保利家园二期砖砌化粪池施工方案打钢板桩.doc
下载文档
上传人:地**
编号:1191814
2024-09-20
128页
12.93MB
1、保利家园二期化粪池施工方案目录一、工程概括.2二、编制依据.2三、钢板桩支护的设计方案.3四、钢板桩施工方法.5五、施工措施.6六、附图.16.一、工程概况保利家园二期共有5个化粪池两种型号。选用标准图集:(02S701)来进行施工, 其中10号化粪池选用有地下水、有覆土型、可过汽车(Z10-40SQF)化粪池有效容积为:40立方米;13号砖砌化粪池,选用有地下水、有覆土型、可过汽车(Z13-100SQF),化粪池有效容积为:100立方米。其中需要打钢板桩的三个化粪池一个位于10-1#号楼北面(10#号 Z10-40SQF)、另外两个位于5-1#北侧(13#号Z10-100SQF)及(10#号2、 Z10-40SQF),另化粪池所需要用到管材品牌为联塑牌。二、编制依据、建筑地基基础工程施工质量验收规范GB50202-2002;、混凝土结构工程施工质量验收规范GB50204-2001;、砌体工程施工质量验收规范GB50203-2002;、建筑给水排水及采暖工程施工质量验收规范GB50242-2002;、地下防水工程质量验收规范GB50208-2002;、标准图集02S701砖砌化粪池等;化粪池位于佛山市顺德区龙江镇东华路57号保利家园二期工程,顶板标高为黄海高程5.6m。工程所在地地质情况:化粪池所在区域从上往下为素填土、淤泥质土、粉砂、粉质粘土。其中素填土均匀分布,呈灰黄色、松散、平均3、厚度约为3.1m,淤泥质土呈深灰色、流塑、平均厚度约为3.0m,粉砂呈灰色、松散平均厚度约为4.6m,粉质粘土呈青灰色、平均厚度约为2.6m。原地坪高程为黄海高程4.0m,化粪池出水口标高为黄海高程3.3m,槽底标高为0.7m,挖土深度为4m。地下水位为黄海高程1.272.48m。三、钢板桩支护的设计方案3.1钢板桩的选用根据工程所在地场地特点,结合钢板桩的特性、施工方法等方面进行考虑,选用25#C钢板桩,25#C钢板桩宽度适中,抗弯性能好,依地质资料及作业条件决定选用钢板桩长度9m长,要求钢板桩入土深度达2m以上。3.2钢板桩理论用量计算:钢板桩施打采用密打方式,每米4根,离开化粪池施工外边4、2m。3.3钢板桩井施工顺序:钢板桩打设开挖基坑集水井降水圆木支撑底板施工。3.3.1、密打钢板桩(1)钢板桩选用6米25#C型槽钢,用220履带挖掘机机打桩。(2)据现场的条件,选择一块平整、坚实的场地,按堆放的顺序、位置、与平面布置施工方便、便于吊运。(3)施工定位为使钢板桩打设位置准确,在地平上根据控制轴线定出位置,放线标出插入位置、间距。打桩时必须根据水准点控制标高。(4)钢板桩施工方法A、根据定位放出钢板桩插打的角桩,放出灰线。B、钢板装施工时采用单独打入法。C、打桩时,钢板桩不能倾斜、扭曲、凹凸不平,施工时要确保精度,垂直度应控制在1%;桩顶标高必须控制在10mm;板桩轴线偏差控制5、在10mm。3.3.2、开挖基坑用220履带挖掘机挖土装车, 自卸车土方外运。3.3.3、集水井降水基坑开挖应设置集水井,收集基坑内地下水,根据出水量设置抽水机,设专人抽水。3.3.4、铺设垫层及混凝土底板垫层采用20cm碎石+10厚C15砼+20厚C25钢筋砼。 因化粪池位于淤泥层,且处于地下水位以下,为减缓沉降,加快排水,化粪池增加20CM厚度的碎石层。在铺筑垫层时,应确保井底内无积水、无流砂、无翻浆等现象。垫层应做到平整,必要时应用水平仪抄平,保证垫层的水平。垫层铺筑完成后,即可在其上绑扎底板钢筋,浇捣底板混凝土。 四、钢板桩施工方法1)钢板桩的检验用于基坑临时支护的钢板桩,进行外观表面6、缺陷、长度、宽度、厚度、高度、端头矩形比、平直度和锁口形状等检验,对弯曲变形、严重锈蚀、外观尺寸等不符合规范要求的钢板桩不得进场使用,对桩上影响核打设的焊接件割除(有割孔、断面缺损应补强)。有轻微锈蚀,量测断面实际厚度,予以折减。2)钢板桩施工打桩时,开始打设第一、二块钢板的打入位置和方向要确保精度,每打入1m测量一次。(1)要求钢板桩适用于埋深较浅的支护结构。钢板桩沉桩适用粘性土、砂土、淤泥等软弱地层。钢板桩沉桩施工先试桩,试桩数量不小于3根。钢板桩放线施工,桩头就位必须正确、垂直、沉桩过程中,随时检测,发现问题,及时处理。沉桩容许偏差:平面位置纵向100,横向为-500;垂直度为5。沉桩施7、前必须平整清除地下、地面及高空障碍物,需保留的地下管线应挖露出来,加以保护。基坑开挖后钢板桩垂直平顺,无严重扭曲、倾斜和劈裂现象,锁口连接严密。基坑土方和结构施工期间,对基坑围岩和支护系统进行动态观测。发现问题,及时处理。(2)钢板桩的拔除基坑回填土时,拔出钢板桩,修整后重复使用。拔除前要注意钢板桩的拔除顺序、时间及桩孔处理方法。拔桩时会产生一定振动,如拔桩再带土过多引起土体位移、地面沉降,给已施工的地下结构带来危害,影响邻近建筑物、道路和地下管线的正常使用。拔除钢板桩采用钢丝绳与大型挖掘机机配合拔除。五、施工措施 结合本工程实际情况,确定工程施工工艺顺序如下:基坑底部清槽混凝土垫层池壁范围内8、满堂红脚手架搭设砌筑池壁砖墙化粪池顶盖及圈梁支模、绑筋、浇注混凝土化粪池顶盖预制板制作化粪池顶盖拆模抹化粪池内、砂浆外壁涂防水水泥基土方回填化粪池预制顶盖安装。根据本工程特点各分项工程确定如下施工方案:1、砌体工程、砌筑砂浆采用M10水泥砂浆,中砂含泥量不大于3%。所用砂浆要随用随拌,砂浆稠度为70-100MM,并要在3-4小时内用完,砂浆所用砂、水泥变动时,要及时调整配比。、砂浆拌和采用重量比,配料误差在2%以内,用搅拌机拌和,先在搅拌机内注入适量的水,再按配比依次投入水泥、砂、水。搅拌时间自投料完毕算起,不得小于120秒钟。、砌块采用规格为240*115*53mm水泥砖,强度等级MU10。9、设计墙体宽为620mm、480mm。砌砖前一天,把砖浇水湿润,严禁干砖上墙,吸水深度控制在15MM以上,防止湿润不均或过湿现象。、砖砌体要上下错缝,内外搭砌,组砌方式为一顺一丁,砌筑时采用“三一”砌砖法,杜绝缩口灰和板凳灰,水平灰缝的砂浆要饱满,饱满度不低于80%竖向灰缝采用挤浆或加浆方法,不得出现透亮灰缝,水平灰缝厚度控制在102mm。落地灰在初凝前回收,重新搅入新砂浆中使用。、砌第一皮砖前,当基础混凝土表面高低差大于20mm时应把上表面用20砼找平,找平后再砌,砌砖完后用笤帚扫净墙缝。、砌砖前应先立好皮数杆,撂摆底砖,防止游丁走缝。皮数杆立在墙的大角处,内外墙交接处,纵墙皮数杆间距不大于110、2M。、撂底砖经检查合适后,挂通线,砌底砖时,应跟线,双面挂线,撂底砖后进行盘角,盘角每次不宜超过5皮高,并用靠尺,线坠,水平尺找平找垂直,每皮砖的高度对准皮数杆,按盘好的墙角为准,挂线砌砖。、砌筑过程中,应经常检查并做到:、墙大角和墙面垂直准确。、五皮一吊线,三皮一靠尺。、砌筑过程中,必须丁砖压顶,沿墙面每隔一定间隔的竖缝处,弹出墨线,墨线用经纬仪或线锤引测,砌一步架,上引一次,控制游丁走缝。2、钢筋工程2.1材料要求底板、盖板、圈梁钢筋采用HPB235、HRB335两种规格。(1)、钢筋出厂合格证和复试试验报告结论均要符合设计和规范要求。 (2)、成型钢筋、2022号火烧丝、水泥砂浆垫块(11、或塑料卡)。主要机具钢筋钩子、小撬棍、钢筋板子、绑扎架、钢丝刷、运钢筋手推车、粉笔、脚手架、工作台等。2.2作业条件(1)、按施工平面图规定的位置平整好场地,按不同规格型号垫好堆放。(2)、进场钢筋应对照设计图纸和配料单,详细核对其型号、尺寸、数量、钢号、对焊的接焊质量。(3)、弹好标高水平线及墙的外皮线。(4)、圈梁及板缝模板已做完预检记录,并将模内杂物清理干净。2.3操作工艺(1)、支完圈梁模板后,即可绑扎圈梁钢筋,如果采用预制绑扎骨架时,可将骨架按编号吊装就位进行组装。如在模内绑扎时,按设计图纸要求间距,在模板侧绑画箍筋位置,放箍筋后穿受力钢筋,绑扎箍筋。注意箍筋必须垂直受力钢筋,箍筋搭12、接处应沿受力钢筋互相错开。2)、圈梁钢筋的搭接长度:因混凝土为C20等级,I级钢筋搭接长度不少于30d,级钢筋不少于40d(d为受力筋直径)。受力钢筋接头的位置应相互错开,绑扎接头时在规3)、圈梁钢筋绑扎时应互相交圈,在内外墙交接处,大角转角处的锚固长度均要符合设计要求。4)、圈梁钢筋绑完后应加水泥砂浆垫块。2.4质量验收(1)保证项目:1)、钢筋的品种和质量必须符合设计要求和有关标准规定,符合有关规定后方可焊接。检查钢筋出厂质量证明书和试验报告。2)、钢筋表面应保持清洁。带有颗粒状或片状老锈,经除锈后仍有麻点的钢筋严禁按原规格使用。3)、钢筋对焊或电焊焊接接头:按规定取试件,其机械性能试验结13、果必须符合钢筋焊接及验收的专门规定。(2)、基本项目:1)、钢筋的绑扎、缺扣、松扣的数量不超过绑扣数的10%,且不应集中。2)、弯钩的朝向正确。绑扎接头应符合施工规范的规定,其中搭接长度均不少于规定值。3)、用I级钢筋或冷拔低碳钢丝制作的箍筋,其数量、弯钩角度和平直长度均应符合设计要求和施工规范的规定。4)、对焊接头无横向裂纹和烧伤,焊包均匀,接头处弯折不大于4度,轴线位移不大于0.1且不大于2。电弧焊接头、焊缝表面平整,无凹陷、焊瘤、接头处无裂纹、气孔、夹渣及咬边。接头处不大于4度,轴线位移不大于0.1,且不大于3,焊接厚不大于0.05,宽不小于0.1,长不小于0.5。2.5成品保护(1)、14、圈梁钢筋如采用预制骨架时,应在指定地点垫平码放整齐。(2)、运输钢筋时,应清理好存放点,以免变形。(3)、不得踩踏已绑好的钢筋,绑圈梁钢筋时不得将梁底砖碰松动。注意事项(1)、钢筋变形:钢筋骨架绑扎时应注意绑扣方法,宜用部分反十字扣或套扣绑扎,不得全绑一面顺扣。(2)、箍筋间距不符合要求:多为放置砖墙拉结筋时碰动所致。应在砌完墙合模前修整一次。 3、模板工程3.1材料设备要求(1)、木模板尺寸915*1830(2)、方木、木楔、支撑(木或钢),模板的附件(碟型扣件、对拉螺栓、紧固螺栓),隔离剂等。3.2主要机具 打眼电钻、搬手、钳子。3.3作业条件(1)、弹好墙身50cm水平线,检查砖墙的位置15、是否符线。办理预检手续。(2)、钢筋绑扎完毕,并办好隐检手续。(3)、模板拉杆如需螺栓穿墙,砌砖时应按要求预留螺栓孔洞。(4)、检查模板内的灰浆,将灰浆清理干净。3.4操作工艺工艺流程: 支圈梁模板作清理准备工作办预检 支板模板 (1)、支模前将圈梁及板缝处杂物全部清理干净。(2)、支模板A圈梁模板可采用木模板或定型组合钢模板上口弹线找平。B. 圈梁模板采用落地支撑时,下面应垫方木,当用木方支撑时下面用木楔楔紧。用钢管支撑时高度调整合适。C钢筋绑扎完以后,模板上口宽度进行校正定位,并用木撑进行校正定位,用铁钉临时固定。如采用组合钢模板,上口应用卡具卡牢,保证圈梁的尺寸。D.外墙圈梁,用横带扁担16、穿墙平面位置距墙两端24cm开始留洞,中间每隔50cm左右留一道,每面墙不宜少于5个洞。3.5质量验收(1)、保证项目:模板及其支架必须具有足够的强度,刚度和稳定性,其支撑部分应有足够的支撑面积,如安装在基土上,基土必须坚实,并有排水措施。对湿陷性黄土,必须有防水措施;对冻胀性土,必须有防冻融措施。(2)、基本项目:1)、模板接缝处应严密,预埋件应安置牢固,缝隙不应超过1.5。2)、模板与混凝土的接触面应清理干净并采取防止粘结措施,粘浆和漏刷隔离剂累计面积应不大于400cm2如模板涂刷隔离时应涂刷均匀,不得漏刷或沾污钢筋。3.6成品保护(1)、在砖墙上支撑圈梁模板时,防止撞动最上一皮砖。(2)17、 支完模板后,应保持模内清洁,防止掉入砖头、石子、木屑等杂物。(3)、应保护钢筋不受扰动。3.7注意事项(1)、支模板时应在外墙面采取加固措施。(2)、圈梁模板外胀:圈梁模板支撑没卡紧,支撑不牢固,模板上口拉杆碰坏或没钉牢固。浇筑混凝土时没专人修理模板。(3)、混凝土流坠:模板板缝过大没有用纤维板、木板条等贴牢;外墙圈梁没有先支模板后浇筑圈梁混凝土,而是包砖代替支模板再浇筑混凝土,致使水泥浆顺砖缝流坠。4、混凝土工程采用材料:池壁垫层用C15级混凝土,底板、盖板、圈梁采用C25级混凝土。、所用水泥必须有质量证明书并应对其品种标号及日期检查验收,做好化学试验分析,要求各项指标必须合格,时间超过18、三个月或发现受潮,结块时必须做试验,按试验数据确定水泥标号。 、所用砂要用中、粗砂,含泥量要少,所用碎石级配良好,不含杂质,石子最大粒径不超过结构截面尺寸的1/4和钢筋最小净距的1/4,对砼实心板可与4050mm粒径的碎石拌和,水采用自来水。、砼采用搅拌机拌和,按实验室重量配合比计量,骨料的允许偏差为:砂石3,计量器具应定期校验,砂含水率应经常测定,雨季要减少加水量,搅第一盘砼时要适当增加水泥和砂子的用量,搅拌采用二次投料先即先投入砂、水泥、水搅拌后再加入石子搅拌,可提高砼强度15%,搅拌时间最短为120秒钟。、砼拌好后,应尽快运到浇灌地点,若发现砼离析,应进行二次搅拌,均匀后方准入模,砼的垂19、直水平运输均采用塔吊。、在浇灌前,先清除干净模板,做好钢筋的隐蔽验收。在浇筑构造柱时,按400mm分层浇筑,并使用吊筒下灰,构造柱浇筑前,应在柱根处先浇50 MM厚高标号砂浆再浇灌砼,砼振动要防止振动预埋件、钢筋,应快插慢拔,振捣时间为30秒,以表面泛浆为准。 、砼浇灌过程中,不得踩倒和压弯钢筋,特别是负弯距钢筋,楼板砼用振捣棒振完后,再用平板器缓慢地来回拖一遍,并把表面用木抹子抹平。、砼浇灌完毕24小时后,待砼表面收水后,浇水保持湿润,一天3次,养护时间不得小于7天。5、抹灰工程采用材料:池壁内外表面及池底均用防水砂浆(1:2水泥砂浆内掺水泥重量的5%的防水剂)抹面,厚20,阴角抹45度斜面20、,厚50。辅助措施: 化粪池内搭设满堂红脚手架进行配合施工。5.1操作工艺工艺流程:墙面清理粉尘、污垢浇水湿润墙面吊垂直找方抹灰饼冲筋、找规矩抹底灰抹面层防水砂浆。 1)、基层处理:将墙面上残余砂浆、污垢、灰尘等,清理干净,并用水浇墙,将砖缝中的尘土冲掉,并将墙面湿润。2)、吊垂直、套方、找规矩、抹灰饼同上。3)、冲筋,抹底层砂浆时,用大横竖刮平,木抹子搓毛,终凝后浇水养护。5.2质量验收(1)、保证项目:所用的材料品种,质量必须符合设计要求,各抹灰层之间,及抹灰层与基体之间必须粘结牢固、无脱层、空鼓、面层无爆灰和裂缝(风裂除外)等缺陷。(2)、允许偏差项目: 立面垂直 5表面平整 5阴阳角垂21、直 4阴阳角方正 4分格条(缝)平直 4用2m托线板检查5.3成品保护各抹灰层在凝结前应防止快干、曝洒、水冲、撞击和振动,以保证其灰层有足够的强度。注意事项(1)、空鼓、开裂和烂根:由于抹灰前对基层清理不干净或不彻底,抹灰前不浇水,每层灰抹得过厚,跟得太紧;对于预制混凝土光滑表面不认真进行“毛化处理”;甚至混凝土表面的酥皮不处理就抹灰;抹灰后不养护。为解决好空鼓、开裂等质量问题,应从三方面下手解决,第一施工前的浇水、清理;第二施工操作分层分遍压实认真不马虎;第三施工后及时浇水养护,并注意施工地点的洁净,抹面层应一次到底。6、回填土工程6.1施工准备6.l 材料及主要机具:6.1.1 碎石类土、22、砂土(使用细砂、粉砂时应取得设计单位同意)和爆破石碴,可用作表层以下填料。它最大粒径不得超过每层铺填厚度的2/3或3/4(使用振动碾时),含水率应符合规定。6.1.2 粘性土应检验其含水率,必须达到设计控制范围,方可使用。6.1.3 盐渍土一般不可使用。但填料中不含有盐晶、盐块或含盐植物的根茎,并符合土方与爆破工程施工及验收规范的规定的盐渍土则可以使用。6.1.4 主要机具:6.1.4.1 装运土方机械有:铲土机、自卸汽车、推土机、铲运机及翻斗车等。6.1.4.2 碾压机械有:平碾、羊足碾和振动碾等。6.1.4.3 一般机具有:蛙式或柴油打夯机、手推车、铁锹(平头或尖头)、2m钢尺、20号铅丝23、胶皮管等。 6.2 作业条件: 6.2.1 施工前应根据工程特点、填方土料种类、密实度要求、施工条件等,合理地确定填方土料含水量控制范围、虚铺厚度和压实遍数等参数;6.2.2 填土前应对填方基底和已完工程进行检查和中间验收,合格后要作好隐蔽检查和验收手续。6.2.3 施工前,应做好水平高程标志布置。基坑或沟边上每隔1m钉上水平桩橛或在邻近的固定建筑物上抄上标准高程点。6.2.4 确定好土方机械、车辆的行走路线,应事先经过检查,必要时要进行加固加宽等准备工作。同时要编好施工方案。 6.3操作工艺 工艺流程: 基坑底地坪上清理检验土质分层铺土分层碾压密实检验密实度修整、找平验收 6.3.1 填土24、前,应将基土上的洞穴或基底表面上的树根、垃圾等杂物都处理完毕,清除干净。 6.3.2 检验土质,检验回填土料的种类、粒径,有无杂物,是否符合规定,以及土料的含水量是否在控制范围内;如含水量偏高,可采用翻松、晾晒或均匀掺入干土等措施;如遇填料含水量偏低,可采用预先洒水润湿等措施。6.3.3 填土应分层铺摊,每层铺土的厚度应根据土质、密实度要求和机具性能确定。6.3.4 碾压时,轮(夯)迹应相互搭接,防止漏压或漏夯。长宽比较大时,填土应分段进行。每层接缝处应作成斜坡形,碾迹重叠。重叠0.5l.0m左右,上下层错缝距离不应小于1m。6.3.5 填方超出基底表面时,应保证边缘部位的压实质量。6.3.625、 在机械施工碾压不到的填土部位,应配合人工推土填充,用蛙式或柴油打夯机分层夯打密实。 6.3.7 回填土方每层压实后,应按规范规定进行环刀取样,测出干土的质量密度,达到要求后,再进行上一层的铺土。6.3.8 填方全部完成后,表面应进行拉线找平,凡超过标准高程的地方,及时依线铲平;凡低于标准高程的地方,应补土找平夯实。六、附图1、10#、13#化粪池尺寸详图2、保利家园二期地质勘查资料3、图集资料附件:4、化粪池定位图岩土层顶板埋深、顶板标高及层厚一览表 单位:米 孔号层序ZK8ZK9ZK10ZK11ZK15ZK16ZK17ZK18ZK19ZK27ZK28ZK29ZK30ZK31ZK32ZK3526、ZK36ZK37ZK38ZK44ZK45ZK46ZK47素填土顶板埋深0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 顶板标高3.13 3.19 3.27 3.25 3.20 3.23 3.35 3.19 3.25 3.25 3.20 3.21 3.15 3.32 3.31 3.21 3.22 3.30 3.17 3.21 3.23 3.31 3.27 层厚2.80 4.00 3.50 3.50 2.50 3.5027、 3.30 2.70 3.50 2.50 2.60 2.90 3.40 5.00 3.50 3.50 3.50 3.50 3.20 2.10 3.30 2.10 3.60 -1淤泥质土顶板埋深2.80 4.00 3.50 3.50 2.50 3.50 3.30 2.70 3.50 2.50 2.60 2.90 3.40 5.00 3.50 3.50 3.50 3.50 3.20 2.10 3.30 2.10 3.60 顶板标高0.33 -0.81 -0.23 -0.25 0.70 -0.27 0.05 0.49 -0.25 0.75 0.60 0.31 -0.25 -1.68 -0.19 -028、.29 -0.28 -0.20 -0.03 1.11 -0.07 1.21 -0.33 层厚1.20 2.20 3.00 2.70 2.90 1.10 5.50 3.30 6.90 2.50 1.40 2.20 0.80 0.50 1.50 1.00 1.00 4.50 4.80 1.20 0.70 2.10 0.90 -2粉砂顶板埋深4.00 6.20 6.50 6.20 5.40 4.60 8.80 6.00 10.40 5.00 4.00 5.10 4.20 5.50 5.00 4.50 4.50 8.00 8.00 3.30 4.00 4.20 4.50 顶板标高-0.87 -3.0129、 -3.23 -2.95 -2.20 -1.37 -5.45 -2.81 -7.15 -1.75 -0.80 -1.89 -1.05 -2.18 -1.69 -1.29 -1.28 -4.70 -4.83 -0.09 -0.77 -0.89 -1.23 层厚4.20 6.70 2.30 5.10 4.60 5.90 2.20 4.00 2.20 2.00 4.80 7.40 7.60 6.80 3.00 3.50 4.30 /3.20 7.30 5.40 3.80 -3粉质粘土顶板埋深8.20 12.90 8.80 11.30 10.00 10.50 11.00 10.00 12.60 7.030、0 8.80 12.50 11.80 12.30 8.00 8.00 8.80 8.00 8.00 6.50 11.30 9.60 8.30 顶板标高-5.07 -9.71 -5.53 -8.05 -6.80 -7.27 -7.65 -6.81 -9.35 -3.75 -5.60 -9.29 -8.65 -8.98 -4.69 -4.79 -5.58 -4.70 -4.83 -3.29 -8.07 -6.29 -5.03 层厚/4.70 /2.20 /1.10 /-4粉砂顶板埋深8.20 12.90 8.80 11.30 14.70 10.50 11.00 10.00 12.60 7.00 831、.80 12.50 11.80 12.30 8.00 8.00 8.80 8.00 8.00 8.70 11.30 10.70 8.30 顶板标高-5.07 -9.71 -5.53 -8.05 -11.50 -7.27 -7.65 -6.81 -9.35 -3.75 -5.60 -9.29 -8.65 -8.98 -4.69 -4.79 -5.58 -4.70 -4.83 -5.49 -8.07 -7.39 -5.03 层厚6.10 /3.10 4.00 4.30 2.50 /5.50 7.00 5.80 2.70 2.60 /-5淤泥顶板埋深14.30 12.90 8.80 11.30 1432、.70 10.50 11.00 10.00 15.70 11.00 13.10 15.00 11.80 12.30 8.00 8.00 8.80 13.50 15.00 14.50 14.00 13.30 8.30 顶板标高-11.17 -9.71 -5.53 -8.05 -11.50 -7.27 -7.65 -6.81 -12.45 -7.75 -9.90 -11.79 -8.65 -8.98 -4.69 -4.79 -5.58 -10.20 -11.83 -11.29 -10.77 -9.99 -5.03 层厚/3.10 7.70 6.90 /6.30 7.00 10.90 1.30 /533、.50 3.10 8.20 10.40 7.10 1.50 2.00 /5.70 -6粉质粘土顶板埋深14.30 16.00 16.50 18.20 14.70 16.80 18.00 20.90 17.00 11.00 13.10 15.00 17.30 15.40 16.20 18.40 15.90 15.00 17.00 14.50 14.00 13.30 14.00 顶板标高-11.17 -12.81 -13.23 -14.95 -11.50 -13.57 -14.65 -17.71 -13.75 -7.75 -9.90 -11.79 -14.15 -12.08 -12.89 -15.34、19 -12.68 -11.70 -13.83 -11.29 -10.77 -9.99 -10.73 层厚0.70 1.00 /1.00 /2.40 4.00 0.40 /0.80 /2.80 2.20 1.00 /1.30 1.70 2.00 -7淤泥质土顶板埋深15.00 17.00 16.50 18.20 14.70 17.80 18.00 20.90 19.40 15.00 13.50 15.00 17.30 16.20 16.20 18.40 18.70 17.20 18.00 14.50 15.30 15.00 16.00 顶板标高-11.87 -13.81 -13.23 -14.35、95 -11.50 -14.57 -14.65 -17.71 -16.15 -11.75 -10.30 -11.79 -14.15 -12.88 -12.89 -15.19 -15.48 -13.90 -14.83 -11.29 -12.07 -11.69 -12.73 层厚/残积土顶板埋深15.00 17.00 16.50 18.20 14.70 17.80 18.00 20.90 19.40 15.00 13.50 15.00 17.30 16.20 16.20 18.40 18.70 17.20 18.00 14.50 15.30 15.00 16.00 顶板标高-11.87 -13.836、1 -13.23 -14.95 -11.50 -14.57 -14.65 -17.71 -16.15 -11.75 -10.30 -11.79 -14.15 -12.88 -12.89 -15.19 -15.48 -13.90 -14.83 -11.29 -12.07 -11.69 -12.73 层厚/4.00 2.30 /1.20 3.00 /1.80 /1.80 1.80 1.00 /-1全风化层顶板埋深15.00 17.00 20.50 20.50 14.70 19.00 21.00 20.90 19.40 15.00 13.50 15.00 17.30 16.20 18.00 18.437、0 18.70 19.00 19.80 15.50 15.30 15.00 16.00 顶板标高-11.87 -13.81 -17.23 -17.25 -11.50 -15.77 -17.65 -17.71 -16.15 -11.75 -10.30 -11.79 -14.15 -12.88 -14.69 -15.19 -15.48 -15.70 -16.63 -12.29 -12.07 -11.69 -12.73 层厚/2.50 1.50 0.80 /2.20 3.00 1.00 /1.40 1.00 2.50 /1.00 1.80 1.00 3.90 -2强风化层顶板埋深15.00 17.038、0 23.00 22.00 15.50 19.00 21.00 20.90 19.40 17.20 16.50 16.00 17.30 17.60 19.00 20.90 18.70 19.00 19.80 16.50 17.10 16.00 19.90 顶板标高-11.87 -13.81 -19.73 -18.75 -12.30 -15.77 -17.65 -17.71 -16.15 -13.95 -13.30 -12.79 -14.15 -14.28 -15.69 -17.69 -15.48 -15.70 -16.63 -13.29 -13.87 -12.69 -16.63 层厚3.80 39、15.80 2.50 3.20 8.50 7.50 6.80 6.10 3.20 1.10 1.30 7.20 2.90 12.70 6.30 /1.00 2.20 1.70 1.00 6.00 3.10 -3中风化层顶板埋深18.80 32.80 25.50 25.20 24.00 26.50 27.80 27.00 22.60 18.30 17.80 23.20 20.20 30.30 25.30 20.90 18.70 20.00 22.00 18.20 18.10 22.00 23.00 顶板标高-15.67 -29.61 -22.23 -21.95 -20.80 -23.27 -2440、.45 -23.81 -19.35 -15.05 -14.60 -19.99 -17.05 -26.98 -21.99 -17.69 -15.48 -16.70 -18.83 -14.99 -14.87 -18.69 -19.73 控制厚度0.20 0.40 2.30 2.50 /1.80 0.30 0.20 1.90 1.40 0.80 2.10 4.70 1.70 0.70 4.80 4.80 1.70 /1.00 1.10 1.00 2.30 -4微风化层顶板埋深19.00 33.20 27.80 27.70 24.00 28.30 28.10 27.20 24.50 19.70 18.41、60 25.30 24.90 32.00 26.00 25.70 23.50 21.70 22.00 19.20 19.20 23.00 25.30 顶板标高-15.87 -30.01 -24.53 -24.45 -20.80 -25.07 -24.75 -24.01 -21.25 -16.45 -15.40 -22.09 -21.75 -28.68 -22.69 -22.49 -20.28 -18.40 -18.83 -15.99 -15.97 -19.69 -22.03 控制厚度2.40 2.00 2.70 5.30 5.30 5.00 2.20 5.40 2.20 2.00 3.80 242、.10 2.85 2.20 4.30 2.10 2.40 5.40 2.50 5.10 2.60 2.15 5.20 (英文版 ) easily blame, to prevent the broken window effect. Supervise the leading cadres to play an exemplary role, take the lead in the strict implementation of the and , lead to safeguard the solemnity and authority of the party discipline, 43、ensure that the party discipline and the laws and regulations for implementation in place. Throughout the discipline in the daily supervision and management, strengthen supervision and inspection, from the thorough investigation of violations of discipline behavior. Strengthen to key areas, key depa44、rtments and key projects as well as the masses reflect the concentration of the units and departments for supervision. - strengthening supervision, discipline inspection and supervision of cadres to set an example for compliance with the and is a man must be hexyl, blacksmith needs its own hardware.45、 Discipline inspection organs as the executor of the party discipline, and supervisor of the defenders, for its supervision must be more strictly, discipline inspection and supervision of cadres to firmly establish the awareness of Party Constitution, sense of discipline and rules consciousness, pol46、itics loyalty, sense obey. Action speak Ji Ordinance to set an example of the regulations of the rule of law, strengthen supervision and accept the supervision of the firmness and consciousness, do comply with and . To firmly establish the discipline must first be disciplined, the supervisor will be47、 subject to the supervision of concept, and consciously safeguard and implement party compasses party, take the lead in practicing three strict real strict, so loyal, clean, play. To be good at learning, the Constitution and the as morality, politics and brought to fruition; to implement , do not wa48、nt to, dare not, not with disciplinary ruler to supervision; to discipline a ruler, often the control inspection, and consciously in the ideological red line to draw the row Ming Good accumulation is indeed the bottom line, so that the heart has fear, said to have quit, the line has ended. Attached:49、 indifferent to heart, calmly to the table in our life, there are many unpredictable things will happen, some good, some bad things, we cannot control is powerless to stop, but with time, you will find in life sometimes turns out to be not good, some bad things finally turned out to be a good thing,50、 but then we muddy however did not know, this is the life teach us things. 1, life can be complex, can also be simple. Want simple life of precipitation, to have enough time to reflect, to make Become more perfect. Life is the most important thing is not to win, but the struggle; not to have conquer51、ed, but to have fought well. 2, the plain is the background of life. Live a plain life, give up on themselves is not a coward, but the wise answers; not disillusioned after the heart, such as ashes, but experience the storm after the enlightenment; not unrewarding perfunctorily, but calm attitude of52、 life of unrestrained self-confidence. Plain living, there is no noise noisy, no earthly troubles, more did not fill in the discontent of desire, some just a calm, a calm. 3, memory of heart will not good things to erase the, life is a When no movie, pain is a beginning, the struggle is a kind of pr53、ocess, death is a kind of ending. Give up this giving up is the helpless, do not give up the abandoned, do not give up this giving up is ignorance, do not give up should not give up is persistent. 4, a thing figured is heaven, think impassability is hell. Since the living, to live better. Sometimes 54、we because of too narrow-minded, too care around the chores and penny wise and pound foolish, not worth the candle. Some things to attract trouble and worry, completely depends on how we look at and deal with it. Dont always take everything back to things, and dont get into a blind alley, dont want 55、to face, dont be narrow-minded. Poke to care, is a kind of open-minded, a free and easy. 5, I am not afraid of others behind me a knife, I afraid to look back and see stab me, is my intention to treat people; I am not afraid of the truth to tell the best friend, Im afraid he turned to it as a joke t56、o tell dont 6, when we are in a positive frame of mind, you will find many good things; and when we are in a negative state of mind, you will find many depressed things; life happy and worry, all is you of life attitude, optimistic, good luck; loss of sink, Eritrea company. When you are in adversity57、, may wish to change a point of view to think everything over to the good Think, because good mentality decided the fate of the! 7, people are tired, rest; heart tired, calm. Grow up, mature, this society read. Tired and sad, squat down, to their a hug. Because the world no one can sympathize with y58、ou, have mercy on you. You cry, tears is your own; you pain, no one can understand. Then you only tears to smile. 8, each people have youth,Each youth are a story, the life of the world never gets easier, I want what, wish the world all know, as has been the same; now want anything, for fear that ot59、hers know, or like to lose the same. 9, the heart move, everything in the world is followed by birth, Rangrang, important thing is often the most difficult to open ones mouth, because words will reduce its importance; to let strangers people care about your life in the good things, the original is n60、ot easy 10, do not blame, do not laugh at who, also dont envy who. Like a person is a kind of feeling, not like a person is true. The truth is easy to explain, I feel Is unspeakable. The best travel life is that you in a strange place found a long lost touched. 11, happy life not in the bustling in,61、 and in the peace of mind; no matter how many grievances, how uncomfortable, and ultimately to heal themselves or their own, others may got you to comfort, but never know your heart is how wanjianchuanxin. 12, maam, like a movie, learn to appreciate, learn to be grateful, learn tolerance, and goodne62、ss, helping others. Instead of accusing the society, as into one; and an exception is better to give than to what 13, dont envy him A sum of, dont lose your life and the life, respectively is: the former is a we experienced cannot escape in a day finally will last minute, while the latter is our per63、sistent, we want to cherish the memory of those people and things. 14, learn to smile, learn to strong, the world you know so many people, so many people and you are, you cannot change also cant let everyone like you, so also do not want to do. Life is too short to go crazy to love to go to waste, t64、o chase the dream to regret. 15, when temper, a blessing to go. A wounding elegant people, the key is to control their own emotions. With the mouth is the most stupid behavior. A control negative emotions than a can take a city more powerful water flow slow, language is expensive. People spent two y65、ears of time to learn to speak, but to spend a few years time to shut up. That is a kind of ability, that is a kind of wisdom. 16, life is not perfect, sometimes, growth is not a cry, not an eyeful of tears, there is no trace of emotion, there is no gleam of hope, no desire, no action, no static, th66、ere is only one kind of downward sinking feeling, sink A murky? 6? 7? 6? 7 sink? 6? 7? 6? 7 toward the bottom of the sink. 17, in some way, do not go, you will not know the other side scenery is beautiful. To you is not good, you do not mind too much, no one has an obligation to you; you learn knowl67、edge, is you have weapons, you can start from scratch, but not unarmed; how do you treat people, does not represent how others treat you, if cannot see through this point, only inviting worry. 18, time is like a sponge in the water, as long as you are willing to squeeze, the total water is still the68、re. Every life, after the ups and downs The best test of live, to life, survival and continuation, do not stop the struggle in the joys and sorrows of life on the road, so that different soul to bear life beat, acceptance of suffering. 19, indifferent to heart, calmly in table, elegant and comfortab69、le life, do not take what is so important. The pursuit will be disappointed; to be alive, you will have trouble. Life is the most afraid of what all want to care about, but also what all grasp is not firm, without scenery, separated populations, such as not to desire, all docked in the fate of the e70、nd. Why is too rigid, the natural, to go stay not to live, let go of obsession, revel is 20, if the fate of the broken Hopes of sailing, please dont despair, the coast is still, if the fate of the withered petals of the beautiful, please do not sink, the spring is still, life will always be endless 71、trouble, please dont helpless, because they are still alive, is still a dream, the sun still, we still. Lost, keep memories; to get, must work to; but the most important is good to cherish their own. 21, life, select the complex, is to choose the pain; choose a simple, is choose to be happy. The com72、plex world like aSignificance of pride. Hope is the ornate palace, outside people admiring the magnificent, living in the deep knowledge of living it to pay the price. Simple world as a simple log cabin outside ridiculed shabby, the heart is willing to go live to know the joy. Suffering and joy is t73、heir own choice. 22, learn how to use a single powerful heart, let the past be the past, let the future come. Life is really the end of the end of an eagle is flying wings, life is constantly pursuit. Dont miss to regret, dont wait for old just miss. Time to return, seize every moment, again painsta74、kingly again tired also Those struggling to fly. 23, life could not Yimapingchuan, even flat pavement, inevitably there will be a few pieces of roadblocks. Some of the rocks around the past, while others have to move it out. Just move others put the stone is very easy, because the stone from the app75、earance we can discern; difficult to myself to move away the heart of stone head. Leave time to spend with her, often reflect my heart, so as to remove your heart of stone. 24, everything does not have to be demanding, come to, everything does not have to care about, over the past; failing to do not76、 frown, laugh it laugh. Results Dont demand, do to; life is a simple, calm and peaceful. Always not to choose their own path and regret, life is like a train, the scenery and then the United States will retreat, the passage of time and encounter will eventually drifting further and further away, bef77、ore is always himself. 25, everyone has a weakness, weakness is true humanity. That has no weakness, a shallow person. That people think there is no weakness, mostly false. Life has shortcomings, there are shortcomings is the real life. That no one regret, or childish or numbness or Self deception. 78、It is in tolerance of weakness and so on to accept, people live happily.Hello, everyone! I am a party member. The title of my speech is: study and implement the partys two laws, doing practical play highway. 