防静电环氧地坪施工方案(8页).doc

1、防静电环氧地坪施工Anti-static Epoxy Self-leveling system抗静电环氧自流平地面The proposal :3mm Anti-static Epoxy Self-leveling system方案: 3mm抗静电环氧自流平地面Sikafloor 239EDF Antistatic epoxy self-leveling system抗静电环氧自流平系统Approx. 3 mm coating thickness涂装厚度约 3 mmSikafloor 239EDF is a seamless, self-smoothing, flooring system ba

2、sed on advanced solvent-free epoxy system and selected graded fillers. The cured floor exhibits excellent electrostatically dissipative behavior. The smooth, impervious surface can be easily maintained in a hygienic condition.Sikafloor 239EDF 是一种无接缝、自流平环氧系统,它以一种先进的无溶剂环氧树脂为基料,并采用专门级配的填充料。该地面具有优异的防静电性

3、能,其表面形成光滑的无渗透的地面,易于保持卫生状态。Performance 性能: Electrostatically dissipative (Resistance to ground 106RG109 Ohm) 防静电性能(106RG109欧姆) High level of aesthetics and easy to clean 高度美观,易清洗 Comfort and care 舒适,安全 Smooth and seamless 光滑,无缝Structure Profile 系统结构图:防静电面层Anti-static Top-coat导电层Conductive Layer找平层 Le

4、vel ayer底漆Primer混凝土ConcreteSystem Description 系统介绍:Step步骤Product & Consumption产品和用量Application Method施工方法Surface Preparation:基层处理Cleaning, grinding and shot blasting清理,研磨和喷砂处理Primer:底漆Sikafloor 161+石英砂 0.3-0.4 kg/m2 Trowel,roller刮板,滚筒Epoxy Leveling mortar环氧找平层Sikafloor 161 0.9 kg/ m2+适量石英砂 0.9kg/m2T

5、rowel刮板Conductive Copper Tape导电铜带Adhibit粘贴Conductive Layer导电层Sikafloor 220W 0.1 kg/m2Roller滚筒Top-coat面层Sikafloor 239EDF 1.8 kg/m2+SikaDur 505 0.6 kg/m2Trowel刮板Material Description材料说明:Sikafloor 161 is a 2 component epoxy resin based, solvent free primer. Sikafloor 161 是一种双组分环氧树脂基无溶剂型底油Sikafloor 220W

6、 is a two part water dispersed, epoxy resin with high electrostatic conductivity是一种双组分水性环氧树脂,具有较高的导电性能。Sikafloor 239EDF is a two part, self-smoothing, coloured epoxy resin coating.Decorative and protective dissipative self-smoothing system for concrete or cement screeds with normal up to medium heav

7、y wear.Sikafloor 239EDF 是双组份的彩色的环氧树脂,作为一种在混凝土表面和水泥地面导静电,装饰和保护的涂层 Sikadur 505Q is a dried fine quartz aggregate, 0.1 -0.3 mm for filling self-leveling floors and as filler in Sikafloor 156/263/264 as leveling mortar or scrape layer.Sikadur 505Q是一种干燥细颗粒骨料,0.1 - 0.3 mm ,用于填充自流平地面及用作Sikafloor161/263/264

8、自流平砂浆或刮磨层的腻子层。Thinner DS or Thinner C is a solvent for cleaning purpose.Thinner DS or Thinner C 是用于清洁的溶剂Application Method 施工工艺Inspection Substrate Quality 基面质量检查The concrete substrate must be sound and of sufficient compressive strength (minimum 25 N/mm2) with a minimum pull off strength of 1.5 N/m

9、m2.混凝土基面必须密实和有足够的抗压强度(最小25 N/mm2),最小抗拉强度为1.5 N/mm2。Substrate needs to be dry, moisture content 4%. Test method: Sika-Tramex meter or CM - measurement. A waterproofing layer must be installed under the concrete base,or vapor going up will result in epoxy layer bubbling and delamination. 2 mm Sikafloo

10、r 81 EpoCem system need to be applied as a moisture barrier.基层须干燥,含水率4%,测试方法:Sika-Tramex仪或CM测量法。混凝土基层下须设置防水层,否则存在水汽上升导致环氧层起泡、脱落风险。建议施工2mm Sikalfoor 81 EpoCem系统作为防潮层。The substrate must be clean and free of all contaminants such as dirt, oil, grease, coatings and surface treatments, etc.基面必须清洁、无任何污染物,

