、安全可靠的方案编制原则,根据国家、业主的规范要求,特编制此电缆桥架安装施工方案,以说明安装过程中施工方法、施工用料、施工顺序。In order to ensure normal and proper field installation for electrical and instrument cable tray safe successful completion of the work, this installation procedure is specially prepared as per the national stand4、ards and the Owners specification requirements in the principle of lowest construction cost, shortest construction duration and safe reliable technology to elaborate the installation construction method, construction materials and installation sequence、适用范围Scope of work 本方案适用于拜耳聚碳酸酯SPCII/LOGII项目桥架施工5、,包括管廊桥架、B204区域、B244区域、B209区域、B252区域、B221区域、B222区域桥架施工及其它区域桥架施工。This scope describes the activities to be performed by the Contractor for the Works and Services as specified below for Bayer SpcII/LogII cable tray installation, including outside pipe rack area, B204, B252,B209,B244,B221,B222 area and 6、other area which need to be constructed.、 编制依据References3.1 设计图纸及及相关技术文件Design drawing and Relevant documents3.2 国家及BAYER公司相关规程、规范、标准National codes & standards, relevant Bayer specifications3.3 建筑电气工程施工质量验收规范GB50303-2002Code of acceptance of construction quality electrical installation of building3.7、4 电气装置安装工程爆炸和火灾危险环境电气装置施工及验收规范GB50257-96Construction & Acceptance Code for Electrical Device Installation in Explosive and Fire Hazard Environment3.5 自动化仪表工程及验收规范GB50093-2002Construction & Acceptance Code for Automatic Instrumentation Works3.6 自动化仪表安装质量检验评定标准GBJ131-90Quality Inspection & Assessment 8、Standard for Automatic Instrumentation Installation、 施工准备Preparation for construction4.1、 技术准备 Preparation for technical method4.1.1 熟悉图纸和相应的国家标准规范,会同设计及业主较早完成对图纸问题的澄清,并完成施工方案和特殊技术措施的编制;Be familiar with drawing and relevant national specification, timely clarify any question about drawing jointly wi9、th AKC and complete construction plan and special technical measures;4.2 人员准备Preparation for person 4.2.1进入施工现场作业的人员应具备相应的施工资质;Personnel preparation: after entering onto site and prior to working, carry out safety training to all construction personnel and clarify all technical details;4.2.2 对进入现场作业10、人员进行安全培训和施工技术交底;The person who enter into site and do construction work will be trained in the safety and accepted technical clarification.4.3 材料准备Preparation for material 4.3.1根据合同内容和施工图纸资料,准确的提出施工主材和消耗性材料用量以及时开展采购工作;Material preparation: since short construction period and tight time, it shall acc11、urately work out primary construction material and consumptions according to contract and drawing to timely carry out procurement;4.3.2 本工程中,管廊上电缆桥架(600mm以上)采用热镀锌钢质托盘式,B204厂区内电缆桥架(600mm)采用热镀锌钢质托盘式,电气桥架(300mm)采用热镀锌钢质梯架式,仪表桥架(300以下)采用不锈钢格栅式。B252厂区内电气桥架(300mm)以上使用梯架,以下使用隔栅式桥架,仪表桥架(300mm)以上使用托盘式桥架、以下使用隔12、栅式桥架。其中电缆桥架(600mm及以上)由业主供应, 电缆桥架(600mm以下)由承包商供应;In this project, equal to and more than 600mm hot galvanized steel cable tray will be adopted on the outside pipe rack and 600mm hot galvanized cable tray will be installed for electrical and 300mm hot galvanized cable ladder will be installed for elec13、trical, 300mm stainless steel grid cable tray for instrument inside room in B204 area; cable ladder will be used in more than 300mm and stainless steel grid tray will be used in equal and less 300mm for electrical in B252 area; channel tray will be used in more than 300mm and stainless steel grid tr14、ay will be used in equal and less 300mm for instrument in B252 area; cable tray(600mm and above) will be supplied by the owner, less 600mm cable tray will be purchased by contractor. 4.3.3 电动工具、测试仪器应符合BAYER的使用要求,工机具的使用应有效期内;Machinery, tool and test instrument preparation: the electric tool and stand15、ard test instrument shall be in compliance with AKC requirement and within valid period;4.4 验收及保管Acceptance and keeping4.4.1 电缆桥架到场后应及时进行材料验收; Materials acceptance shall be done in a timely manner for cable tray after delivery to site.4.4.2 检查厂家技术文件、合格证和质保书是否齐全。出厂产品数据是否符合设计要求;The manufacturers techn16、ical documents, certificates of compliance and quality certificates shall be checked for completeness and the product data be checked for compliance with the design requirements;4.4.3 桥架及附件齐全、表面光滑、不变形,型号规格符合设计要求。The cable tray and accessories shall be complete and have smooth and undeformed surface.17、 The type and specification shall comply with the design requirements. The cable tray section at the bends and joints shall be smooth and free of burrs;4.4.4 验收合格的材料应分型号、规格摆放,便于材料领用。 Qualified material by acceptance will be stored by type and specification in order to convenience for using.4.5 施工主要工18、程量及主要施工材料Main work load and materials in construction序号No.