2015 October 18, the Central Committee of the Communist Party of China promulgated the imple79、mentation of the and Chinese Communist Party discipline and punishment regulations. We Heyuan male passers-by to respond positively to the call of the Central Committee of the party, earnestly organize the study party two regulations, truly grasp the essence and gist, and in their respective positio80、ns, to hold the bottom line of the discipline, build a strong ideological line of defense, with the courage to play, the courage to fight tough and fearless spirit, at the crucial moment well to complete the task, with practical action to test the study and implement effect Because of discipline in 81、the * * * * * * * * * * * story. Here, let me to cast a brick to attract jade, speak about our highway. Highway line section of the road surface transformation project, last year towards the country seized will be seized one of the items. To complete this arduous task, as a project management office82、 director Comrade, keep in mind from the Communist Party membership, recognize and identify the bottom line, strict management, and strict adherence to the quality of the project. He not only set an example, honesty and self-discipline, but also requires the management of all the members of the O.K.83、, do not eat the construction unit one meal, do not accept the construction unit a ceremony. In this way, they didnt really dare to adhere to the principle. No comrade, constantly put on reworking an emergency meeting to Comrade Zhen to speak louder, management tube too strict. Remember in Dongguan 84、Street, 400 meters long cement concrete surface layer, because of various reasons, the smoothness of the poor in the bottom cavity, covering film traces and car imprinting quality problems, * * * inquiries, immediately rushed to the scene to understand and verify the situation, the convening of the 85、management office, the construction units, supervision units, construction units, construction units construction time is tight, the economic loss and other reasons to intercede * unmoved. He said, now a popular word, to the discipline and rules quite in front, there are no rules Radius, you constru86、ction team not accordance with the technical specifications, quality problems, it must be to carry out rectification. Engineering quality responsibility be weightier than Mount Tai, if we manage to this matterPavement quality quantity are placed the matter, we this time to learn two regulations have87、 what use? Still what is the Communist Party? Finally, in his insisted, the road after rework, to solve these problems. In the construction of the new comrades and the project all the colleagues efforts, after four months of fighting, the project the main project was finally completed and passed ins88、pection. Thousands of miles of ice, thousands of miles Piao, this is a splendid and romantic scene. But snow for the highway, it is a disaster, a serious threat to the traffic safety. This year, a month, a century of cold wave swept from North to south, and the snow blowing to Guangdong, but also to89、 bear the blow To * * * * the highway. In January on the evening of 23, Lianping county city temperatures dropped to minus 2 degrees, a wide range of sudden rain sleet, before and after the provincial S341 line in Jiulianshan Mountain tunnel sections of the road appeared in the snow, lead to the pas90、sing vehicles skid, traffic is blocked. In the face of the sudden natural disasters, city and county highway department immediately launched the emergency plan for disaster prevention. As the front line of the main force, Lianping Highway Bureau of all Party members and cadres to remember the Party 91、member responsibility, braving the biting cold wind, the first time rushed to the scene, on the icy pavement of salt disposal. Because the temperature is too low, just melt water immediately freezes, addition to the ice work to increase the difficulty. To ensure In addition to the re organization of92、 the depths of the traffic safety, road people braved the icy put reflective cones and warning signs, endure cold at minus 2,3 of Jiulianshan patrols until one in the morning. Just before dawn, Lianping Highway Bureau personnel on the icy road salt ice melting processing until ten oclock, ice meltin93、g ice success, the road gradually returned to normal traffic. In the cold winter night, which people do not miss the warm bed, which people do not miss the warm home. However, our highway on the road to the owners of the masses can go home early, the night fighting to secure the avoidance of the roa94、d safety and smoothness, fulfill their responsibility. Xi General Secretary Every Party member cadre cautioned against said: blacksmith needs self hard . two regulations , is our own hard standard test, more exercise every party members and cadres of the fire. We should continue to strengthen the pa95、rty two regulations, conscientiously in practical work, practical play road, the road for the development of the cause of Heyuan and struggle.In the industry domain report the situation of road traffic in recent years, in the province highway departments of the concern and support, our bureau manage96、ment department based on the job, loyalty duty, best service, to further promote the highway management standardization, legal, scientific and information technology to improve the management level and service quality. This will be my last work is as follows: first, around the center, go all out to 97、greet the seizure in 2015, meet national examination is my bureau work. As the highway management department, we focus on the work of the center to strengthen road renovation and management as the focal point, further optimize the service environment, improve service levels. Inspection, the inspecti98、on group and the Ministry of transport, the Bureau under the leadership of the ministries and agencies highly evaluated and fully affirmed. (a) increase road area remediation efforts. The programme of work, strengthen the organization and leadership. The timely development of the city of , along the99、 road signs and markings, traffic safety facilities, on both sides of the green, advertising signs, control area illegal construction and implementation of remediation tasks to the relevant departments, clear work time of the node to ensure rectification work timely. Set up road area special rectifi100、cation work leading group, implement a bureau, the Bureau of the county (District), the project road site domain environment comprehensive improvement Mechanism. To ensure that the work carried out smoothly, the bureau also organized the city road managers participated in the regulation of road regi101、on and the relevant laws and regulations of the special training. 2. Active butt joint is reported, actively strive for the support of. Local Party committee and government support is the jobAs a magic weapon, I am one of the Bureau of the principal leaders repeatedly attack inspection remediation a102、nd road area to the principal leaders of the municipal report. * * *, the Secretary of municipal Party committee, mayor * *, * * *, vice mayor of many times the rate of the relevant departments directly under the responsible person in-depth National Highway G105 line, G205 line, provincial S341 line103、 and the other highway project site, on-site office, coordination solve engineering construction and environmental comprehensive renovation in the presence of difficulties and problems. Last year, national highway along the county (District) government led organizations deploy traffic, urban managem104、ent, public security, land, environmental protection, industry and commerce, highways and other related departments, to carry out to dismantle illegal construction and ground structures, cleaning up illegal standard Records label as the main content of the road domain integrated environmental remedi105、ation activities and achieved good results. 3. Pay attention to comprehensive management, improve the effectiveness of remediation. Road construction control management has been strengthened. According to the relevant provisions of the laws and regulations of the and and so on, county * *, * * Count106、y Peoples Government on highway construction control area were delineated and issue a public notice, * * County Peoples government also approved by the executive meeting of the government through discussion, implementation of road boundary markers of 73 million yuan of special funds input, stake set107、ting. According to statistics, last year the city has erected building control zone peg 820, construction control area boundary markers 815 . the second is highway greening and beautification work enhance the road area remediation effectiveness. Will highway greening and beautification work as road 108、area remediation of a key, invite garden experts to guide the design of green, the implementation of high standards for ecological landscape highway activities to create, five years, I board greening mileage of more than 900 kilometers, appropriate road greening greening rate of 100%, effectively en109、hance the city road greening level and grade, adds a sharp scenery line for *. Third, rectification of illegal construction and occupation of the road has been checked. By through the town, crossing the road on many occasions to carry out concentrated rectification actions, to clear the remnants of 110、the wall, broken Archives of highways in strict accordance with the wall of building structures and the illegal deposits, remediation along the Jeeves, Jeeves placed advertisements and vehicle maintenance, car washing and other acts, standardize and purification on both sides of the highway billboar111、ds and other non road signs, I city of national and provincial highway basic elimination of the dirty, chaotic, poor, blocking phenomenon, highway traffic environment purification, landscaping. (2) to strengthen the management on the basic data management. The level of the archives management regula112、tions, formulate the , the establishment of the road, the implementation of the file manager, file collection, filing, sorting, filing, confidentiality, custody, borrow, identification pin Destroy the standardization. 2, standardized management, enhance service image (a) evaluation system to further113、 improve in order to strengthen and standardize guidance and assessment of each county (area) bureau of highways management work, the Bureau developed a * City Highway Bureau highways management assessment implementation measures (Trial). To regularly check for half a year, year-end assessment and i114、rregular random sampling combined, taking the spot road inspections, sampling sections, listening to the reports, archives data check, for each county (area) bureau of highways management work implementation of the special assessment. According to the annual comprehensive assessment appraisal score 115、results, evaluation of outstanding, excellent compliance and Not up to the standard of four grades. And in accordance with the level of assessment, the award on behalf of dial highway management funds. Total score is above 95%, is excellent, 10 million yuan reward; total score of 90 - 94 for excelle116、nt, 8 million yuan reward; for the total score of 80 - 89 points for standard, reward 50000 yuan. On the total score is less than 79 points for non-compliance unit, circulate a notice of criticism. (II) Sheung inspection work to further standardize a is in place to ensure the inspection. National an117、d provincial trunk highway patrol monthly not less than 20 days, State Road a week of not less than 3 times, dart a week of not less than 2 times. The second is to explore and promote the electronic patrol monitoring.City highway patrol vehicles are installed on the highway patrol vehicle monitoring118、 system; highway law enforcement personnel are equipped with a recorder for law enforcement, on the process of supervision and law enforcement to ensure evidence has played an effective role. The third is unified and standardized inspection