11、如:灰尘、油、油脂、涂层和表面处理等。Measure Application Conditions 施工条件测量Substrate Temperature: +10 min. / +30 max.基面温度:最低+10/最高+30Ambient Temperature +10 min. / +30 max.环境温度:最低+10/最高+30Relative Air Humidity: 80% R.H. max.相对空气湿度:最高80%相对湿度Dew Point: The substrate and uncured floor must be at least 3 above dew point t

12、o reduce the risk of condensation or blooming on the floor finish.露点:基面和未固化的地面温度必须至少高于露点3,以防水汽凝结形成斑点。Substrate Preparation 基面处理re-clean the floor surface, degrease agent will be used where necessary.清洁地表,必要时使用清洁剂;Carry out surface preparation by using shot blasting machine (dust free self enclosed s

13、teel shot blasting unit) and hand tools to remove surface laitance and to provide sound and textured surface.使用自动无尘喷砂设备和手动工具进行表面预处理,去除混凝土表面翻沫及松散结构,并提供涂装所需的必要的粗糙度;Remove all remaining dust and debris by dry brushing and vacuum cleaning.扫除残留的钢丸及灰尘,并真空吸尘;Repair all floor defects such as honey combs, sc

14、ratches, working joints and so on by using SikaDur and Sikaflex range of materials. .使用SikaDur 与Sikaflex等系列产品对地面缺陷如蜂窝麻面、划痕、施工缝等进行修补;Mixing of material 材料混合:In general, all products must be mechanically mixed using an electrical power stirrer with 300 400 rpm, prior to mixing stir part A mechanically

15、. When all of part B has been added to part A, continuously mix for 2 minutes until a uniform mix has been achieved. Depending on the product ad in the filler or C component and mix for another 2 minutes until a uniform mix has been achieved.通常,在机械搅拌A组分之前,所有产品必须用电动搅拌器以300 400 转速/分机械搅拌。把所有B组分加入A组分之后,

16、持续混合2 分钟直到混合均匀。根据产品加入填料或C组分,继续搅拌两分钟直到混合均匀。To ensure thorough mixing, pour materials into another container and mix again to achieve a consistent mix. Over mixing must be avoided to minimize air entrapment.保证通过混合、倾倒材料进入另一容器后,再次搅拌达到一致混合。需要避免过度搅拌产生气泡Application of Primer and Leveling layer 底油与找平层施工:App

17、lication of Sikafloor 161, consumption approx. 0.4 kg/m for primer;consumption approx. 0.9 kg/m Sikafloor 161 mixed with 0.45kg/m2 quartz sand.Sikafloor 161 用量大约0.4 kg/m;底油固化后,施工环氧砂浆层 ,2.7kg/m2 Sikafloor 161混合2.7kg/m2石英砂.Application of Conductive Copper Tape 导电铜带施工Placing Earthing Points 设置接地点Applic

18、ation of Conductive layer 导电层施工Apply with a layer of Sikafloor 220W, consumption approx. 0.1 kg/m.施工一层Sikafloor 220W, 每层用量大约0.1 kg/m, Checking and Measuring of Resistance 导电层电阻检测Application of anti-static Top layer 防静电面层施工After curing of the conductive layer, application of a layer Sikafloor 239EDF

19、with a trowel; consumption approx. 1.8 kg/m Sikafloor 239EDF mixed with 0.6kg/m2 quartz sand.导电层固化后,用刮板施工Sikafloor 239EDF; 1.8kg/m2 混合0.6kg/m2石英砂;Also apply with a spike rolling for deairing and levelling.用齿状刮刀施工并立即用带钉的滚筒排气找平。After application, clean the application tools with Thinner DS.施工结束后用Thinner DS 清洗工具Curing Details 养护细则Temperature 温度Foot traffic 可步行Light traffic 轻度荷载Full cure 完全固化+1030 hours5 days10 days+2024 hours3 days7 days+3016 hours2 days5 daysNote: Times are approximate and will be affected by changing ambient conditions.备注:以上时间为约值,并会随周边环境变化有所改变。