名称Description规格及型号specification单位Unite数量Quantity备注Remark1热镀锌钢质梯架Hot galvanized steel ladder600150米 m2002热镀锌钢质梯架Hot galvanized steel ladder300150米m5003热镀锌钢质梯架Hot galvanized steel ladder400150米m1004不锈钢隔栅桥架Stainless steel grid tray300150米m15005不19、锈钢隔栅桥架Stainless steel grid tray200100米m10006不锈钢隔栅桥架Stainless steel grid tray 10050米m25007热镀锌钢质托盘Hot galvanized steel tray600150米m1008热镀锌钢质托盘Hot galvanized steel tray900150米m309热镀锌钢质托盘Hot galvanized steel tray400150米m6010C型钢C steelP4141米m20005、 桥架安装技术要求Technical Requirements for Cable Tray Installati20、on5.1 严格按设计图纸施工。安装前与工艺、设备等专业图纸进行会审,以免发生碰撞后,二次拆装;The construction shall be performed strictly as per the design drawings. The drawings for process, equipment shall be reviewed before installation to avoid interference and re-work;5.2 桥架及其支架和引入、引出的网格桥架必须可靠连接且应符合下列规定:Cable tray and its supports and its21、 branch grid tray shall be reliably connected and comply with the following specification:5.2.1 电缆桥架直线段每隔30米应安装一膨胀节,并且在膨胀节处增加桥架跨接线;Expansion joint will be added in strait line segment at interval of 30m when cable tray be installed and jumper wire will be connected from one cable tray to another in 22、the place of expansion joint.5.2.2 电缆桥架在弯曲处的弯曲半径,不得小于桥架内电缆最小弯曲半径;电缆最小弯曲半径见下表: The bending radius of cable tray at the bend shall not be smaller than minimum bending radius of cable inside cable tray;Minimum bending radius of cable sees the table as follow: 序号No.电缆种类Cable description最小允许弯曲半径Minimum b23、ending radius1聚氯乙烯绝缘电力电缆 VV cable10D2交联聚氯乙烯绝缘电力电缆 YJV cable15D3多芯控制电缆 multi wire control cable10DD为电缆外径 D- outside diameter5.2.3 电缆桥架支架水平安装时支架间距不大于2.5米做一次固定,垂直安装的支架间距不大于2米做一次固定,在有弯通或三通的地方则必须单独增加支撑点; For the cable tray support, if no requirements, the spacing for horizontal supports shall be 2.5m and24、 that for vertical supports shall be no greater than 2m;individual support will be added in the elbow and tee.5.2.4 桥架支架与各种钢结构的连接都采用卡接方式,不得焊接,如若需焊接必须事先获得业主的批准认可,方可施焊,焊接必须牢固可靠,且要对施焊的部位采用防腐处理;The support of cable tray connect to all kinds of steel structure with bolt , not allow to weld. The welding o25、f brackets and supports with structural steel shall be approved by the Owner ahead of time and the welding shall be reliable and will be done anti-corrosive treatment for the welding point.5.2.5 桥架连接应使用桥架厂家的连接片通过螺栓连接。螺栓应带有平垫片和防松垫片,The cable trays shall be bolted with each other using the connection 26、pieces supplied by the cable tray manufacturer. The bolt shall have flat washer and spring washer;5.2.6 桥架与桥架支架的连接用专用的桥架压板,通过螺栓连接紧固; Special compressed plate will be adopted to connect cable tray and its support fastened by bolt.5.2.7 所有用螺栓紧固的材料、设备,在紧固前必须在螺杆上涂层放防卡剂; All kinds of material and equipme27、nt with bolt fastening should coat anti seize agent in the screw before fastening.5.3 电缆桥架敷设在易燃、易爆气体管道和热力管道的下方,与管道的最小净距应符合下表:The minimum clearance between the cable tray laid under the inflammable and explosive gas piping & thermal piping and the piping shall comply with the following table:Piping C28、lassification管道类别Parallel Clearance (m)平行净距(m)Overlapping Clearance (m)交叉净距(m)Common Piping一般管道0.40.3Inflammable, Explosive Gas Piping易燃、易爆气体管道0.50.5Thermal Piping热力管道With Insulation有保温0.50.3Without Insulation无保温1.00.5不符合上述要求时必须加装隔热板;Thermal baffle will be installed if not in line with above require29、ment.5.4 不同防火区的桥架,应按设计要求,采取防火、隔离措施;Fireproof and isolation measures shall be taken for the cable trays laid inside vertical shaft or across different fireproof areas;5.5 对于SPCII厂房内部所有600mm宽的桥架,必须在桥架内敷设一根95mm2的裸铜绞线作为接地线,然后分别与SPCI主桥架内95mm2的裸铜绞线相连接,对于主管廊上的桥架,应在最上层电缆桥架内敷设一根95 mm2的裸铜绞线作为接地线,并且分别与全厂接地网连接。30、电气桥架必须有良好的电气通路,桥架两端并且每隔30m做一次接地线;95mm2 bare copper stranded wire as a earthling line will be laid in all 600mm cable tray inside the SPCII workshop and connected to another 95mm2 bare copper stranded wire in the SPCI cable tray. A piece of 95 mm2 bare copper stranded wire as a earthling line will be31、 laid in the top cable tray of outside pipe rack and connected to main earthling net of factory. All cable tray should have good electric conductivity and earthling wire will be installed in each 30M in the cable tray.5.6 安装结束后保证桥架不应有明显的波形弯或蛇形弯。在电缆安装结束后,主管廊最上层桥架应盖上盖板,厂房内部600mm宽的电缆桥架需加盖板,300mm宽度及以下无需32、加盖板;After completion of cable tray installation, it shall be ensured that there is no visible wave or snake type curve. After cable installation, the top cable tray shall be covered with plate;、 桥架施工工序Cable tray installation procedure施工准备Preparation for installation支架预制Support pre-fabrication支架安装Sup33、port installation 桥架预制Cable tray pre-fabrication桥架安装Cable installation接地线安装Earthling wire installation 、 施工详细描述Installation description7.1 施工准备详见第4条;Preparation for Installation see above item 47.2 桥架支架预制Support of cable tray pre-fabrication7.2.1 根据桥架施工图,合理安排桥架支架安装位置,标注好桥架支架安装的具体位置,计算出每根支架的尺寸,在事先选好的34、C型钢材上标出相应的位置;标出后统一拿到预制场地加工,严禁在现场加工支架.