ledger records, inspection equipment use and management of 119、the electronic Patrol information storage utilization. The fourth is the establishment of highway maintenance and inspections mechanism. The citys 19 country and provincial trunk highway maintenance center equipped with the CPPCC keeper, and to develop a road of the Chinese peoples Political Consult120、ative Conference tube member responsibilities. According to statistics, in 2015 (on the road. Day. Stop the road mileage, 17 cases; clean up debris on both sides of the road 20 , demolition billboard 30, demolition chaotic scaffolding house 3, clean Lane Hawking 15.) (3) road permit work to further 121、strengthen the implementation of administrative licensing system, strengthen the supervision and administration of the licensing. Strict implementation of the . According to the provisions of the road approval procedures and processes to carry out road license, do according to the law, the license i122、n accordance with the law, shall be subject to examination and approval of the. Implement the collective examination and approval, to strengthen supervision. Highways and approval of business implementation of technical review of administrative approval and separation, the audit focused on the more 123、complex involved in the road licensing matters, collective decision-making, to improve the scientific nature of the road administrative examination and approval, reduce approval corruption risks. Second is to promote the In administrative permission of information technology to improve service quali124、ty. According to the and ministries and provincial and municipal government, I realized the butt of Guangdong Province highway information network and provincial network business hall * * * branch office highways licensing examination and approval work. Simplify the licensing process, and strengthen125、 the office system, optimize the quality of service. (4) image of the team to further enhance a is grasp Windows image.2015 years, my bureau highways licensing in the city administrative service center settings window service. According to the and , I Bureau for damaged highway capacity compensation126、 standard, occupied by highway repair (lost) compensation expenses standards, in accordance with the law of administrative licensing items, the communications administrative license implementation procedures into the line on the wall publicity, in the service window is equipped with all kinds of app127、lication fill in sample, administrative licensing service guide brochure, in a conspicuous place public commitment to the system and advisory telephone complaints, for the masses provides warm and thoughtful service. Second is to grasp the Four Unifications working in the citys highway law enforceme128、nt image. According to the Ministry of transport and the ministries of the Provincial Bureau of the relevant documents, I board in front of the June 2015 completed the identification of law enforcement, law enforcement station appearance, clothing of law enforcement, law enforcement documents four u129、nification. (5) the AILU nursing atmosphere further formation of my bureau attaches great importance to the propaganda work of highway management road awareness month into * City Highway Bureau 2015 road administration work points. One is around the norms of law enforcement, improve the service them130、e road awareness month activities carried out. According to statistics, the citys highway system were deployed highways propaganda car 60 times, staff of highways 152 people, set point consulting 6, issued and publicity Data of 8000, hanging banners 134; broadcast 60 hours / 20, update 7 inch high r131、od making permanent propaganda page 4; in 7th edition published , purchased and distributed , legal text, a total of 500 this. The second is to carry out 12.4 national legal advocacy day activities, the city road officers go deep among the masses interpretation of highway Highways Management laws, r132、egulations and policy advocacy, analysis for illegal construction at both sides of the road, a typical case of illegal advertising management, showing public road construction and maintenance of highways The actual results of the management, the masses love protection consciousness and social awaren133、ess to further enhance the enforcement of highways.In recent years, I board in the highway management work were some beneficial explorations and the attempt, and achieved initial results, but there is still a certain gap compared with requirements of the Provincial Bureau and other brothers City, we134、 will to implement the partys spirit of the Fifth Plenary Session of the eighth session of the opportunity, and further increase the intensity of road management work, and constantly improve the overall quality of the workforce and the ability to learn, and strive to achieve the new highway across.T135、oday the topic of democratic life will I talk about the main to correctly treat leave turn ensure transition delicate gas is understanding, to carry out criticism and self-criticism, in-depth to find problems, profound analysis of the causes, through self analysis to find their own existence problem136、, to correctly understand their own, strengthen the party spirit training, to ensure that the election of smoothly and successfully completed. Below I talk about their own situation, please put forward valuable opinion. Main understanding (a) serious discipline, to create a delicate gas is in the ge137、neral environment in accordance with the Central Commission for discipline inspection organs, , municipal and county Party Committee Organization Department of the county Party Committee Organization Department files related to the spirit of the requirements, earnestly implement the nine is prohibit138、ed, nine shall be the solemn discipline, I earnestly study the . , , and file, and a profound understanding of the nine is prohibited, a nine law discipline essence and firmly safeguard the election of serious Ensure the unhealthy tendencies have successfully completed, and actively create a delicat139、e gas is the election of environment, to ensure that the election, so as to further strengthen the town leadership and cadre team construction. Through the study, in-depth thinking, to a serious discipline the importance and necessity of a more profound understanding. First, it is the iron disciplin140、e. The central put forward the nine is prohibited, nine shall be the reason for early serious general discipline, designated high-voltage wire, itself reflects the party committees at all levels of the reelection of attaches great importance to the objective is bright resolute attitude, the implemen141、tation of effective measures, the same candidate to fight with discipline election of wind Discipline in gas is health. Secondly, this is prevenient. From some typical cases, we can see that individual cadres election to engage in speculative hack canvassing votes, in violation of discipline, and ul142、timately paid a high price. The destruction of Hengyang election case and Nanchong canvassing bribery case that strengthen election discipline, serious election discipline of necessity and importance. The discipline of publicity to the public, wide report, that is, early warning, early hit precautio143、nary needle, tell the cadres should do what shouldnt do, what to do and what not to do, and better education of cadres, warning cadres, and build a strong line of defense, to avoid the occurrence of similar problems. There is duty. Serious discipline, with a strong team is an important starting poin144、t. As the leadership of the party members and cadres, take the lead in the implementation and take the lead in upholding the election of discipline, which is a major political responsibility. Must be clear requirements, strict constraints themselves, cherish the honor, safeguard the image of the org145、anization; promote righteousness, play an exemplary role. Especially as deputy Township, but also to give a full play to its role, always stand in the discipline of first-line maintenance. The wind Su Ji through the election of the work of the whole process. (II) serious discipline, treat correctly 146、leave turn as a cadre of the party, whether it is in, is back, stay, turn are organizationMetabolism of entrepreneurial career, need and development need. So, his first with a broad mind to treat leave turn. The position is officer positions, power for the people service tools. Different positions o147、f the partys cause, plays a decisive role, the same important. To ability strong, style of comrade to important positions and applause, is full of vigor and vitality and promising young cadres in leadership and cheer for their own leave turn and calmly face, calm place. Second is to a healthy state 148、of mind to treat leave turn. The personnel of metabolic, between the past and the present. Cadre new old alternant, team, push In the party constitution control strict working to career development objective need, is never the end of the historical process. Each a cadre must face up to the laws of n149、ature to think we also took the former relay baton go on leadership post, regardless of the current positions, positions and responsibilities have what change, can do for peace of mind and mood, such as water, in a happy mood. (3) carefully and find out the problem, correct understanding of themselv150、es, even though they do conscientious, serious attitude, honesty in politics, but high standard , the control standard, especially control learning, striving for excellent activities emerge in large numbers of advanced characters, advanced deeds Static not consciously practice the strict three real 151、and strengthen the party spirit accomplishment to find the gap, swing is insufficient, a clear direction, mainly manifested in the following aspects: one is the learning initiative and self-consciousness. Often busy with work as an excuse, not consciously take the initiative to spare time to learn. 152、Is often superior to learn what to learn what, and work closely to learn, and working relationship is not less to learn. Mainly manifested in the theoretical study is not thorough, system is not thorough, the Marxism Leninism, Mao Zedong thought, Deng Xiaoping Theory and Three Represents important t153、hought, the scientific concept of development and learning, general secretary of the series of speech learning, just from the surface on learning In the less less less and not deep enough, not from the deeper study, to study, to understand, to sentiment, to use, to guide the work. The second is to i154、nvestigate the research. This year their participation in the county, the county governments important meeting, the town Party work time is more, coupled with the specific affairs busy, in-depth primary research time reduced. The inspection was carried out research activities, there are surface exam155、ination, thematic research, listen to reports and discussion research, the general requirements and specific guidance, in a certain extent, affected the timely discovery and solve. Third is the level of leadership, leadership and need to be further improved. Stroke the personnel selection is positiv156、e, work coordination and cooperation cant to the best effect; in the coordination to deal with some complex problems, the approach is not enough. Especially encountered, time is tight, the task is heavy, is often the soldiers to be blocked, the water to soil cover, struggling to cope with. The globa157、l and forward-looking innovation is not enough. (4) to ensure that the transition delicate gas selected loyal to the party loyal to the people of leading cadres (recommended) for the county to provide accurate information to ensure the transition in the air, after the general election