1、施工高峰期用电设备负荷统计表一、长期或短时工作制用电设备容量计算(Pjs=KxPe;Qjs=Pjstg)二、反复短时工作制用电设备组设备容量计算(Pjs=SenKxCOS;Qjs=Pjstg)序号用电设备型号设备容量(kW)设备数量(台)需用系数(Kx)功率因数cos计 算 负 荷有功功率Pjs(kW)无功功率Qjs(Kvar)1塔吊C60135390.500.65155.03181.222施工电梯SC200/200TD(暂定)4490.600.65154.44180.543高压水泵扬程160M30110.50.8132.0099.004钢筋弯曲机GW40380.50.89.607.205钢筋
2、切断机GQ401180.50.835.2026.406钢筋调直机JK-3T1140.50.817.6013.207套丝机Y11ZM-4-WD-X440.50.86.404.808木工平刨床MB504B320.50.82.401.809手电锯0.35100.50.81.401.0510混凝土振动器ZX701.160.50.82.641.9811平板振动器1.120.50.80.880.6612潜水泵(降水)11100.60.852.8039.6013冲击钻TE151.230.50.81.441.0814两用冲击钻12120.50.80.800.6015台钻160.3810.50.80.150.1
3、116手电钻日立0.520.50.80.400.3017机电加工设备机电工程用10010.50.840.0030.0018砂浆搅拌机UJZ-25011100.50.844.0033.0019电焊机ZX7-400C16150.50.874.3055.7320二氧化碳气体保护焊机OTC-60036180.50.8200.62150.4721空压机YJ600WS3.350.50.86.604.9522熔焊栓钉机SS-2508020.50.849.5437.1523生活区、办公区空调、风扇项12024现场照明66备注经查表,Cos为0.65,tg约1.169;当Cos为0.80,tg约0.75;当Cos为0.50,tg约1.732;当Cos为0.55,tg约1.519。经计算:Pjs= K1 KxPjs= 988.24 (KW)Qjs= K1 KjsPjs tg= 870.84(Kvar) Sjs = 1317(KVA)现场照明取施工用电的5%,则本工程主体阶段施工高峰期用电总容量为:1317+120+66=1503 KVA。而目前,业主在整个现场设两个变压器可提供(630+630)KVA80%=1008KVA。1503(630+630)0.8=1008因此,施工高峰期现场提供的变压器满足不了施工要求,需要再增加一台630KVA的变压器。