对于装纳电缆容量大的桥架应选用背靠背叠在一处的C型钢支架,增强支架强度;We will arrange the reasonable location of support of cable tray and make label when we install it according to cable tray drawing, We will also calculate each support size and draw detail position in the C steel we selected in35、 advance. After finishing position in the c steel, support will be made in the pre-fabrication shop and avoid making support in the installation site. Double C steel support of back against back installed is adopted for heavy load cable in the cable tray in order to reinforce strength. 7.2.2 切割时用砂轮切36、割机切割,严禁动用气焊、电焊切割,然后清除毛刺,并打磨光滑;Abrasive cutting machine will be used to cut support of cable tray and it is forbidden to use welding machine to cut. after finishing cutting, removing burrs and make it smooth.7.2.3 对预制加工部位喷上镀锌漆,并对预制好支架做好标识;Galvanized lacquer will be sprayed in the processed part of su37、pport, sign will be made and put in the processed support.7.3 桥架支架安装;Installation for support of cable tray7.3.1 对于建筑物内安装的桥架,应在桥架末端和变高处先安装桥架支架;The end and elbow position of cable tray as well as the place height varied will be installed support first according to design requirement.7.3.2 然后在同一水平长度段,38、以不超过20m为一间隔先安装首尾两个立柱,然后拉一直线,以此线为参照安装中间其他立柱;Each 20M of cable tray firstly install two hanging bracket for the both end in the same horizontal length of cable tray , then draw a straight line, refer to this strait line, other support can be installed between these two hanging bracket.7.3.3 对于安装在钢结构上的39、支架,直接用卡扣卡在钢结构上,用螺栓紧固,不得焊接;Support installed in the steel structure will be used clamp and bolt to install not allow to welding.7.3.4 吊顶安装在楼面的支架,先标出需要打眼部位,用冲击电锤钻出合适的孔洞,通过内膨胀螺栓固定预制好的支架;If bracket need to install in the structure ceiling, firstly draw hole position and make hole with electric punch ham40、mer drill, then bracket be fixed by expansion bolt.7.4 桥架预制Cable tray prefabrication7.4.1 桥架预制都在预制场地进行,预制桥架过程中,只允许用切割机进行切割,严禁用电焊、气焊切割,切割完后清楚毛刺并打磨光滑;the cable tray will be prefabricated in the prefabrication shop. abrasive cutting machine will be used to cut prefabricated cable tray and it is forbidd41、en using welding machine to cut. after finishing cutting, removing burrs and make it smooth.7.4.2 Galvanized lacquer will be sprayed in the processed part of cable tray.对于镀锌桥架,应在预制处喷涂镀锌漆;7.4.3 不准用电焊直接把两段桥架焊在一起;It is forbidden to connect two cable tray with welding method.7.5 桥架安装Installation for cab42、le tray7.5.1 桥架安装前应尽量在地面进行预组装;对于管廊处大跨距桥架,直接在支架上安装;The cable tray will be assembled in the floor as best as we can before installation.7.5.2 在地面预组装完后,将桥架架上托臂,把桥架调整水平,然后用压板固定;After finishing assemble, cable tray will be put on the bracket arm, then make leveling and fixed by clamping plate.7.5.3 桥架固定应43、牢固,连接无错边,连接板螺栓应紧固且螺母应位于桥架槽的外侧,螺帽应安装在内侧。The cable tray will be firmly fixed, there is no change in the connection joint; bolt will be tighten in the connection plate and nut will be outside in the cable tray, head of bolt will be inside in the cable tray.7.5.4 连接螺栓前应在螺栓上喷上防卡剂;Before connecting bolt, 44、anti block agent will be sprayed in the bolt.7.5.5 同一水平面桥架水平度要一致、无变形,多层桥架间距应保持一致;The horizontality should be the same in the same horizontal and no deformation; The distance of cable tray between layer should keep the same.7.5.6 桥架穿越楼板洞、墙洞,应用防火胶泥密封;Cable tray through floor hole and wall hole,fire pr45、oof clay will be used to seal hole after cable to be laid.7.6 桥架接地线敷设Laying earthling wire of cable tray.7.6.1 桥架安装完后,应对桥架做接地处理,详见第5.5条After cable tray be installed, earthling of cable tray will be done according to technical requirement. see item 5.5、 施工注意事项及措施Construction precaution and measuremen46、t to be taken8.1 SPCII电缆桥架安装大部分是在生产与施工的环境下同时进行,务必要求所有进入生产区域现场施工的人员不得接触任何与施工无关的设备,并且严禁碰撞生产设备、管线,施工用的材料只能堆放在指定的场所,当日施工结束后,必须清扫干净;In SPCII project, cable tray be installed is under production and operation environment in the same workshop, It is required that all construction people can not touch any i47、rrespective equipment with construction and forbidden to hit any production equipment and pipe. The material using for construction only put appointed site. Work finished every day, construction site should be cleaned.8.2 生产区域内介质都为有毒的液体、气体或粉末状物质,在建筑物内生产区域施工时,应设置警戒线,只能在规定的警戒线范围内施工;从管廊进入B204区域桥架施工时,应在48、施工区域内搭设防护栏,并且派专人看管,施工时严禁动用电焊或气焊;There are a lot of poisonous gas and liquid material in production area, guarding line will be set up in construction area of inside building. Construction only be made within stated guarding line. When cable tray be installed from outside pipe rack into B204 area, gu49、ard rail will be established in this construction area and should have person to be in charge. Welding will be prohibited in the construction. 