of work have a158、 greater change. The second is balanced, promote the work in an orderly manner. In the future a period of time, the transition will be in the county under the leadership of the Extended surface. And breeding industry and the construction of key projects also in actively, they have to seriously consi159、der, overall transition and key projects to promote. Education team members and the town, village cadres actively participate in industry cultivate the work, with outstanding achievements to accept the assessment of test of the organization and the masses of the people, in the town set up promising 160、is a strong general business and the right atmosphere general election, do election and projects to promote the two not mistake, the promotion of two. Second, the rectification measuresOne is to enhance learning, awareness raising, he will continue to strengthen learning, improve the level of awaren161、ess, their own unity of thought and action to the county, township party committee of arrangements for the election. The second is correctly, strengthen discipline, own the right of transition, a matter of personal leave turn, as a town, deputy secretary of Party committee, themselves are fully awar162、e of the only serious work, strict demands on themselves in order to not negative expectations of organizations and the masses, so that individuals can well deal with good transition in personal leave turn. Three people on the election promise as Deputy Secretary of the Party committee, in the elect163、ion of my solemn commitment to Catch: if a is strictly abide by and take the lead in the implementation of the nine is prohibited, nine transition discipline, not to engage in cliques, not to engage in canvassing votes buying and selling, buying, and no fraud swindlers officer, do not intercede say 164、hello, not illegal, not to run gas leak, do not interfere with changing times, accomplish strict discipline, warning, with iron discipline firmly put unhealthy trends, promote delicate gas to ensure transition in the healthy and orderly development; the second is resolutely obey organization arrange165、ment, and resolutely to stress the party spirit, principle, discuss overall situation, correctly treat personal leave turn, the correct treatment the election results and focus on their careers, from start to finish, ensure the normal and orderly develop.For in-depth study and implement the partys e166、ighteen, the eighth session of the fourth, the spirit of the fifth plenary session, the implementation of comprehensive strictly required, a solid grasp of the construction of Party member team, in accordance with the requirements of the county Party Committee Organization Department No. 3 (2016) Lu167、o Zufa. According to the requirements of the and the central work of education for the party members, combined with actual town, 2016 Party member education and training scheme is formulated. The guiding ideology adhere to a comprehensive study of implementing the scientific development view as guid168、ance, in-depth study and implement the partys eighteen, the eighth session of the fourth, fifth plenary session and the General Secretary Xi Jinping series important Speech adhere to the application for promoting learning, and strive to improve our ideological and political quality of Party members;169、 firmly establish catch a party to build pipe must be members, tube members first catch education of ideological understanding, close to the Party members ideological and practical work, strive to build a party regular education work mechanism, promote the party members play a vanguard and exemplary170、 role; firmly grasp the construction of ability of administration of strengthening the party, advanced nature and purity of construction of the main line, adhere to to enhanced grasp the party building work consciousness, strengthen the self construction of the party organizations as the fundamental171、 starting point, for the towns economic and social development provided for ideological and political guarantee of the strong and powerful organization guarantee. Second, target 201 The main task of 6 years of education and training of Party members is earnestly implement the (Luo Wei do 2015 121) t172、o further strengthen the work of the education and training of Party members request, to training the town, the grassroots party members and common. From 5 January 2016, through a variety of channels in a variety of forms in a planned, step by step, to focus on the organization to carry out the educ173、ation and training of Party members. A party spirit idea generally enhanced. Through education and training, prompting the majority of Party members to further strengthen the ideal and faith, enhance the party concept, consciously practice the agency will socialist core value system. To further enha174、nce the confidence of the road of socialism with Chinese characteristics, theoretical system of self-confidence and confidence. (II) Party members working ability greatly improved. Through the development of education and training, to boost the knowledge structure of Party members transformation and175、 upgrading, improve the party to use the Marxist stand, viewpoints and methods of analysis and problem solving ability, adapt to the new situation and new tasks. (3) play an effective role of Party member model. Through the development of training and education, promote the party members in theProdu176、ction, work, learning and service to the community in give full play to the exemplary vanguard role, and actively striving to take the lead in learning to improve and take the lead in striving for success, serving the masses to take the lead and lead law-abiding, take the lead in promoting the healt177、hy atmosphere model. (4) the building of grassroots organizations strong impetus. Through the development of education and training, the Party member troop overall quality and ability to serve the people increased, grass-roots party organizations creativity, cohesion and combat effectiveness of the 178、improved. Contents and measures according to different type of the town, at different levels, the actual needs of the different positions of Party members, hierarchical class to carry out the education and training of Party members. Adhere to the town overall and please tutoring, please Come in and 179、sent down the combination, to the party spirit education and ability cultivation as the center, overall constitution and discipline, the core value system, political theory, domestic and international situation in town situation, party organization construction, legal education, culture, science and180、 technology, industrial development, management, resource management and protection, social management innovation in the aspects, to village (unit) as a unit, to all members of the organization a above rotation activities. Focus on Township and village committee cadres straight unit leading Party gr181、oup secretary, activist of join or be admitted to the party, the education and training of village class mothball cadre training, efforts to strengthen the parties organization Secretary of party spirit accomplishment, do a good job of the consciousness of the party building work, enhanced the Party182、 activist , people in rural areas to promote rural economic development of practical abilities. At the same time, through the development of the theme of practical training, autonomous learning training, make full use of the party members and cadres of modern distance education network etc., for the183、 party members in various fields to carry out the classification of rotation, party spirit training, tobe grind quality, improve quality. Organizational Leadership (a) strengthen leadership, implement the responsibility. Town Party committee to the work of the education and training of Party members184、 into the party building work important content, the overall responsibility of the Secretary of the Party committee, vice secretary of the lead and the implementation of specific members of the organization, the organizational Secretary of the parties to personally plan, personally deploy, supervise185、 the implementation; the education and training of Party members to carry out into the grass-roots party Construction work responsibility system and the building of grassroots organizations special assessment, directly with the grass-roots party organizations Pingxianpingyou link, to strengthen the 186、organization and leadership to do a good job of work to implement. (II) the overall progress, implement the plan. Ensure that the deployment, according to the arrangement of the 2016 Party member education and training plans, based on the actual needs of the party, on-demand rationing; do supervisio187、n and guidance, strengthen the supervision of the work of the education and training of Party members, guidance and services to help solve the difficulties and problems in the training; assessment, by listening to the report, information search, evaluation, etc., with emphasis on the assessment of t188、he implementation of the plan, Party members to participate in training proportion and effect, indeed Protect task implementation. (3) the typical guide, step up publicity. Pay attention to cultivate advanced and typical, timely promotion and the typical experience of the characteristics of the prac189、tice. The work of the education and training of Party members as the focus of the grass-roots party building and the sector skills training for communication and advocacy, by setting the column, offering special journals and other forms of propaganda, to create a strong atmosphere of public opinion,190、 promote the orderly conduct of the work and achieved certain results.In order to further implement the General Secretary Xi Jinping series of major speeches about the partys work style and clean government and anti-corruption struggle spirit and the central, province, city, County Commission for Di191、scipline Inspection and the spirit of the plenary session, to further strengthen the awareness of the loyal party members and cadres, sense of purpose, sense of responsibility and a sense of discipline, boost the countys economic and social development. In accordance with the ensemble of Ji Qing 201192、6) spirit of the document No. 3, combined with my bureau actual, make this program of activities, and a theme of learning party discipline, strict discipline, boosting Qingshen development.Second, activity time April 2016 1 - April 30, three, activity content (a) carry out party discipline learning 193、activities. Global organization of cadres and workers to focus on learning, network learning, self-study and other forms of strengthen constitution , and other relevant information learning. Education for Party members and cadres to as the ruler, combined with its work, measure, control and their ow194、n ideas and practical test, take the initiative to conduct Lianzheng is affirmatory consciously practice commitment, achieve the hearts of the party, Zun Jishou Confessions of readings of the Si confessions to carry out the hearts of the people, in the heart has the responsibility, in the heart has 195、quit, maintain the partys advanced nature and purity. (2) to carry out special warning education activities. In the global read writing experience, the concept of warning education independent micro film reflections, prisons and courtroom free as the main content of the special warning education act196、ivities. Use of the weekly worker will focus to watch a warning education. The , cadres and workers to write their feelings, reflections, and the clean publicity column posted; 4 month global organization of Party members and cadres to the eyebrow delta prison visits to detainees xianshenshuifa educ197、ation of cadres and workers With