1、拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂直度%开始时间结束时间01Z01LS01126.371299.108:2108:2402Z02LS02126.371299.208:2408:2703Z03LS03126.371299.308:2708:3004Z04LS04126.371299.208:3008:3305Z05LS05126.371299.108:3308:3606Z06LS06126.371298.708:3608:3907Z07LS07126.
2、371299.208:3908:4208Z08LS08126.371298.908:4208:4509Z09LS09126.371299.108:4508:4810Z10LS10126.371299.509:0209:0511Z11LS11126.371298.809:0509:0812Z12LS12126.371299.109:0809:1113Z13LS13126.371298.909:1109:1414Z14LS14126.371299.209:1409:17拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备
3、注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂直度%开始时间结束时间15Z15LS15126.371299.014:2114:2416Z16LS16126.371299.214:2414:2717Z17LS17126.371299.414:2714:3018Z18LS18126.371299.214:3014:3319Z19LS19126.371299.114:3314:3620Z20LS20126.371298.714:3614:3921Z21LS21126.371299.214:3914:4222Z22LS22126.371298.814:4214:4523Z23LS23126.371
4、299.114:4514:4824Z24LS24126.371299.415:0215:0525Z25LS25126.371298.615:0515:0826Z26LS26126.371299.015:0815:1127Z27LS27126.371298.815:1115:1428Z28LS28126.371299.115:1415:17拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂直度%开始时间结束时间29Z29LS29126.371299.010:2110:
5、2430Z30LS30126.371299.210:2410:2731Z31LS31126.371299.410:2710:3032Z32LS32126.371299.210:3010:3333Z33LS33126.371299.110:3310:3634Z34LS34126.371298.710:3610:3935Z35LS35126.371299.210:3910:4236Z36LS36126.371298.810:4210:4537Z37LS37126.371299.110:4510:4838Z38LS38126.371299.411:0211:0539Z39LS39126.371298
6、.611:0511:0840Z40LS40126.371299.011:0811:1141Z41LS41126.371298.811:1111:1442Z42LS42126.371299.111:1411:17拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂直度%开始时间结束时间43Z43LS43126.371299.010:2110:2444Z44LS44126.371299.210:2410:2745Z45LS45126.371299.410:2710:304
7、6Z46LS46126.371299.210:3010:3347Z47LS47126.371299.110:3310:3648Z48LS48126.371298.710:3610:3949Z49LS49126.371299.210:3910:4250Z50LS50126.371298.810:4210:4551Z51LS51126.371299.110:4510:4852Z52LS52126.371299.411:0211:0553Z53LS53126.371298.611:0511:0854Z54LS54126.371299.011:0811:1155Z55LS55126.371298.81
8、1:1111:1456Z56LS56126.371299.111:1411:17拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂直度%开始时间结束时间43Z43LS43126.371299.010:2110:2444Z44LS44126.371299.210:2410:2745Z45LS45126.371299.410:2710:3046Z46LS46126.371299.210:3010:3347Z47LS47126.371299.110:3310:3648Z4
9、8LS48126.371298.710:3610:3949Z49LS49126.371299.210:3910:4250Z50LS50126.371298.810:4210:4551Z51LS51126.371299.110:4510:4852Z52LS52126.371299.411:0211:0553Z53LS53126.371298.611:0511:0854Z54LS54126.371299.011:0811:1155Z55LS55126.371298.811:1111:1456Z56LS56126.371299.111:1411:17拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压
10、机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂直度%开始时间结束时间43Z43LS43126.371299.010:2110:2444Z44LS44126.371299.210:2410:2745Z45LS45126.371299.410:2710:3046Z46LS46126.371299.210:3010:3347Z47LS47126.371299.110:3310:3648Z48LS48126.371298.710:3610:3949Z49LS49126.371299.210:3910:4250Z50LS
11、50126.371298.810:4210:4551Z51LS51126.371299.110:4510:4852Z52LS52126.371299.411:0211:0553Z53LS53126.371298.611:0511:0854Z54LS54126.371299.011:0811:1155Z55LS55126.371298.811:1111:1456Z56LS56126.371299.111:1411:17拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂
12、直度%开始时间结束时间43Z43LS43126.371299.010:2110:2444Z44LS44126.371299.210:2410:2745Z45LS45126.371299.410:2710:3046Z46LS46126.371299.210:3010:3347Z47LS47126.371299.110:3310:3648Z48LS48126.371298.710:3610:3949Z49LS49126.371299.210:3910:4250Z50LS50126.371298.810:4210:4551Z51LS51126.371299.110:4510:4852Z52LS521
13、26.371299.411:0211:0553Z53LS53126.371298.611:0511:0854Z54LS54126.371299.011:0811:1155Z55LS55126.371298.811:1111:1456Z56LS56126.371299.111:1411:17拉森钢板桩施工记录表工程名称工程部位拉森钢板桩静压机型号施工单位 场地地面 标高(m)6.37序号桩位编号拉森钢板桩插拉森钢板桩备注拉森钢板桩编号尺寸(m)顶标高(m)长度(m)垂直度%开始时间结束时间43Z43LS43126.371299.010:2110:2444Z44LS44126.371299.210
14、:2410:2745Z45LS45126.371299.410:2710:3046Z46LS46126.371299.210:3010:3347Z47LS47126.371299.110:3310:3648Z48LS48126.371298.710:3610:3949Z49LS49126.371299.210:3910:4250Z50LS50126.371298.810:4210:4551Z51LS51126.371299.110:4510:4852Z52LS52126.371299.411:0211:0553Z53LS53126.371298.611:0511:0854Z54LS54126.371299.011:0811:1155Z55LS55126.371298.811:1111:1456Z56LS56126.371299.111:1411:17