8.3 在防爆区域内施工时,要求所有施工用电器设备都具有防爆功能,所用的临时施工电源要求使用防爆插座,并配置防爆插头;When construction made in the anti-detonation area, It is required that all electrical appliance f50、or construction should have explosion proof function and all temporary power should use explosion proof receptacle and plug.8.4 在生产区域施工时,施工用电源线不能直接跟运行设备、管线接触,应加工电缆挂钩挂临时电源线,挂钩也不能挂在设备及管线上,并且挂钩上应用塑料套管隔离。When construction made in the production area, power cable for temporary construction can not touch 51、operation equipment and pipe. Leased clamp be used for hanging the temporary power cable and can not hang on the equipment and pipe.8.5 在对有电缆在内的桥架开槽时,应把运行电缆隔离开,严禁损坏一期原有电缆,采取的防护措施如下:在需切割的部位事先放上C形状的薄铁板,然后用防火布覆盖,并且在桥架下方铺设一层防火布,再用砂轮切割机切割,切割后清除毛刺,并打磨光滑;When we need to make duct in the cable tray with liv52、ing cable, cable with electricity will be unplugged and not allowed to damage existing cable, measure will be taken as follow: the places we need to cut should put a pieces of C type thin steel plate in advance, then cover a piece of fire proof cloth on the steel plate and put fire proof cloth under53、 cable tray at the same time, then we can cut hole with abrasive cutting machine , after cutting, remove burry and make it smooth.8.6 从B196至B204厂房间的桥架都位于室外管廊上,且属于高空作业, 除了遵守相应的高空作业规定外,雾天、雨天应禁止在管廊上施工作业;Some installation from B196 to B204 in the outside pipe rack is aloft work, except following relevan54、t regulation of aloft work, it should be prohibited in the rain and fog weather.8.7 在生产区域施工时,禁止利用原有的电缆桥架、工艺管线或风道及设备来搭设跳板,严禁踩踏;It should be prohibited to use exist cable tray and pipe or ventilation duct to set up sleeper and to trample the equipment in the production area.8.8 在生产区域动火作业时(包括用电锤、电钻、磨光机55、等用电设备)必须有专人监护,且必须事先准备好消防器材; There are special people to supervise when hot work( including using electric hammer and drill as well as grater etc ) to be done in the production area, at the same time, fire-fighting apparatus will be prepared in advance.8.9 在B196、管梁上、B204生产区域内施工时必须开操作票,办理工作许可证,无证严禁施工 56、Before job performed in the B196 area, outside pipe rack, B204 production area, operating sheet and permitting work certificate should be done, if no this kinds of certification, it is prohibited that not allowed to work in above area. 9、 施工特别措施Special measurement to be taken in construction9.1 在B1957、6区G36G37轴线安装时,在+6.75米处用900150桥架同原有预留桥架连接,通过管廊钢梁做支架立柱,把C型钢用卡扣固定在钢梁上做桥架支架,升至14.0米后跟NO. 1.7桥架支架处桥架连接,连接时需在桥架开槽,开槽时应参照第8.5条;在施工作业前,需搭设脚手架,脚手架操作平台搭设区域见附图1,样式图见附图2;When we install cable tray at axis of G36-G37 in B196 area, 900x150 cable tray will be connected to exist 900x150 cable tray at +6.75m, using 58、clamp to fix C steel as bracket to the steel beam of pipe rack, then install vertical cable tray up to 14.0m and put cable tray on NO.1.7 bracket and connected to exist cable tray. When cable tray need to be connected to exist cable tray, sometimes we need to make hole in the existing cable tray, me59、thod refer to item 8.5 Scaffold have to be established when construction to be made at axis G36-G37 in the B196 area. Operation platform position of scaffold see attached diagram 1, pattern see attached diagram 2.9.2 在管廊G9G12区施工时,需在+14.4米NO.2.7层支架上桥架开600150槽,开槽注意事项同前,整个作业在管廊高空作业,且原有桥架密集,施工时注意别碰撞桥架、管60、路。安装管廊大跨距桥架时,先用叉车把桥架运到G9轴线处位置,然后用16T吊车将桥架吊至管廊顶上的G9轴至G10轴线间,吊装完一段桥架应立即沿着搭设的脚手架操作平台,用人工拉至安装的合适位置,然后再吊装另外一段桥架。安装时先沿着NO. 2.7层支架安装至G10轴线,再从G10轴线处爬至顶层,从G9轴线用直角弯敷设至NO. 1.8层支架,再降至NO. 1.4桥架;在吊装前应在需安装桥架的上层桥架底处铺设层薄木版,避免在吊装及运输时损伤原宥电缆,并且在管廊上运输、安装桥架过程中,施工人员必须带好安全带, 安全带卡扣不得挂在管线、桥架、阀门等设备上。管廊G9G12区需搭设脚手架搭设的脚手架操作平台区域61、见附图3,样式图见附图4;When cable tray to be installed in G9-G12 area of pipe rack, the 600x150 duct will be made in the existing cable tray of No.2.7 bracket at +14.4m, the precaution of making duct same as before. All outside cable tray installation is aloft work and existed cable tray and chemical pipe is 62、denseness, we will take some measure to prevent hitting and damage existing cable tray and pipe. When we install big span cable tray, first use fork lift truck move cable tray to the axis G9, then we use 16t crane to lift the cable tray to installed position, in this part, we lift the cable tray to 63、the scaffold platform between axis G9 and G10, then install step by step. First, install cable tray to axis G10 along No.2.7 bracket, then up to top of pipe rack from G10 till to axis G9 through right angle bend to No.1.8 bracket, then down to No.1.4 bracket. The thin wooden board will be fixed in t64、he bottom of cable tray which is up cable tray related to installed one before lifting in order to avoid damaging existing living cable. when moving and installing cable tray in the pipe rack, construction people must tie the safety belt, but hook of safety belt not allow to hang existing pipe, valv65、e, cable tray etc. Scaffold have to be set up at G9-G12 area in the outside pipe rack, Operation platform position of scaffold see attached diagram 3, pattern see attached diagram 4. 