low-cost combined with special method. (3) to teach a class of anti-corruption initiate cheap course. By the leaders of anti corruption and financial supervision and administration of state-owned assets of explain the profound things in a simple way to explain, so th198、at all staff of honest business, according to the law to act in a more profound understanding, so as to enhance staffs sense of responsibility and sense of mission. (4) to promote innovation to help the family activities. To carry out the party members and cadres motto, bright family traditions acti199、vities for family education into harmony, filial piety, encouraging learning, goodness, thrifty, inspirational, cultivation of excellent genes to guide Party members and cadres to good tradition folk, with a good tradition being honest, with good tradition promote political winds, creating a delicat200、e gas is the general atmosphere. Four activities (a) to strengthen leadership, careful organization. One is the establishment of the independent warning education month activities leading group of the state owned Financial Bureau, bureau leading Party group secretary of the leader, board members of 201、the team to serve as deputy head. The second is making determine promotional content, clear steps, truly understanding, measures, and put in place, ensure the effectiveness of the activities. (II) take all factors into consideration, pay attention to actual effect. According to strict three real spe202、cial education and two studies do activities, in based on the provisions of the action without aliasing, and creativity to carry out various forms, rich and colorful activities, and strive to Pay attention to actual effect, and resolutely prevent, going through the motions, really promote the party 203、members and cadres from the depths of the ideological solidating abide by discipline regulations of the defence. (3) strengthening propaganda, to create atmosphere. To make full use of the column publicity, propaganda position of network, increase publicity efforts, expand warning education activiti204、es of the coverage and influence.Today, we hold the citys precise technology to poverty alleviation and project work to promote the meeting, the main purpose is to further promote the task of aiding the poor with technology roots and accelerate all kinds of scientific and technological projects. Las205、t year, this year, the citys scientific and technological work has made remarkable achievements, such as the convening of national poverty alleviation of science and technology on the spot will, cultivate high-tech enterprises, Bashan scholar training and the introduction of scientific and technical206、 personnel incentives, listing national agricultural science and Technology Park, science and technology incubator building. Just now, Huangli In recent years city science and technology to help the poor and science and technology project effectiveness, the main problems were analyzed, and in a peri207、od of time in the future, the citys precise technology to poverty alleviation and science and technology project work arrangements, I agree, I hope everyone to earnestly implement. Here, I stressed the three points.Learning learning, to carry out the learning and doing education as the citys innovat208、ion and development of an important driving force. The Party Central Committee decided to 2016 years in all Party members to carry out learning the party constitution, party rules, a series of speech, do a qualified party member education (referred to as learning to do). Some time ago, I called the 209、learning the party constitution, party rules, a series of speech, do a qualified party member education and mobilization, the province carried out within the two a learning education mobilization. Municipal Party committee will soon be held a mobilization will make arrangements for the deployment. T210、o carry out the two a study and education, based on learning , key in do . As the science and Technology Department of cadres and workers, to (benchmark for two pilot demonstration study through studying the party constitution of party compasses, a series of speech, not only to do a qualified party 211、members, to do a good job of science and technology innovation. Next week, I as the citys county-level leading cadres reading class open cooperation and innovation driven study group members went to Mianyang, Meishan national innovation driven development characteristics and the provinces Innovation212、 Driven Development Zone work experience, a great harvest, feeling very deep. Mianyang, Meishan city innovation driven strength is very great, especially is Mianyang has become civil military integration, a comprehensive reform and innovation, our benchmarking in Mianyang, the gap is very large. Mia213、nyang Science and technology city construction as the basis, built around the Five goal of building Hotbed of innovation of construction science and technology, military and civilian fusion demonstration, collecting and distributing center of scientific and technological achievements, innovative tal214、ents convergence and high technology industry concentration), vigorously promote to military and civilian fusion for the characteristics of comprehensive reform pilot innovation, and achieved remarkable results, is toward the national civil military integration innovation demonstration area, the nat215、ional innovation driven development characteristics demonstration area and western economic development growth emerging great step forward. The expanding Park, stronger innovation platform; incubated enterprises, cultivate innovation; poly talent, to improve the ability of innovation; promoting fusi216、on, highlighting the characteristics of the innovation; catch open, form innovation efforts of the experience is worth learning from. Benchmarking advanced, we have to struggling to The amount of weight is to grasp to catch the strategic innovation. To improve the target oriented system. The innovat217、ion actually placed in the core position, firmly establish the grasping innovation development, seek innovation is to seek the future, innovation is not backward, slow innovation also will lag behind concept, accelerate factor driven to innovation driven change. City Branch Bureau to actively seek t218、he city management system emphasizing the innovation driven development, focus on strengthening the scientific and technological enterprise incubator construction, scientific and technological innovation platform, technology oriented small and medium-sized enterprises to cultivate, high and new tech219、nology industry output value and product evaluation. Second, we must built innovation and Entrepreneurship platform. The city will be in Pakistan and the open area to build the whole To confidence, double center, the new industrial park for a period, the city public entrepreneurship Park Phase II, Q220、in Ba electricity supplier industry park for three period, incubation area of more than 50 million square meters. The county (District) to take advantage of idle assets of construction science and technology enterprise incubator, a passenger space and other new public record space, the formation of 221、a, a, a, to create vivid situation. Third, we must foster technological innovation subject. To vigorously implement the high and new technology enterprise doubling plan and science and technology oriented small and medium-sized enterprises to cultivate plan, to honor the implementation of tax incent222、ives, financial subsidies, such as a package of policies to support, so that high technology enterprise indomitable spirit, let the small and medium-sized enterprise overwhelming. To increase investment in science and technology innovation. To actively seek special funds for the development of Munic223、ipal Science and technology part for cashing innovation drive the development of financial subsidy policy, transfer a portion of funds for science and technology enterprises of loan guarantees and interest subsidies. Encourage banking institutions set up science and technology branch of the franchis224、e, push the patent pledge loan, for the small and medium sized enterprises of science and technology provide financing services tailored. Fifth, we must strengthen science and technology personnel. To attract more technology military personnel and high-end talent with technology, project, with funds225、 to Bazhong Lingban or joint science and technology enterprises, encourage and support both inside and outside the citycomrades and the5 years of college graduates and college students to a new public space, science and technology business incubator innovation and entrepreneurship.Second, it is nece226、ssary to promote the precision technology poverty alleviation as the important content of the scientific and technological work. To build a well-off society in an all-round way by 2020 is the partys eighteen to the whole Party and the people throughout the country to make a solemn commitment. Lead t227、he city people out of poverty to become rich go straight towards well-off, Party committees at all levels, political responsibility and mission of the times of the governments major political, technology sector is also the bounden responsibility. Municipal three tenth plenary session made , proposed228、 to further promote the five a group of precise action to help the poor, six precision and 1 + 6 poverty alleviation projects, clear the add Great science and technology achievement transformation efforts, accelerate the construction science and technology poverty demonstration village and demonstra229、tion households, give full play to the role of modern information network, for the impoverished village poor households to provide production technology, market information, policy advice, encourage scientific and technical personnel to the poor village launched a to one helping and guiding the deve230、lopment of income industrial projects, strengthen technical training and propaganda of popular science, highlighting grasp large breeding, family farmers, agricultural co-operatives are the backbone of the training technical poverty alleviation mission. The citys science and technology sector must b231、e from the political height, the assault fortified positions that help deficient up as the most important task, the most urgent work. The most arduous mission, to science and technology for precise poverty alleviation promote to speed up a well-off society in an all-round way Decision to deploy, boo232、st the process to precise technology to poverty alleviation and the effectiveness of a well off society in an all round way. One should obey the overall situation. The citys scientific and technological system of cadres and workers, especially leading cadres, should have the political consciousness,233、 ideological conscious action conscious, in accordance with the central, provincial and municipal deployment requirements, to strengthen the organization and leadership, reasonable arrangement of time, carefully study the deployment, to ensure poverty. There must be resolutely implement the politica234、l position and character, poverty alleviation and the attitude to be distinctive, poverty alleviation action should be strong, to politics, to understand the overall situation, re implementation, see results. To lock the target. In accordance with the provincial Party committee and the municipal Par235、ty committee, municipal government, lock 2 provincial-level General requirements for the completion of the goal of poverty alleviation poverty alleviation poverty alleviation poverty alleviation poverty alleviation poverty alleviation and Technology Demonstration County, four provincial science and 236、technology demonstration towns, 10 provincial science and technology demonstration