个人中心
个人中心
添加客服WX
客服
添加客服WX
添加客服WX
关注微信公众号
公众号
关注微信公众号
关注微信公众号
升级会员
升级会员
返回顶部
ImageVerifierCode 换一换

顶管法施工方案英文版(5页).docx

  • 资源ID:487016       资源大小:68.09KB        全文页数:5页
  • 资源格式:  DOCX         下载积分: 10金币
下载报告请您先登录!


友情提示
2、PDF文件下载后,可能会被浏览器默认打开,此种情况可以点击浏览器菜单,保存网页到桌面,就可以正常下载了。
3、本站不支持迅雷下载,请使用电脑自带的IE浏览器,或者360浏览器、谷歌浏览器下载即可。
4、本站资源下载后的文档和图纸-无水印,预览文档经过压缩,下载后原文更清晰。
5、试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓。

顶管法施工方案英文版(5页).docx

1、.Method Statement for Pipe Jacking1. Construction of PitsThe jacking pit with a dimension of 6mx5 clear opening with depth of 250mm below invert level of the steel pipe.The floor will be leveled by 100mm thick concrete blinding fixing tow I beams(1.5mx15cm) in the center of the pit for fixing jackin

2、g frame.2. Installation of Jacking FrameAfter the construction of drive, the jacking rig will be lowered into the pit and adjust to the control line and level. The rig will be used on this contract consist of two number of hydraulic cylinders with a capacity of 150 ton each to give a total jacking f

3、orce of 300 tons. The rig will have guided rails, pushing plate and base plate to hydraulic power back with control unit. The hydraulic system will run through a diesel engine installed the top of the pit.The rig will installed to the correct line and level and check by the consultant in respect to

4、level and alignment.3. Thrust WallConstructing a concrete block behind the base plate of the rig to a dimension of 2x1.5x0.5m will be provided to take and distribute the jacking load.4. Pipe Jacking OperationA steel shield is used at the front of the pipe to accommodate the.miner and to allow for st

5、eering of the pipe jack. The soil within the shield is manually excavated and loaded into a wheel skip for transport to the pit bottom. The miner does not dig outside the shield (both in front and radically) and the front, or cutting edge, of the shield is always kept buried in the face, so stabilit

6、y is maintained. The shield is thus used to trim the excavation to the size of the pipe thus minimizing the potential for settlement of the ground above the pipe jack.In the pit bottom, the skip is hoisted to the surface, emptied and returned to the used to loosen it prior to digging. The exact diam

7、eter of shield will be selected to suit the pushing pipes.As excavation continues, the shield is jacking forward using two hydraulic jacks thrusting from the back wall. When the shield is buried, the jacks are retracted and the first sleeve pipe lowered on to the rails. This in then pushed up to the

8、 shield and excavation can then continue. When the sleeve pipe is pushed home, the hydraulic jacks are retracted and the services (lighting& ventilation) disconnected. The next sleeve pipe is lowered on to the rails and the services reconnected and the cycle repeated until the shield is pushed into

9、the receiving pit and the pipeline pushed into final position.5. Maintaining Line and LevelIn order to maintain the correct line and level, a graduated target plate.is located within the shield. The site engineer notes the position of the visible sport on the target, this initial position is used as

10、 reference value to locate the relative position of the shield at all times during the drive. At each push, the site engineer monitors the position reference value with the help of level instrument and theodalite, thus giving a shield position (high or low, right or left) relative to the design posi

11、tion. Based on this information, the operator manipulates a correct course.Extending or retracting a combination of steering rams causing the front of the shield to articulate in the required direction carries out the steering. As the pipe follows the shield, the correct line and level will be maint

12、ained. At all times, the amount steering applied is kept to minimum.6. Fixing Carrier PipesAfter completion of the pipe jacking , we check the line and level for the steel pipe and we take the exact line and level for the carrier pipe with the help of survey instruments.A 3 steel anglebar fixed by w

13、elding in the correct bottom level of the carrier pipe, then 3mm thick flat bar half moon claps will fixed through wielding in the correct line after that we put neoprene rubber 3mm thick in the clamp to avoid the scratches of the carrier pipes.Then we start laying the carrier pipe one by one and fi

14、x the clamps.through nuts and bolts. After fixing the nuts and bolts we make angle support in between the top of the clamp and top of the pipe. Then we fix the other pipe in the same manner. The same procedure will continues up to the requirement.7. GroutingUpon completion of pipe jacking we make 4

15、2 holes like ventilationin every meter, it helps the concrete fill the gap between the steel pipeand ground. Then we fixed six inch grouting pipe vertically one meterheight in the top of the pipe both end jacking and receiving. One sidewillkeep ventilation and the otherside forconnection andtheconcr

16、ete pump.Afterthat we lay the carrier pipe inthe correct line and levelthencheck with the consultant and make the test required fromtheconsultant then we close the both end between steel and carrier pipe by m/s plate welding or masonry, the gap between steel sleeve and ground in the both end we close by cement.During grouting the grout will push through the down string end. Pumping process will continue till the grout reaches the up string end ventilation pipe. When the grout will overflow from the ventilation pipe, grouting process is completed.


注意事项

本文(顶管法施工方案英文版(5页).docx)为本站会员(正***)主动上传,地产文库仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。 若此文所含内容侵犯了您的版权或隐私,请立即通知地产文库(点击联系客服),我们立即给予删除!