9.3 在管廊G6G9区需搭设脚手架,脚手架操作平台搭设区域见附图5,样式图见附图6;其运输及安装方法详见第9.2节;Scaffold have to be set up at G6-G9 area in the outside pi66、pe rack, Operation platform position of scaffold see attached diagram 5, pattern see attached diagram 6. The method of transportation and installation see item 9.29.4 从+12.5米2.3层管廊桥架返至B204区C轴D轴间+4.9米时,桥架安装从+4.9处往上安装,桥架支架尽量利用原有钢梁作支撑,避免在墙上打眼.当在室内动用用电设备时,应采用防爆用电设备,电源电缆避免跟原有管线接触,并且在下方铺设放火布;在B204一期工程C轴D轴67、间需搭设脚手架,脚手架操作平台搭设区域见附图7,样式图见附图8;Cable tray will enter into room of B204 between axis c and d from 12.5m No. 2.3 bracket of pipe rack down to 4.9m after finishing installation of outside pipe rack. The cable tray will be installed from 4.9m to up inside B204 room, we will use exist steel beam as supp68、ort and avoid to make hole on the wall of building. When electrical appliance to be used in construction, explosion proof equipment will be adopted and power cable will not touch any exist cable and pipe, fire proof cloth will be put under cable tray when installation. Scaffold have to be set up at 69、axis C-D in the B204 area of first term project , Operation platform position of scaffold see attached diagram7, pattern see attached diagram 8. 9.5 进入B204一期生产区作业施工时,应在施工区域内拉上警戒线,并搭设防护栏;安装桥架时,桥架应从里往外安装,以原预留的桥架连接;搬运时首先把桥架放至+4.9米处的脚手架操作平台,并在原预留的支架上铺上层防火布,然后沿着支架平拉至原预留桥架接口处,再取下垫着的防火布,固定桥架;在建筑屋内施工采用移动式脚手70、架;When construction to be done in first term project area of B204, pull guard line and set up safety rail in construction area;when cable tray to be connected from inside room to outside room, method is from inside room to outside room in order to connect to existing cable tray; when installation, w71、e will move and lift the cable tray to the platform of scaffold at 4.9m, then we put fire proof cloth on the existing bracket, pull cable tray in the horizontal direction to the existing duct of cable tray, finally take off fire proof cloth and fix the cable tray. Mobile scaffold will be adopted in 72、the room and not allowed to prefabrication and manufactory cable tray and support in the construction workshop. 9.6 在B204区+16.4米层横轴线间,纵轴线A轴以外需搭设脚手架,脚手架操 作平台搭设区域见附图9,样式图见附图10; Scaffold have to be set up at lateral axis 4-5 area in B204 16.4m and at direct- axis A outside, Operation platform position 73、of scaffold see attached diagram 9, pattern see attached diagram 10. 9.7 脚手架搭设立杆间隙不得大于1.0m,横杆间隙不得大于1.2m,每五米高要架设一 剪刀撑;The distance between vertical tube not more than 1m and between horizontal 1.2m, each 5m high need a bracing in establishing scaffold. 10、 脚手架搭设描述及注意事项 The procedure of setting up sca74、ffold and precaution10.1 脚手架搭设立杆间隙不得大于1.0m,横杆间隙不得大于1.2m,每五米高要架设一剪刀撑,并且在底端都应设扫地杆;在搭设脚手架过程中注意别碰撞原有桥架、管线及 设备 The distance between vertical tube not more than 1m and between horizontal 1.2m, each 5m high need a bracing in establishing scaffold and bottom beam needed in the scaffold; precaution will be n75、oted than not allow to hit and damage existing equipment, pipe and equipment when scaffold to be established. 10.2 G9G12轴脚手架是从管廊上开始搭设,搭设距地高度+15.0米;横向是与原钢隔板为底面在其上面搭设,纵向固定在管廊的钢梁上,在钢隔板上搭设的脚手架,架子管尽量靠北但不得触及原有桥架,然后在靠近北面桥架一侧的脚手架上铺设木板与原有桥架隔离;通过钢梁固定的架子管,在架子管与钢梁间应垫层木板,用铁丝绑扎结实;整个脚手架搭设完后,应在安装桥架的下方也铺层薄木板,达到保护原有的76、桥架及管线,安装完的桥架人不能在上面行走,不得把安装完的桥架作为人行通道。The scaffold which is +15.0m from ground is established on the outside pipe rack between at axis of G9 and G12 ; the horizontal tube be fixed on the existing steel partition board and vertical tube be fixed on the beam of pipe rack. when scaffold established on t77、he steel partition board, the scaffold will be close to north side as possible as we can ,but not allow to touch existing cable tray, then wooden board will be put in the north side in order to separate existing cable tray; If scaffold tube be fixed on the beam of pipe rack, wooden board will be put78、 between tube of scaffold and beam of pipe rack, then tied with iron wire; After scaffold is established, thin wooden board will be applied under cable tray in order to protect existing cable tray and pipe. Please note that not allow people to walk on the scaffold which have been established as a ac79、cess.10.3 G6G10轴脚手架是从管廊上开始搭设,搭设距地高度为+13.6米;横向是与原管道钢梁支架为底面在其上面搭设,纵向固定在管廊的钢梁上;搭设时先在管道钢梁支架上垫上方木块,再把预制好的架子管底板放在木板上,用铁丝捆扎牢固,然后插入架子管,另一端通过架子管固定在钢梁上; The scaffold which is +13.6.0m from ground is established on the outside pipe rack between at the axis of G6 and G10; the horizontal tube be fixed on the