village and a municipal science and technology demonstration area, 2 Municipal Science and technology demonstration towns, five municipal science and technology demonstration village and the five one precise technolog237、y to poverty alleviation and special operations tasks, inverted duration, wall chart battle, set the time, tasks, measures, staff, given the responsibility to ensure high quality precision technology poverty alleviation task. To focus on the key. To focus on precise poverty and accurate out of pover238、ty, detailed measures, clear job responsibilities, to develop targeted and operable precise technology to implement poverty alleviation program. Prominent precise poverty technical training, poor village informatization construction, technology oriented poverty reduction model village and demonstrat239、ion households construction precision technology poverty alleviation focus, in a precise sense, precise attitude, precise style, go all out to fight the precise technology of poverty alleviation and battle.Three, it is necessary to strengthen science and technology funds supervision as an important 240、means to enhance the quality of the project. Science and technology project fund supervision is the key to the implementation of the project of science and technology. In recent years, especially during the Twelfth Five Year Plan period, the system of science and technology management in the city vi241、gorously to declare the implementation of the country and province science and technology projects, science and technology demonstration lead brought obvious effect and improve the scientific and technological innovation capability of enterprises, boosting the characteristics and advantages of indus242、trial development, science and technology support to the economic and social leading role improved significantly. In the project management of science and technology, in addition to seriously implement the state, provincial science and technology project management rules and regulations, and the act243、ual Bazhong, established the access system of science and technology projects, the project of science and technology commissioner system, science and technology Project credit system and scientific and technological projects honest commitment system, and the Municipal Finance Bureau jointly issued t244、he Bazhong City Science and technology development funds management approach, formulated the trilogy of seven science and technology project implementation specification, these are worth fully affirmed. However, we should also see clearly, we in the science and technology project management still ex245、ist account of the special accounts, earmarking system is no effective implementation and other issues. In particular, this year the Audit Commission Chengdu Tepai ban on Bazhong confidence found in the audit of science and technology business incubatorProblem has certain representativeness. The aud246、it to us sounded the alarm, should cause everyone vigilance. Here, I will strengthen science and technology project budget supervision put forward four requirements: a strict project reporting, prevent fraud. Implementation of the project to declare the competition mechanism, the annual financial su247、pport to science and technology projects oriented society Bulletin, conditions open content, open competition to declare, open field investigation, public presentations, the public assessment of the decision, do full open and transparent, fair, accept social supervision. To those who resort to decei248、t or something real is not clear, suspected of defrauding, impersonator national subsidy funds, once found immediately cancel Declaration of qualification, recovery of funds subsidy and discipline in accordance with the law strictly held responsible. Second, we must innovation funds supervision. In 249、county finance to establish science and technology project account, the project undertaking entity in accordance with the key nodes task completion by formal invoice to apply for funding and audited by the Department of science and technology, the Ministry of finance funds, and resolutely put an end250、 to project funds are retained, misuse and misappropriation. Third, we need to strengthen scientific and technological project supervision. Department in charge of science and technology to strengthen project inspections to check or checks, of ineffective implementation to strengthen the supervision251、 and the existence of violations of responsibility into the project undertaker rectification. To establish a scientific and technological project, black list system, the Project implementation quality particularly poor recorded in the black list, stage or permanent abolition of the applicant country252、, province, city science and technology project qualification. Fourth, it is necessary to carry out training funds management. Science City Bureau to the initiative to meet with the finance department, organize project unit commitment held science and technology project funds management training, of253、 country, provincial and municipal science and technology project funds management of the relevant policies, financial acceptance specification, mid supervision points, budget review points and key contents were training system, to ensure the use of project funds safe and reasonable.Thank you all!To254、 implement the central, provincial, city and county to make important decision about the grass-roots party construction work in the deployment, push forward the county public security organs in the work of Party building, further strengthen the party secretary of the governing party and party liabil255、ity, according to requirements, according to the arrangement of the Bureau of the party work. Today, the organization held the county public security organs party secretary grasping grass-roots party construction work in the debriefing will. The implementation of this is a powerful measure to the Se256、cretary of the party organization construction of the party, and is learning to carry out the partys spirit of the Fifth Plenary Session of the eighth session of the, grasp the new situation of Party building work under the rules, pushing Public security party building services in the public securit257、y center of the inevitable requirement.Just now, the 3 Juzhu unit Party branch secretary of debriefing, below I on the 3 party organization work one by one review.Party branch of the Political DepartmentGood: first, strengthen ideological and political work, pay close attention to the work of the im258、plementation. The Political Department of the Party branch strictly in accordance with the requirements of bureau Party committee, to strict three real special education as the main line, take effective measures, pay close attention to the ideological and political work of the implementation, streng259、then the education of Party members and the police thought, improve the Police Ideological and political consciousness, make a solid foundation for public security work smooth development of health. Second, strict management team, boost the morale of the team. Strict implementation of Police Ideolog260、ical Trend of periodic analysis, timely grasp the ideological situation of the personnel; strictly implement the system of check on work attendance, strengthen the daily management; cash rewards and punishments, continue to boost the morale of the team. The third is The intensification of police tra261、ining, improve the police actual combat skill. Seriously and actively carry out a series of training activities and learning activities, the majority of police in the political quality, physical quality, professional quality, policing skills improved. The fourth is to adhere to the preferential trea262、tment from the police, the warm pool police. According to thRequirements, and actively do a good job of personnel management work, to run within the scope of the policy, help the police solve the practical difficulties, the police systemic heart into work. The fifth is strengthening propaganda, prom263、ote righteousness. Around the center of the public security work, actively do a good job in the publicity, fully display the spirit of good public security team. Six is to fulfill the responsibility of Party building, do a good job of education and management of Party member team. Sound and perfect 264、three class, Party of democratic appraisal, commendation and reward system, effectively enhance the branch of the creativity, cohesion and fighting capacity.Shortcomings: is ideological and political work still can not adapt to the new situation, new task, in the form of a single, innovation is not 265、enough, lack of learning education of the appeal and study the effect of education needs to be improved, the political department to strengthen the guidance to the grass-roots units. The second is the branch of organizational life will implement the is not good enough to play an exemplary role.Traff266、ic Police Brigade Party branchSystem of good practice: one is grasping the implementation of the work of Party building system, enhanced branch team cohesion, combat force. The brigade Party branch always pay close attention to the work of Party building and would not let go, conscientiously perform267、 their duties, strict implementation of democratic life etc., to develop the branch of learning plan, all equipped with learning record the experience and experience the and organize regular inspection learning, ensures that the learning plan, implement, effect. Second is to carry out the strict thr268、ee real special education. The development of special education learning scheme, held a party branch focus on learning and the level of consultation forum, deputy director in charge of, brigade leader for the party members and the police on the lectures, deployed to carry out Ban Zicheng throughout 269、the Yan Zhenchang Yang Shuicai to relive the oath to join the party, visit the memorial hall, learning advanced characters, micro lectures attention and learning characteristics of the activities, and to develop measures for rectification. Three is to pay attention to the party building work into th270、e public security work. The brigade Party branch and always will be the work of Party building in 9.3 security, national civilized city re examination, the SCO security meeting, the focus of illegal investigation, sword, anti terrorist violence, to ensure safety, five wave, camp turn non bus, detoxi271、fication, the focus of the work, in a timely manner to carry out the pre war mobilization, wartime dynamically judged, the post-war award in recognition of a series of measures Members always fighting in the first line of traffic management, all traffic police has always maintained a high state of m272、ind, a strong impetus to the work carried out.Shortcomings: first, there is a hand hard and soft phenomenon. Of work of Party building under the new situation is not enough emphasis, focus on light business building, re form light effects. The second is measures are not enough effective. In particul273、ar, catch a party to build working innovation consciousness is not strong, measures and methods used in the experience of the old, old practices and effectiveness needs to be further strengthened. The third is three lesson not very good insist, life of the party organization to carry out less often.274、Zhao police station Party branchGood practice: one is to strengthen the study and education. To strict three real special education as an opportunity to take leadership lectures, seminars, individual learning, exchange of experience in various forms, the police organization learning leaders at all l275、evels of the spirit of the important speech, in the constitution as well as the side of corruption cases and asked party members