exi80、sting steel pipe bracket and vertical tube be fixed on the beam of pipe rack. When scaffold established on the steel pipe bracket, square wooden board will be put on the steel pipe bracket, then put prefabricated steel tube base board on the wooden board, tired firmly with iron wire, finally insert 81、the steel tube, another end of scaffold be fixed on the steel beam.10.4 进入B204区域桥架的脚手架搭设时,底层从+0.0米开时,搭设高度+13.2米,因原有管线、桥架较多,只能利用管线及桥架间空隙搭架子管,在搭架子管时注意不能碰到原有的管线、桥架,并且应在需穿架子管的管线上包裹层厚的防火布,在穿架子管顶端也应裹防火布,避免撞坏管线、桥架等;从+4.9米开始,每隔2米高搭设操作平台;When scaffold to be established in the outside of B204 area, the bottom82、 of scaffold is +0.0m and height is +13.2m. There are a lot of existing pipe and cable tray in this area, We are only able to utilize the gap between pipe and cable tray to establish the cable tray, It should be noted that construction worker not allowed to touch existing pipe and cable tray. Fire p83、roof cloth will be applied on the places where on the bottom of existing upper cable tray and on the existing pipe the area we need to install the tube .operating platform will be set in every other 2m from beginning of 4.9m in this area.10.5 附图2在管廊G35轴线南面做一爬梯通道,爬梯一直搭设至管廊+11.0米处,人可 经过B196处的钢平台通至B20484、区,因管廊+11.0米处的钢平台通道没有护栏,必须事先在过道两边拉上钢丝绳,作为临时护栏,且人在上行走时,不得接触管廊上的桥架,并且挂上安全带;附图8脚手架通道可用搭设的脚手架,在脚手架上每隔300mm高固定一架子管;附图8通道搭在东面;详见图;A ladder for access will be made in the south side of axis G35 in the outside pipe rack, see attached diagram 2, this ladder is up to elevator +11.0m, and thus people can walk f85、rom steel platform of B196 to B204 area. Because there is no guard rail in the steel platform of pipe rack at +11.0m, we will pull wire rope in both side of catwalk as a temporary safety rail. when people walk on this catwalk, they have to hang safety belt and not allow to touch existing cable tray 86、in the pipe rack. Established scaffold can be used for access in attached diagram 8 and steel tube in every other 300mm height fixed in the scaffold ; the access will be built on the east side of the axis of G36 in the attached diagram 8,see detail diagram as follow:附图1:(attached diagram 1) 11、(JHA)87、工作安全分析编号No.:工作名称Work Description:电缆桥架预制、安装及脚手架搭设 Cable tray and support fabrication, installation and setting up scaffold 参与分析人员Attendee: 艾禄芳、章新华、宋建平、谢治中等分析日期Date: 审核人Reviewed by:批准Approved by:必须采取的个人防护设备Necessary people protection equipment:1:安全帽Helmet 2:安全眼镜Safety glass 3:工作鞋Work boot 4:工作手套Work g88、love 5;安全带Harness 施工使用主要设备、工具Main equipments and tools using in construction吊装带 lifting belt, 扳子 spanner、脚手架管 scaffold tube, 卡扣 clamp, 跳板sleeper、砂轮切割机abrasive cutting machine 、磨光机grinding machine 、电钻、electric drill 电锤、electric hammer防爆电气设施 explosive proof electric appliance.主要工作描述:main job工作地点:厂区的桥架89、施工,包括管廊桥架的施工、B204区域桥架施工、B252区域桥架施工及其它区域桥架施工。Location:Construction of cable tray include outside pipe rack area, B204 area, B252 area, other area which need to install cable tray.工作内容: SPCII/成品包装仓储系统二期项目整个厂区的桥架施工,包括管廊桥架的施工、B204区域桥架施工、B252区域桥架施工及其它区域桥架施工电缆桥架的预制、安装。安装电缆桥架时需在管廊的钢平台上搭设工作平台。Scope of work:90、 Cable tray and support fabrication and installation in SPCII above area. when cable tray to be installed, in some places, scaffold need to be set up, especially on the outside steel piperack.基本工作步骤Basic work sequence潜在的危险因素Potential work hazards造成危险的原因Causes必须采取的预防措施或操作步骤Precautions or operation se91、quences adopted necessarily1检查电动工机具、脚手架管、卡扣。Checking electric power machine and tool, chain block, scaffold tube and clamp1吊具损坏造成吊物坠落。Lifting devices are so damaged that the object falls off2工机具损伤造成工作中断或人员伤害Tools and equipments crack down causing work stop and injuries. 1对使用的吊具和工机具没有进行安全检查do not saf92、ety inspect the cranes, lifting devices, tools and equipments.2.没按要求进行检查 Not check according to requirement1吊装前对使用的吊具和工机具进行安全检查,检查内容:砂轮切割机、电钻、电锤、吊装带等,不合格和报废,使用符合的吊具和工机具。Prior to lifting, check lifting tool and machinery for safety, including abrasive cutting machine, grinding machine ,electric drill93、, electric hammer, chain block, lifting belt, abrasion, damage, defect and obsolescence, to make sure all tools satisfy safety requirements2对人员进行审核,作业前对所进行的工作进行工作技术交底before starting confirm the qualification of the workers and hold technical meeting1人员操作不正当造成设备工机具损伤或人员伤害causing injuries and damages 94、to the equipments by bad operation2在管廊上作业时施工人员磕碰运行的管线,造成停车或人员伤害When construction people work in the outside pipe rack, pipe and cable damaged by worker and cause injuries equipment not work.1使用不合格的操作人员unqualified operators2作业前没有进行技术交底,工作盲目造成安全事故Commencing the work without pre-work technical meeting 95、causes accident.1工作前对工人进行审核,工作前对工作人员进行技术交底。作业时要进行安全教育,对所要工作的区域的潜在危险进行剖析。interview the workers and hold the technical meetings before starting the work making sure they all know the potential hazards and precautionsSafety educates the workers before starting work.2在作业过程中不要动运行中的管线,有滴水的地方切勿靠近,以防有害液体。Do96、 not touch the living equipments and pipe as well as cable during work. Do not get close the dropping area to keep away the hazardous liquids.3所有人员要知道应急程序,并知晓工厂的逃生应急路线。All working staff should not the emergency procedures and excavation route.4所有在B204施工人员不得携带手机等电子产品关闭。All working in B204 should not 97、bring such electronics as cell phone.5各负责人员和安全监督人员都应知道工厂应急电话67121415 every responsible personnel and safety personnel must know the emergency call 67121415.3脚手架平台搭设Scaffold platform erecting1伤害 injury2脚手架扭曲变形,倒伏。Scaffold twist and fall down.3高空坠落people falls from high4高空落物,材料滑落,安全帽跌落,脚手架杆滑落,卡扣跌落obje98、cts fall from high such as material, helmet, scaffold pipes and clamps.5杆倾倒 standards are not straight, incline.6每天进到工厂施工点是否有自检。Self inspect the scaffold the first thing get to site.1交叉作业,没有进行维护 cross work and without maintenance.2没有矫正 without correction3没有挂安全带没有护栏,上下攀爬时手没抓牢,工作平台跳板没有满铺 ,跳扳未绑扎。Failur99、e to tie safety belt, lack of guardrail, failure to firmly grasp frame tube when climb up & down, failure to fully pave catwalk, failure to tie catwalk up.4剩余材料没有清干净、材料没有固定,没有系帽带,手没有抓稳,小的物件没有装在容器里。Doesnt remove the remain materials, and the material is not fixing on the scaffold. Without tying helme100、t belt. Do not grasp the scaffold pipes firmly. The little pieces are not collected in the container.5绳索没有绑牢。The rope doesnt tie firmly.6发现泄漏要撤离。Withdraw while noticing leak7未设立警戒区 Not establish guard line area8脚手架地基未按要求进行处理 The foundation of scaffold not disposal according to requirement9未正确使用PPE N101、ot use PPE correctly1设足够距离的警戒维护区,设专职安全监督。Setup barricade with enough room, appoint special watcher to supervise.2尽量避免交叉作业,必要时有安全保护措施。Try the best to avoid cross working and provide safety measures if necessary.3每搭设一步都要进行矫正,确保横平竖直,架杆不许有缺档现象。Very step should inspect and make correction if needed to ma102、ke sure it is straight and level. Transoms and standards must not be missed a single one.4搭设中安全带要100%的系挂在牢靠的物体上。While erecting, apply full harness at one hundred percent time tying to firm object.5上下攀爬时手中不允许拿东西,要使用绳索运送材料和固定材料,严禁抛扔任何物件。Should not carry things when climbing up and down. Use rope to li103、ft the material which should be fixed. Through away any object is forbidden.6脚手架工作平台要满铺,搭设护栏,搭设挡脚板。The thick board will be put all the platform of scaffold, setting guard rail and skirting board in the scaffold.7剩余的材料及时清理下去。Clear up the remain material in time8系好安全帽带,防止安全帽跌落,个人头部瞬间失去安全帽保护和帽子下落伤害他人。T104、ie the helmet firmly to avoid falling off hurt some one and leave oneself in danger. 4拆除作业 dismantling work1磕碰、挤压、管线、管件。Hitting and compressed, extruding pipe and cable.2高空坠落坠物falling from height.1交底不清楚,工作准备不充分,警戒维护不到位。Unclear technical handover, inadequate preparation and barricades2区域维护不到位 。the li105、fting area is not maintained completely 3没有穿戴好个人PPE 。PPE isnt applied fully.4使用的工具随手乱放. Put the tools disorderly.5为按要求拆除作业Not dismantle relevant thing according to requirement 1工作前检查个人PPE,作业区域作好警示维护,设专职安全员进行看护。拆除前做临时护栏或铺设好作业平台并挂上警示标志。Before work starts, re-check the PPE, maintain and separate the wo106、rking area by appointed a safety professional. Setup barricade temporarily or build work platform for dismantled area and hang warning signs before work.2避免交叉作业,拆除作业区域下严禁站人和行走。底下设置隔离区,指派监护人员。如底下有设备,则须对设备进行保护,搭设保护平台。Frees of cross work. No people are allowed to stay and walk under the dismantling are107、a. Under it set up isolated zone and appoint safety watcher. If there are equipments below, a protective platform shall be needed.3要使用双背式大挂钓双钓安全带。并要有稳固的挂靠点。While working, apply one hundred tied off measure with full body double big hooks harness. There shall be firm hook point for harness; if necess108、ary.4工具必须放在工具袋里面. All tools should be put in the bag.5吊运电缆桥架、架子管、跳板,登高作业。 Lifting cable tray, sleeper, shelf tube and aloft work .1磕碰、挤压、管线、管件。Hitting and compressed, extruding pipe and cable.2吊物倾斜。Lifting object incline3吊物晃动.lifting object swings 4高空坠落坠物falling from height.1交底不清楚,工作准备不充分,警戒维护不到位。Un109、clear technical handover, inadequate preparation and barricades2管线、管件碰坏造成有毒有害气体泄漏,导致人员伤亡。Pipe to be damaged and cause hazardous gas leakage and worker injuried.3吊运时有交叉作业。人员站位不恰当。场地陕小,吊运时与现场设施相碰。Cross working while lifting. Work staffs stand in the wrong position. No enough room for lifting causing c110、ollision with site facilities.4吊绳没有系到物体的重心位置。Without hemp ropes or the hemp ropes dont tie to the gravity point.5.吊装区域维护不到位 。the lifting area is not maintained completely 6没有穿戴好个人PPE 。PPE isnt applied fully.7两个人配合的工作没有沟通好。