and the police carefully recorded study notes, writing experiences, join and pay attention to the micro lectures, according to the control requirements of inspection, enha276、nce their own, to ensure that the learning effect. The second is to strengthen the leadership responsibility. Party branch secretary as the first responsibility of honest government, earnestly implement the four person , and insisted on the important work personally Department Department, major issu277、es personally intervene, personally key aspects of coordination, supervision of important cases personally , Party branch members always strict demands on themselves, play an exemplary role model. Third, strengthen the service for the people. Every act of the masses for the warm reception, carefully278、 recorded masses anti reflect each a problem, and make the resistancee bureau Party committeeHeart to answer, and constantly improve the quality of service. Combined with the one village, one police work, police organization carefully touch row all may affect the stability of the unstable factors, r279、esolve conflicts and disputes, and arrange for the police with daily visits, issued security leaflets, collecting sites, personnel information, promote the harmony police.Existing problems: a party branch team party affairs knowledge is not rich enough, on some of the procedural provisions are not f280、amiliar with, in a certain extent restricted the work carried out. The second is regular ideological education is not deep enough, the ideological trends of the police command is not timely and accurate. Third, there is a need to improve the management level of refinement, police standardization awa281、reness is not strong enough, daily habit is not quite self-conscious.Since this year, bureau unit Party branch to strict three real special education as the main line, to the service center, troop construction as the focus, adhere to the combination of ideological building of the party and the syste282、m of the party, solid to carry out the comprehensive strictly required, to further standardize the construction of the party organization, continuously improving the quality of Party members and police, continue to strengthen the party building innovation, service building execution significantly im283、proved, has made remarkable achievements.Meeting debriefing of 3 units in the work of Party building problems in other units are also different degrees of existence to other units by the party building debriefing, draw on the experience of face the problem, replicability, careful analysis of rectifi284、cation, promote the sustained and healthy development of the work of Party building units.Below, to further strengthen the county public security organs party building work stressed the views of five points.One, improve the ideological understanding, enhance the sense of political responsibility and285、 historical missionFollow the basic construction of the partys eighteen years, Xi Jinping, general secretary: the series of important speech to the party put forward many new ideas, new judgment, the new requirements is to promote grass-roots party building work. We should thoroughly study and under286、stand, and consciously assume responsibility. One is to grasp the party building three questions of the new requirements. Xi, general secretary of the partys mass line education practice summary of the General Assembly on the proposed the construction of three questions, namely: is not the party com287、mittees at all levels and the departments of Party committees (party) to achieve the sedulous catch a party to build is not at all levels of Party committee secretary, the Department of the party committees (party) secretary become strictly administering the party secretary? Is not at all levels and288、 all departments of the party Forced the construction of Party committees (party) members to fulfill the responsibilities strictly responsibility? General Secretary of the party building three questions , directed at the crucial point, enlightening, three mirror placed in front of everyone, let you 289、according to a photo, see a look, want to think about the conscious of it, is the three pieces of papers placed in front of us, it is clear to judge ourselves whether in to do their duty. Building three questions , urge people to watch, thought-provoking, and convey a strong responsibility to ask si290、gnal. The second is to understand the building three no new judgment. Xi, general secretary of the partys mass line education practice summary congress pointed out that history and reality Are accounted for in the police forces of discipline, do not do, is to stop the event tells us, not a clear res291、ponsibility to implement the responsibility, accountability, and strictly administering the party is not to . General Secretary of the three no , a clear responsibility to implement the responsibility, accountability, and point out the key. The county public security organs is a team of the Communis292、t Party as the main body, Party members and the vast majority of bureau of belonging to different units of the leadership cadres and backbone of the party members, the power and responsibility are relatively concentrated in the partys construction, must be clear responsibilities, the implementation 293、of responsibility, accountability, or catch a party to build is an empty word. Three is to clear the three grasping new initiatives. The total learning book Remember that catch a party to build must grasp the responsibility system, grasping accountability must grab the responsibility person, graspin294、g the responsibility must catch the first responsible person. Why should we let the Bureau unit Party branch secretary of the debriefing is to implement general secretary put forward 3 catch. To seize the party organizations primary responsibility, seize the key issue.Two, the full implementation of295、 the task of ideological construction, the theory of armed tasks implementedGeneral Secretary Xi Jinping in the mass line of educational practice summary congress put forward in the new period party building thought of tasks and requirements, to strengthen the construction of the Party pointed out t296、he direction and path. One is to strengthen theoretical study. The urgent task is to fully understand the study and implement the spirit of the fifth plenary session of the eighth session of the significance of, the organization of Party members and the police through the focus on learning, self-stu297、dy and special counseling and other forms of serious in-depth learning, adhere to the first step in learning, deep layer, accurately grasp the spirit of the Third Plenary Session of the Eleventh Central Committee, and do the thinking and learning gains, use it. The second is to strengthen the party 298、spirit temperance. Adhere to the school party constitution. Through the center of the group learning. Secretary of the party organization about lectures and other forms of learning the party constitution, enlightenment spirit, guide Bureau unit Party branch and all members of the police to firmly es299、tablish the consciousness of the party. Persist in learning advanced. Vigorously carry forward the spirit of Jiao Yulu, Yang Shuicai spirit, seriously study the advanced deeds of Comrade Yan Zhenchang, deep fine shine Dusing the police party guided, to strengthen public opinion and public servant co300、nsciousness, consciously practice the strict three real. The third is to strengthen the party and Party discipline education. For the ideological construction of the party faces new tasks, new requirements, the emergence of many new problems, new situations, and actively take the initiative to adapt301、 to the constantly emancipate the mind, innovative ways, making use of the Internet, micro channel, micro Bo new platform for new, enrich the content of education, improve education forms, the constant reminder education, enhance the police Party discipline in awe, guide Party members and the police302、 do political understanding discipline about the rules of the leaders. The fourth is to strengthen the ideological and moral education. Guide the party police exemplary practice the socialist core values, cultivate good political and moral character, professional ethics, family virtue and morality, 303、forming a strong atmosphere of moral construction. Pay attention to strengthen the positive guidance to the police party ideology, adhere to the diversification of the social ideology guided by the system of theories of socialism with Chinese characteristics, improving and perfecting the Party membe304、rs and the police thought The dynamic analysis of mechanism, providing an ideological guarantee for the purity and firmness of team members.Three, fully implement the strict requirements, the management and administration of the partys responsibility to implementGeneral Secretary Xi Jinping stressed305、 that to implement strictly the responsibility, do a good job of Party building as the biggest achievement. Therefore, in my bureau implement comprehensive strictly required must be the party tube responsible party implemented. First, to further implement the responsibility system in Party building.306、 To establish and improve the party building responsibility assessment mechanism, at the beginning of the year to progressively signing party builds working target responsibility book. Party organizations at all levels is mainly responsible for comrades to do a good job of Party building as the grea307、test achievements, adhere to the development wholeheartedly for, to concentrate its attention on the construction of the party, the party building work is included in the agenda, and business to work with the deployment, with checks, with the implementation of, true to form Party grasping, Secretary308、 to take the lead in efforts, in charge of the leadership Specific catch, catch a, layers of implementation pattern of Party building work. Is to improve the reporting and appraising system. In accordance with the debriefing the party building, the appraisal rating of Party building, Party building 309、assessment test, use of cadres at request of the party, CF county Party debriefing practice, and constantly improve the annual party built debriefing appraisal system, in particular, to the year debriefing appraisal evaluation and annual comprehensive examination closely together, the party builds t310、he job evaluation results into the leading bodies and leading cadres of the annual comprehensive assessment system, strengthen the use of dynamic management and results of debriefing appraisal work, further enhance the debriefing appraisal of scientific, effective and directive The new integration b311、usiness. Three is to improve the three class system. Three class system is to improve the partys organizational life, strict party member education management system, we must do a good job in the implementation and long-term persistence. According to the party secretary of the organization lectures,312、 party members and cadres micro lectures and Thematic Party Day activities, innovation three class form, rich three class content, pay attention to the work of Party building with the public security work, the formation of the same resonance frequency, the linkage of communion party organization lif313、e situation. At the same time, the three class system implementation of join or be admitted to the party organization committee debriefing appraisal of important content, strict grasp the three class system Real.Four, strict political discipline and political rules.Guide all Party members and the police in ideological political action always as the general secretary of the CPC Central Committee with Comrade Xi Jinping highly consistent, involved in major political principle, p