Doesnt communicate well with colleague when works8对吊运前的安全检查不到位。Doesnt do safet111、y inspection completely before lifting.9使用的工具随手乱放. Put the tools disorderly.1工作前检查个人PPE,吊运区域作好警示维护,设专职安全员进行看护。Before work starts, re-check the PPE, maintain and separate the lifting area by appointed a safety professional. 4在吊运过程中,应尽量避免冲击和震动. During lifting to avoid impact and shake as much as possi112、ble. 5工具必须放在工具袋里面. All tools should be put in the bag.6吊装过程中应设立牵引绳 The traction rope will be set in the process of lifting6焊接、切割welding & cutting打磨Grincling1 火花飞溅烫伤。Get burn by sparks2 轮机的伤害。Injury by grinder disc3 触电。shock4 火灾。fire5 弧光伤害。Arc injury1个人防护用品穿戴不齐全,焊接站位不正确。PPE isnt applied completely. T113、he welding position is not correct.2没有设置警戒区域,维护不到位造成闲人误入。The working area isnt barricaded and maintained that people no concerned enters by accident. 3磨光机不使用时磨口朝上,不小心碰到开关,the grinder should stands with the grinding opening up and is switched on cautiousness less.4电缆漏电,保护装置失灵,电源线破损。the cable become c114、reep age, the protection device malfunction and the power wire disrepair5地下有积水电源线没有架空,砸断电缆。The power wire isnt put in air while the ground is wet. The cable is broken.6周边有易燃物,动火没有灭火器,Combustible is around and no fire extinguishers nearby while hot working. 7动火前要检查一下周围。Inspect the surrounding before 115、starting hot work8防火措施没有作好。Fire protection measures are not prepared and followed well.9所有的工机具应经过合格的人员检查,合格后贴上色标。All tools and equipments should be inspected by qualified personnel and be color coded afterwards.10不按要求使用 Not used according to safety requirement1 穿戴好个人PPE,焊接时身体要避开火花下落位置。Apply full PPE116、. The body should be kept away from the sparks drop place2 围好警戒区域无关人员要远离。Barricades the working area and no entry for unauthorized personnel.3 使用完磨光机后,磨口向下放置,拔掉电源。After using the grinder the side with the disc should be down. And shut the power4经常检查电气开关,漏电断路器要始终处于良好的状态。Frequently inspect the electri117、c-gas switch, breaker should be always in good condition.5.配备有效的灭火器。Fire extinguishers and sparks free blanket should be equipped.6动火要有专人监守。Assigned fire watchman for hot working.7焊接时设挡光板,多人焊接拉开距或有遮挡隔离措施。Setup arc screen. When multiple welding, the working positions should be keep certain distance o118、r be isolated with shield measures.8使用合格的砂轮片,清理有缺陷的砂轮片并与磨光机匹配,打磨焊接区域,设立防护屏。Isolated grind and weld area by protection screen; Remove defective disc and follow the disc technical description; using face shield when grinding. 9非电工人员严禁私接电源7钻孔 Drilling 1触电伤害electric-shock injuries2火灾fire3电钻伤害Injury by d119、rill4金属铁屑飞溅伤害Injury by scrap iron1电线破损power line damage 2使用前没有检查电缆线。Use the lines without inspected3.钻孔时身体姿势不正确. While drilling holes, the body stands wrongly. 1电线破损power line damage 4.个人防护用品穿戴不齐全,钻孔作业时戴手套PPE incomplete and drilling operation with gloves5操作方法不当 Operating method not correct6未按安全操作规程操120、作 Not done according to safety rule requirement1.经常检查自己使用的电源线的外观,使用时电源线架空, 确保电缆不漏电。Often inspect the outlook of the power line that used. Put on air the power lines when using making sure not electricity leakage.2.使用手持电钻时手扶固定物,以免滑偏人受到闪失或碎石打伤人员。使用电动工具贴标hold tightly the electric hammer to avoid hammer121、 slippery injure people or split gravel bits the people. Stick the electric tool sticker3指派合格的监火人员和安全监督人员。做好维护工作,四周围好防火布。不许无关人员进入。Assigns qualified fire watcher and safety watchman. Set up barricade and round up four sides with fire retardant blanket. Authorized people entry only. 1.经常检查自己使用的电源线的外观,122、使用时电源线架空, 确保电缆不漏电。Often inspect the outlook of the power line that used. Put on air the power lines when using making sure not electricity leakage.4.使用电锤时手扶固定物,以免滑偏人受到闪失或碎石打伤人员。使用电动工具贴标hold tightly the electric hammer to avoid hammer slippery injure people or split gravel bits the people. Stick the 123、electric tool sticker5指派合格的监火人员和安全监督人员。做好维护工作,四周围好防火布。不许无关人员进入。Assigns qualified fire watcher and safety watchman. Set up barricade and round up four sides with fire retardant blanket. Authorized people entry only.6穿戴好个人PPE,钻孔时严禁戴手套Put on PPE, no gloves when drilling.8文明施工. Work educated.文明施工隐患. Wor124、k hazards without working educated.1,带班人员没有负起责任,监督不到位. The foremen do not shoulder their duties. Supervision isnt completely carried out.1带班人员要把要求讲清楚,并带领工人一起清理现场各种工具,机具和索具等。要做到工完,料尽,场地清。The foremen dont make themselves understood basing on the requirements and lead the group to clean the site all th125、e tools, equipments and ropes catching up the saying when the work done the material should be used up and the site clean.2清扫施工场地,清除施工垃圾. Clean up the construction site and clear up the garbage. 3设备就位后注意维护工作,保护成品。 When the equipments are perched the maintenance should be followed up to protect the equipments.